Start-up work under way for Akkuyu pumping station

Monday, 3 February 2025

Start-up work under way for Akkuyu pumping station
Akkuyu is to be Turkey’s first nuclear power plant (Image: Rosatom)

The pumping units for the main cooling water supply and pumps connected to the back-up diesel power supply are now undergoing load tests, with operating parameters of the equipment being checked, following test runs of the main cooling water pumping units.

The four-unit Akkuyu nuclear plant will be cooled by water from the Mediterranean Sea. There will be one pumping station for each power unit, a drainage channel, siphon wells, a distribution chamber, a water intake and spillway structure and desalination processes. Rosatom says the total capacity in the normal operation of the power unit will be 260,000 cubic metres per hour and that the design “will reliably protect the pumping station equipment from any external factors including floods and tsunamis”.

Akkuyu Nuclear JSC CEO Sergei Butckikh said: “Construction and installation works at the pumping station are almost completed … the nuclear power plant’s largest pumps … will provide water to all the cooling systems of the power unit, that is why stable operation of the pumps is extremely important for the reliable operation of the main equipment, including the reactor plant and the turbine unit. The onshore pumping station is a unique hydraulic engineering structure. The station’s design solution, developed taking into account the advanced safety standards, was successfully implemented thanks to the well-coordinated work of the Turkish-Russian team of designers and builders.”

Background
 

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December, and in February it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system in 2025. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs, with the aim that all four units will be operational by the end of 2028.

   

  • Related Posts

    Global nuclear M&A deals ‘double to USD7 billion’

    The firm says that the number of deals increased by 10%, from 40 to 44, and says that “at the current pace of dealmaking activity, 2026 is set to surpass…

    Economic assessment filed for Swedish uranium project as law comes into force

    The Canadian company first announced the results of its assessment in early June, envisioning a conventional open-pit mining and processing operation with average annual production of 3.3 million pounds U3O8…

    Have You Seen?

    Goldman Warns Oil Could Hit $120 as Middle East War Drags On

    • July 21, 2026
    Goldman Warns Oil Could Hit $120 as Middle East War Drags On

    Oil Reverses Gains on Renewed Hope of Peace in Iran

    • July 21, 2026
    Oil Reverses Gains on Renewed Hope of Peace in Iran

    Iran Says U.S. Struck Unfinished Nuclear Plant, Warns of Safety Risk

    • July 21, 2026
    Iran Says U.S. Struck Unfinished Nuclear Plant, Warns of Safety Risk

    ADNOC Approves $6.2 Billion Gas Project in Abu Dhabi

    • July 21, 2026
    ADNOC Approves $6.2 Billion Gas Project in Abu Dhabi

    Pakistan Shells Out Record Sums for Spot LNG as Qatar Supply Falters

    • July 21, 2026
    Pakistan Shells Out Record Sums for Spot LNG as Qatar Supply Falters

    India Keeps Buying Russian Oil at Near-Record Pace Despite Expired Waiver

    • July 21, 2026
    India Keeps Buying Russian Oil at Near-Record Pace Despite Expired Waiver

    UK Scraps 5% VAT on Electricity

    • July 21, 2026
    UK Scraps 5% VAT on Electricity

    Ryanair Profit Falls 36% as Unhedged Jet Fuel Costs Double

    • July 21, 2026
    Ryanair Profit Falls 36% as Unhedged Jet Fuel Costs Double

    Oil Prices Top $90 as Kuwaiti Tanker Hit in Strait of Hormuz

    • July 21, 2026
    Oil Prices Top $90 as Kuwaiti Tanker Hit in Strait of Hormuz

    IMF Flags Higher Oil Price As Key Risk to India’s GDP Growth

    • July 21, 2026
    IMF Flags Higher Oil Price As Key Risk to India’s GDP Growth