APTEL Orders CESCOM To Pay ₹6.89/kWh Tariff And Refund Deductions In 50 MW Solar Project Case

Representational image. Credit: Canva

On May 30, 2025, the Appellate Tribunal for Electricity passed a significant order in Execution Petition No. 16 of 2021 filed by Azure Sunrise Private Limited. The company had approached the Tribunal seeking enforcement of its earlier judgment dated February 28, 2020, in Appeal No. 340 of 2016. Azure Sunrise is a special purpose vehicle of Azure Power India Private Limited, which signed a Power Purchase Agreement (PPA) on January 2, 2015, with Chamundeshwari Electricity Supply Corporation Limited (CESCOM) for a 50 MW solar project in Karnataka.

The dispute began when KREDL, the nodal agency, awarded the solar project to Azure’s parent company, and a PPA was signed between Azure Sunrise and CESCOM. However, both original copies of the PPA were retained by CESCOM for submission to the Karnataka Electricity Regulatory Commission (KERC) and only a scanned version was shared with Azure. Due to the delay in receiving the approved and effective PPA, which was eventually provided on May 21, 2015, the project was delayed by 137 days. Though CESCOM initially granted an extension for this delay, later they sought to reduce the applicable tariff from ₹6.89/kWh to ₹6.51/kWh and imposed penalties, citing KERC’s directions.

KERC, in its order dated December 14, 2016, not only upheld the reduced tariff but also limited the time extension to just 25 days instead of the initially approved 137 days. Azure Sunrise challenged this before the Tribunal, which in its 2020 judgment ruled in Azure’s favor. The Tribunal held that the reduction in time extension, lowering of tariff, and imposition of liquidated damages were not legally sustainable and should be set aside. Despite this clear judgment, CESCOM failed to make payments to Azure at the PPA tariff and continued paying at the lower interim rate of ₹4.36/kWh.

As CESCOM did not implement the judgment, Azure Sunrise filed the execution petition in 2021. It sought payment of ₹89.27 crore as the outstanding amount and ₹29.44 crore as interest, calculated at 1.25% per month, following the late payment surcharge provision in the PPA. Azure also sought a refund of all liquidated damages deducted earlier.

The Tribunal reiterated that the execution court cannot modify or go beyond the terms of the final judgment. It emphasized that CESCOM had neither challenged the 2020 judgment before the Supreme Court nor sought any review or clarification. The Tribunal noted with disapproval CESCOM’s conduct of non-compliance, misrepresentation, and failure to disclose facts during the execution proceedings. It stated that the continued underpayment and non-refund of damages constituted wilful disobedience of the Tribunal’s order.

The Tribunal concluded that Azure Sunrise’s request was well within the scope of the original judgment and deserved full enforcement. It directed CESCOM to pay the differential amount between ₹6.89/kWh and ₹4.36/kWh for all energy supplied from the project’s commissioning date until the effective realization date. CESCOM was also ordered to refund all liquidated damages along with interest and carrying costs within six weeks.

The Tribunal made it clear that if CESCOM failed to comply within the stipulated period, its bank accounts would be attached and the required amount would be recovered from them. With this, the execution petition and any related applications were disposed of.

 

  • Related Posts

    Top Stories Of The Day: Global Solar Capacity Tops 3 TW -India Ranks Second; GUVNL Launches 450 MW/900 MWh BESS Tender; GERC Proposes New Green Energy Banking Charges and More…

    Global solar power capacity surpassed the landmark 3 TW threshold after a record 664 GW of new solar installations were added during 2025. The achievement highlights the accelerating pace of…

    Week in Africa: South Africa Speeds Up RE Curtailment Claims; AfDB Approves US$100M for West Africa Renewables; Zambia Signs PPA for 500 MW Solar Project and More…

    A large solar panel array stretches across dry savanna land during sunset, illustrating renewable energy use. South Africa’s National Transmission Company South Africa (NTCSA) is accelerating the processing of renewable…

    Have You Seen?

    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    • June 24, 2026
    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    Novak: Russia Considers Complete Ban on Diesel Exports

    • June 24, 2026
    Novak: Russia Considers Complete Ban on Diesel Exports

    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    • June 24, 2026
    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    Trump Insists Iran Has Agreed to Nuclear Inspections

    • June 23, 2026
    Trump Insists Iran Has Agreed to Nuclear Inspections

    Will US and International Sanctions on Iran be Lifted?

    • June 23, 2026
    Will US and International Sanctions on Iran be Lifted?

    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    • June 23, 2026
    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    • June 23, 2026
    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    • June 23, 2026
    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions