Start-up work under way for Akkuyu pumping station

Monday, 3 February 2025

Start-up work under way for Akkuyu pumping station
Akkuyu is to be Turkey’s first nuclear power plant (Image: Rosatom)

The pumping units for the main cooling water supply and pumps connected to the back-up diesel power supply are now undergoing load tests, with operating parameters of the equipment being checked, following test runs of the main cooling water pumping units.

The four-unit Akkuyu nuclear plant will be cooled by water from the Mediterranean Sea. There will be one pumping station for each power unit, a drainage channel, siphon wells, a distribution chamber, a water intake and spillway structure and desalination processes. Rosatom says the total capacity in the normal operation of the power unit will be 260,000 cubic metres per hour and that the design “will reliably protect the pumping station equipment from any external factors including floods and tsunamis”.

Akkuyu Nuclear JSC CEO Sergei Butckikh said: “Construction and installation works at the pumping station are almost completed … the nuclear power plant’s largest pumps … will provide water to all the cooling systems of the power unit, that is why stable operation of the pumps is extremely important for the reliable operation of the main equipment, including the reactor plant and the turbine unit. The onshore pumping station is a unique hydraulic engineering structure. The station’s design solution, developed taking into account the advanced safety standards, was successfully implemented thanks to the well-coordinated work of the Turkish-Russian team of designers and builders.”

Background
 

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December, and in February it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system in 2025. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs, with the aim that all four units will be operational by the end of 2028.

   

  • Related Posts

    Podcast: Canada’s leading role in life-saving medical isotopes

    Tuesday, 25 March 2025 He outlines the life-saving diagnostics and treatments that now exist thanks to isotopes produced in Canada’s Candu reactors, research reactors and cyclotrons, and talks about the…

    ExLabs, Antares to develop nuclear-powered spacecraft

    Tuesday, 25 March 2025 (Image: ExLabs) Through the partnership, Antares’ microreactor technology will be integrated into ExLabs’ Science Exploration and Resource Vehicle (SERV), establishing a high-power spacecraft platform for Geostationary…

    Have You Seen?

    China’s Purchases Stall After Trump’s Tariff Threat on Buyers of Venezuelan Oil

    • March 25, 2025
    China’s Purchases Stall After Trump’s Tariff Threat on Buyers of Venezuelan Oil

    COMMENTARY: Solar and Wind Power Are Expensive – Fraser Insitute

    • March 25, 2025
    COMMENTARY: Solar and Wind Power Are Expensive – Fraser Insitute

    Shell Vows to Raise Investor Returns as It Bets Big on LNG

    • March 25, 2025
    Shell Vows to Raise Investor Returns as It Bets Big on LNG

    Shell Traders Haven’t Lost Money in Any Quarter Over Last Decade

    • March 25, 2025
    Shell Traders Haven’t Lost Money in Any Quarter Over Last Decade

    US Army Corps to Narrow List of Emergency Energy Projects by Next Week

    • March 25, 2025
    US Army Corps to Narrow List of Emergency Energy Projects by Next Week

    Alaska Seeks South Korean Investors for Its $44-Billion LNG Project

    • March 25, 2025
    Alaska Seeks South Korean Investors for Its $44-Billion LNG Project

    India’s Peak Electricity Demand Set to Jump By 10% in 2025

    • March 25, 2025
    India’s Peak Electricity Demand Set to Jump By 10% in 2025

    Biggest Indian Oil Producer Seeks to Diversify to Withstand Supply Glut

    • March 25, 2025
    Biggest Indian Oil Producer Seeks to Diversify to Withstand Supply Glut

    Shell Flags Uncertain Outcome of $1.6-Billion Russian Court Claim

    • March 25, 2025
    Shell Flags Uncertain Outcome of $1.6-Billion Russian Court Claim

    Analyst Says NatGas Bulls Attempting to ‘Hold Line’ Ahead of April Rollover

    • March 25, 2025
    Analyst Says NatGas Bulls Attempting to ‘Hold Line’ Ahead of April Rollover