Rooppur unit 1 progressesing though commissioning tests

Tuesday, 5 August 2025

A blowdown of the fresh steam pipelines in the turbine compartment has been completed at the first unit of the Rooppur nuclear power plant being built in Bangladesh.

Rooppur unit 1 progressesing though commissioning tests
(Image: Rosatom)

The blowdown was carried out using fresh steam under 2.0 MPa pressure at 200 degrees Celsius. Rosatom described it as one of the key stages of cold and hot functional tests during the commissioning process and shows the readiness of the unit’s steam lines to supply steam to the turbine.

The tests, during which the steam was discharged into the atmosphere, clean the pipelines and “will be followed by the repeated blowdown of the steam pipelines with an increased volume of fresh steam which will allow for the final cleaning of the main lines and specify the equipment operating parameters under a near-operational load”.

Hot testing of the unit began last month and it is designed as a general check of the reliability of the reactor unit “before moving on to the next, more important stages … and shows where the system is ready to function under conditions close to real operation”.

Atomstroyexport, part of Rosatom, explained last month that “during the tests, the reactor unit is heated up, and our specialists check step-by-step how key elements operate under these conditions: pumps, pipelines, heat exchange equipment. It is important to record how the equipment behaves under load – after all, it will be the one that will ensure reliable operation of the plant later”.

Leak tests on the containment building for Rooppur 1 were successfully completed in June.

Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh, said: “With the completion of this stage of commissioning works, the Rooppur NPP takes another step towards the pivotal event, such as launching of power unit No 1 and its subsequent connection to the power grid, which will supply the country’s residents with additional energy, vital for both the economy and industry. In the future, the Rooppur NPP built according to the latest Russian VVER-1200 design, is expected to supply Bangladesh with up to 10% of clean energy for decades to come.”

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    • April 10, 2026
    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates

    • April 10, 2026
    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates