Rosatom continuing work for Iran’s Bushehr units 2 and 3

Russia’s state nuclear corporation was also ready to send its specialists back to Iran as soon as it was clear there was no threat of renewed military conflcit, Likhachev told reporters.

According to the corporation’s in-house news magazine Strana Rosatom, Likhachev said there were 20 Rosatom staff at the construction site, and four more in the central office in Iran’s capital, Tehran.

“About 2,200 employees of Iranian contractors have already returned to the construction site. The main work is focused on reinforcing and concreting unit 2, which is under construction. The number of Iranian workers continues to grow,” said Likhachev.

After giving the update on progress with the reactor and steam generators, he said “we plan to begin shipping key equipment next year. We are continuing casting and forging metallurgical blanks for the equipment for unit 3”.


An aerial mage of unit 2, shared by the Atomic Energy Organisation of Iran in January (Image: AEOI)


Another view of unit 2, shared by AEOI in January (Image: AEOI)

According to a report by the official Tass news agency, he said “the project remains a priority for us. Rosatom’s enterprises continue to manufacture equipment for the Bushehr Nuclear Power Plant as planned”. The agency also reported him as saying that unit 1 at the plant continues to work at 100% capacity.

Background

The USA and Israel launched attacks on Iran on 28 February, saying they were targeting Iran’s leadership and its military infrastructure. Iran has retaliated – there is currently a ceasefire and talks taking place aimed at ending the conflict. International Atomic Energy Agency (IAEA)  Director General Rafael Mariano Grossi has said that diplomacy and negotiations are the way “to achieve the long-term assurance that Iran will not acquire nuclear weapons and for maintaining the continued effectiveness of the global non-proliferation regime”.

The first unit at the Bushehr plant was connected to the grid in 2011. It is a Russian-designed VVER unit with a capacity of 915 MWe. Two further units featuring VVER-1000 units are under construction – unit 2 had first concrete poured in 2019 and the core catcher installed in 2024. In January the third tier of the inner containment building for unit 2 was installed.

At an event at the IAEA’s General Conference in September 2024, Iran suggested unit 2’s then target date for operation was 2029. According to Russia’s Rosatom, unit 3 is also under construction.

In September 2025, Rosatom and the Atomic Energy Organisation of Iran signed a memorandum of understanding for cooperation in the building of small modular reactors in Iran. The country says it has an ambition for 20 GW of nuclear energy capacity by 2041.

   

  • Related Posts

    Ceremony marks start of work at Canadian uranium project

    Denison’s Board of Directors made its final investment decision in February, after receiving final federal regulatory approvals for the start of construction from the Canadian Nuclear Safety Commission. Provincial-level approvals…

    Studsvik seeks state support for SMRs in Sweden

    The application was formally handed over to the Minister for Financial Markets Niklas Wykman on Friday. Studsvik, which acquired Kärnfull Next and its ReFirm programme earlier this year, is developing potential small…

    Have You Seen?

    Nigeria’s Crude Oil Production Hits 15-Month High

    • June 13, 2026
    Nigeria’s Crude Oil Production Hits 15-Month High

    Oil Falls to Lowest Since March on Expected Peace Deal

    • June 13, 2026
    Oil Falls to Lowest Since March on Expected Peace Deal

    Just 6 Days to Go: Solar & Storage Expo Odisha 2026 Set to Accelerate the State’s Clean Energy Journey  

    • June 13, 2026
    Just 6 Days to Go: Solar & Storage Expo Odisha 2026 Set to Accelerate the State’s Clean Energy Journey  

    Ormat Technologies Launches Ormega100, A 100MW Surface Power Unit Designed For Enhanced Geothermal Systems

    • June 13, 2026
    Ormat Technologies Launches Ormega100, A 100MW Surface Power Unit Designed For Enhanced Geothermal Systems

    ACCIONA Energía Announces New 980MWh Battery Storage Project At El Romero Solar Plant In Chile

    • June 13, 2026
    ACCIONA Energía Announces New 980MWh Battery Storage Project At El Romero Solar Plant In Chile

    Solaria Secures EUR 41 Million in Grants for Agrivoltaic and Battery Storage Projects in Spain

    • June 13, 2026
    Solaria Secures EUR 41 Million in Grants for Agrivoltaic and Battery Storage Projects in Spain

    GreenYellow to Install 38 MWp of Solar Capacity for Carrefour Brazil

    • June 13, 2026
    GreenYellow to Install 38 MWp of Solar Capacity for Carrefour Brazil

    Shell Pauses $3 Billion Share Buyback Ahead of ARC Acquisition Vote

    • June 13, 2026
    Shell Pauses $3 Billion Share Buyback Ahead of ARC Acquisition Vote

    US LNG Exporters Find Few Takers in Europe for New Supply

    • June 13, 2026
    US LNG Exporters Find Few Takers in Europe for New Supply

    Trump Says Iran’s Leaked Deal Terms are Untrue

    • June 12, 2026
    Trump Says Iran’s Leaked Deal Terms are Untrue