Second tier installed for Leningrad inner containment building

The new phase of the plant – known as Leningrad II – features two VVER-1200 units, commissioned in 2018 and 2021 respectively, with a third and fourth new unit currently under construction. Together, they will replace the four RBMK-1000 units from the original 1970s phase of the Leningrad nuclear power plant.

There are currently 1,500 people from the general contractor, Titan-2 Holding, working on the construction site for the two units – Leningrad II’s units 3 and 4, or the seventh and eighth units if the older four units are included.

Rosatom said that there is considerable work still ahead on the already installed tiers, and the tiers yet to be installed – including reinforcement and concreting and installation of the prestressing system.


(Image: Rosatom)

VVER-1200 reactors have two containment buildings – an inner one and an outer one – which provide extra safety and protection from external impacts. Both containments are being worked on – the aim is for this new unit’s double containment shell to be ready in 2028.

Rosatom Director General Alexei Likhachev attended the event and said: “The Northwest region of our country is traditionally energy-intensive, with industrial and port infrastructure actively developing here. Two of our nuclear power plants operate in the region – the Leningrad and Kola Nuclear Power Plants – with a combined capacity of over 6,000 MW. Together, they provide over 35% of the region’s electricity generation. Both plants have been operating for over 50 years, and each is currently receiving a second lease of life – replacement capacity that will last for at least another 60 years.”


The inner and outer containments are being built simultaneously (Image: Rosatom)

Regional Governor, Alexander Drozdenko, said: “Today, we have confirmed that construction of the replacement capacity at the Leningrad Nuclear Power Plant is proceeding at a good pace. We are confident that the new power units will be commissioned on schedule and will guarantee electricity for millions of our households and hundreds of industries, as well as healthcare, cultural, and sports institutions.”

Background

The Leningrad nuclear power plant is one of the largest in Russia, with an installed capacity of 4,400 MWe, and provides more than 55% of the electricity demand of St Petersburg and the Leningrad region, or 30% of all the electricity in northwest Russia.

Leningrad 1 shut down in 2018 after 45 years of operation. Leningrad 2, also a 1,000 MWe RBMK unit, started up in 1975 and was permanently shut down in November 2020. As the first two of the plant’s four RBMK-1000 units shut down, new VVER-1200 units started up at the neighbouring Leningrad II plant. The 60-year service life of these fifth and sixth units (also known as Leningrad II-1 and Leningrad II-2) secures power supply until the 2080s. Units 7 and 8 (also known as Leningrad II-3 and Leningrad II-4) will replace units 3 and 4 as they are shut in the coming years.

The pouring of the first concrete for unit 7 in March 2024 marked the start of the main phase of construction of the new power unit, which is expected to generate power for 60 years, with the possibility of a 20-year extension. First concrete was poured for the eighth unit in March 2025.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Diversifying helium: Can dedicated projects reshape global supply?

    • August 17, 2026
    Diversifying helium: Can dedicated projects reshape global supply?

    How Phoenix is capitalizing on the Southwest’s opportunity

    • August 17, 2026
    How Phoenix is capitalizing on the Southwest’s opportunity

    India Daily: SECI Seeks Inputs for RE PMU, UPERC Rejects UPRVUNL Solar Petition, Adani Acquires Vizag Transmission SPV, KERC Drafts 2026 Supply Rules, Telangana Eyes 2,545 MW Solar and More…

    • August 17, 2026
    India Daily: SECI Seeks Inputs for RE PMU, UPERC Rejects UPRVUNL Solar Petition, Adani Acquires Vizag Transmission SPV, KERC Drafts 2026 Supply Rules, Telangana Eyes 2,545 MW Solar and More…

    How ReNew Is Advancing Its Net-Zero and Sustainability Roadmap: Key Takeaways From Its FY2025–26 Integrated Report

    • August 17, 2026
    How ReNew Is Advancing Its Net-Zero and Sustainability Roadmap: Key Takeaways From Its FY2025–26 Integrated Report

    CATL Achieves Carbon Neutrality Across Core Operations, Targets Full Value Chain by 2035

    • August 17, 2026
    CATL Achieves Carbon Neutrality Across Core Operations, Targets Full Value Chain by 2035

    Why Has Oil Not Rallied to $150 or Higher?

    • August 17, 2026
    Why Has Oil Not Rallied to $150 or Higher?

    Türkiye And Saudi Arabia Expand Renewable Energy Partnership To 5,000 MW

    • August 17, 2026
    Türkiye And Saudi Arabia Expand Renewable Energy Partnership To 5,000 MW

    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    • August 17, 2026
    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    • August 17, 2026
    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    Shell Energy Philippines Advances 30 MW/60 MWh Hermosa Battery Storage Project

    • August 17, 2026
    Shell Energy Philippines Advances 30 MW/60 MWh Hermosa Battery Storage Project