APTEL Orders CESCOM To Pay ₹6.89/kWh Tariff And Refund Deductions In 50 MW Solar Project Case

Representational image. Credit: Canva

On May 30, 2025, the Appellate Tribunal for Electricity passed a significant order in Execution Petition No. 16 of 2021 filed by Azure Sunrise Private Limited. The company had approached the Tribunal seeking enforcement of its earlier judgment dated February 28, 2020, in Appeal No. 340 of 2016. Azure Sunrise is a special purpose vehicle of Azure Power India Private Limited, which signed a Power Purchase Agreement (PPA) on January 2, 2015, with Chamundeshwari Electricity Supply Corporation Limited (CESCOM) for a 50 MW solar project in Karnataka.

The dispute began when KREDL, the nodal agency, awarded the solar project to Azure’s parent company, and a PPA was signed between Azure Sunrise and CESCOM. However, both original copies of the PPA were retained by CESCOM for submission to the Karnataka Electricity Regulatory Commission (KERC) and only a scanned version was shared with Azure. Due to the delay in receiving the approved and effective PPA, which was eventually provided on May 21, 2015, the project was delayed by 137 days. Though CESCOM initially granted an extension for this delay, later they sought to reduce the applicable tariff from ₹6.89/kWh to ₹6.51/kWh and imposed penalties, citing KERC’s directions.

KERC, in its order dated December 14, 2016, not only upheld the reduced tariff but also limited the time extension to just 25 days instead of the initially approved 137 days. Azure Sunrise challenged this before the Tribunal, which in its 2020 judgment ruled in Azure’s favor. The Tribunal held that the reduction in time extension, lowering of tariff, and imposition of liquidated damages were not legally sustainable and should be set aside. Despite this clear judgment, CESCOM failed to make payments to Azure at the PPA tariff and continued paying at the lower interim rate of ₹4.36/kWh.

As CESCOM did not implement the judgment, Azure Sunrise filed the execution petition in 2021. It sought payment of ₹89.27 crore as the outstanding amount and ₹29.44 crore as interest, calculated at 1.25% per month, following the late payment surcharge provision in the PPA. Azure also sought a refund of all liquidated damages deducted earlier.

The Tribunal reiterated that the execution court cannot modify or go beyond the terms of the final judgment. It emphasized that CESCOM had neither challenged the 2020 judgment before the Supreme Court nor sought any review or clarification. The Tribunal noted with disapproval CESCOM’s conduct of non-compliance, misrepresentation, and failure to disclose facts during the execution proceedings. It stated that the continued underpayment and non-refund of damages constituted wilful disobedience of the Tribunal’s order.

The Tribunal concluded that Azure Sunrise’s request was well within the scope of the original judgment and deserved full enforcement. It directed CESCOM to pay the differential amount between ₹6.89/kWh and ₹4.36/kWh for all energy supplied from the project’s commissioning date until the effective realization date. CESCOM was also ordered to refund all liquidated damages along with interest and carrying costs within six weeks.

The Tribunal made it clear that if CESCOM failed to comply within the stipulated period, its bank accounts would be attached and the required amount would be recovered from them. With this, the execution petition and any related applications were disposed of.

 

  • Related Posts

    Morocco Launches 350 MW NOOR PV Multisites Solar Programme With November 30, 2026, Prequalification Deadline

    Morocco has launched a recruitment process inviting qualified contractors to participate in its NOOR PV Multisites programme, a large-scale solar power initiative aimed at expanding renewable electricity generation across the…

    HELLENiQ ENERGY Commissions 100 MW/200 MWh Battery Storage Park In Greece With €50 Million Investment

    HELLENiQ ENERGY has brought its first Battery Energy Storage System (BESS) into operation at its Thessaloniki Industrial Facilities in Greece, marking a significant step in the company’s strategy to expand…

    Have You Seen?

    U.S. Wants World Bank to Drop Ban on Upstream Oil and Gas Funding

    • October 15, 2026
    U.S. Wants World Bank to Drop Ban on Upstream Oil and Gas Funding

    Europe’s Gas Prices Close to 2022 High as Hormuz LNG Flows Remain Limited

    • October 15, 2026
    Europe’s Gas Prices Close to 2022 High as Hormuz LNG Flows Remain Limited

    India’s Annual Wind Power Installations to Double by 2030

    • October 15, 2026
    India’s Annual Wind Power Installations to Double by 2030

    Ship-to-Ship Oil Transfers Surge Off India’s West Coast

    • October 15, 2026
    Ship-to-Ship Oil Transfers Surge Off India’s West Coast

    Taiwan advances Alaska LNG deal as project funding remains uncertain

    • October 15, 2026
    Taiwan advances Alaska LNG deal as project funding remains uncertain

    Taiwan advances Alaska LNG deal as project funding remains uncertain

    • October 15, 2026
    Taiwan advances Alaska LNG deal as project funding remains uncertain

    White Paper: Determination and Measurement of Trace Impurities in Battery Off-Gas Using GC-ICP-MS

    • October 15, 2026
    White Paper: Determination and Measurement of Trace Impurities in Battery Off-Gas Using GC-ICP-MS

    Lithium Prices Plunge as EU-China Trade Deal Sparks Demand Fears

    • October 15, 2026
    Lithium Prices Plunge as EU-China Trade Deal Sparks Demand Fears

    IMF Warns of Worldwide Fallout as Attacks on Saudi Arabia Escalate

    • October 15, 2026
    IMF Warns of Worldwide Fallout as Attacks on Saudi Arabia Escalate

    Ukraine to Resume Russian Oil Refinery Strikes After Failed Energy Ceasefire

    • October 15, 2026
    Ukraine to Resume Russian Oil Refinery Strikes After Failed Energy Ceasefire