UPNEDA Invites Bids For 110 MW Solar Projects In Kanpur Under Tariff-Based Competitive Bidding

Representational image. Credit: Canva

The Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) has released a Request for Selection (RfS) for selecting solar power developers (SPDs) to set up a 110 MW grid-connected solar PV power project in Uttar Pradesh. The project will be implemented in two locations—35 MW in Kanpur Nagar and 75 MW in Kanpur Dehat.

The tender process will follow a single-stage, two-envelope bidding system under tariff-based competitive bidding. The selected developer will supply power to the Uttar Pradesh Power Corporation Ltd. (UPPCL) for 25 years. The project must be implemented on a Build-Own-Operate-Maintain (BOOM) basis inside the designated solar parks being developed by the Lucknow Solar Power Development Corporation Ltd. (LSPDCL), a joint venture of UPNEDA and SECI.

The last date for bid submission is May 27, 2025, by 6:00 PM, and techno-commercial bids will be opened on May 28, 2025, at 12:30 PM. A pre-bid meeting is scheduled for May 14, 2025, at UPNEDA’s office in Lucknow and will be held in hybrid mode. The e-Reverse Auction (e-RA) date will be communicated later to the eligible bidders.

The non-refundable cost of the RfS document is ₹25,000 plus 18% GST, totaling ₹29,500. The document processing fee varies: ₹1 lakh plus 18% GST for a 35 MW capacity bid, and ₹3 lakh plus 18% GST for a 75 MW capacity bid. These amounts are to be submitted via NEFT/RTGS or in the form of a demand draft/pay order to UPNEDA.

As a financial security measure, an Earnest Money Deposit (EMD) of ₹8 lakh per MW is required, to be submitted through a bank guarantee. This means an EMD of ₹2.8 crore is required for the full 110 MW project. Additionally, the selected bidders must furnish a Performance Bank Guarantee (PBG) of ₹20 lakh per MW per project before signing the Power Purchase Agreement (PPA). For the full 110 MW capacity, the PBG totals ₹22 crore.

The Scheduled Commencement of Supply Date (SCSD) is defined as 24 months from the Effective Date of the PPA. If the supply is delayed beyond the SCSD, a maximum grace period of 6 months is allowed with daily penalties applied to the portion of capacity not yet supplying power. Failure to commence supply within this extended period will lead to termination of the PPA for the non-operational capacity.

Power purchase agreements must be signed within 30 days from the date of issuance of the Letter of Award (LoA). Early commissioning of the power supply before the SCSD is permitted, with advance notice, and UPPCL may accept early power at the PPA tariff.

This tender aligns with the Ministry of Power’s guidelines dated July 28, 2023, and its subsequent amendments. The entire bidding and communication process will be conducted through the ISN-ETS portal. UPNEDA holds the authority to cancel or amend the tender without assigning any reason. Interested bidders must adhere to all eligibility, technical, and financial conditions detailed in the RfS document.

 

  • Related Posts

    India Daily: NTPC REL Secures 500 MW, POWERGRID Tenders 265 MW BESS, RE Generation Crosses 38,497 MU, REC Transfers Luhri SPV, OREDA Tenders Rooftop Solar, POWERGRID Wins ₹822.91 Cr Project, KELTRON Tenders Solar Projects

    NTPC Renewable Energy Limited (NTPC REL), a wholly owned subsidiary of NTPC Green Energy Limited, has secured 500 MW under SECI’s FDRE-IX tender at a discovered tariff of ₹6/kWh. The…

    Cube Green Energy Appoints Dr Felix Grolman as Executive Chair to Drive European Renewable Energy Growth

    Cube Green Energy, an integrated renewable energy and battery storage platform, has appointed Dr Felix Grolman as Executive Chair, effective August 1, 2026, as the company advances the expansion of…

    Have You Seen?

    JPMorgan and Santander Lead $15 Billion Financing Push for Argentina LNG

    • August 25, 2026
    JPMorgan and Santander Lead $15 Billion Financing Push for Argentina LNG

    Japan Holds Off on New Oil Reserve Release Despite September Import Drop

    • August 25, 2026
    Japan Holds Off on New Oil Reserve Release Despite September Import Drop

    India’s Crude Import Bill Surges as Hormuz Shipping Rates Soar

    • August 25, 2026
    India’s Crude Import Bill Surges as Hormuz Shipping Rates Soar

    Malacca States Vow to Keep Asia’s Busiest Shipping Route Open

    • August 25, 2026
    Malacca States Vow to Keep Asia’s Busiest Shipping Route Open

    Equinor Eyes Major Oil Discovery Offshore Namibia

    • August 25, 2026
    Equinor Eyes Major Oil Discovery Offshore Namibia

    Japan’s Air Water buys 35% stake in Taiwan semiconductor gas supplier

    • August 25, 2026
    Japan’s Air Water buys 35% stake in Taiwan semiconductor gas supplier

    Japan’s Air Water takes 35% stake in Taiwan semiconductor gas supplier

    • August 25, 2026
    Japan’s Air Water takes 35% stake in Taiwan semiconductor gas supplier

    India Daily: NTPC REL Secures 500 MW, POWERGRID Tenders 265 MW BESS, RE Generation Crosses 38,497 MU, REC Transfers Luhri SPV, OREDA Tenders Rooftop Solar, POWERGRID Wins ₹822.91 Cr Project, KELTRON Tenders Solar Projects

    • August 25, 2026
    India Daily: NTPC REL Secures 500 MW, POWERGRID Tenders 265 MW BESS, RE Generation Crosses 38,497 MU, REC Transfers Luhri SPV, OREDA Tenders Rooftop Solar, POWERGRID Wins ₹822.91 Cr Project, KELTRON Tenders Solar Projects

    Equinor considers putting more wind into East Africa LNG sails

    • August 25, 2026
    Equinor considers putting more wind into East Africa LNG sails

    Cube Green Energy Appoints Dr Felix Grolman as Executive Chair to Drive European Renewable Energy Growth

    • August 25, 2026
    Cube Green Energy Appoints Dr Felix Grolman as Executive Chair to Drive European Renewable Energy Growth