GERC Reviews Dispute Over 11.5 MW Solar Plant Capacity Restoration In Gujarat

Representational image. Credit: Canva

Kundan Solar (Astronfield) Pvt. Ltd., formerly known as Astronfield (Gujarat) Pvt. Ltd., has filed a petition before the Gujarat Electricity Regulatory Commission under Section 86(1)(f) of the Electricity Act, 2003. The petition pertains to a dispute between the petitioner and Gujarat Urja Vikas Nigam Ltd. (GUVNL) regarding the petitioner’s solar power project. The company has sought adjudication related to the generation of solar power at its full installed capacity of 11.5 MW under the terms of the Power Purchase Agreement (PPA) dated April 30, 2010, and the amended PPA dated August 7, 2010. The company wants to restore the plant to its full potential by undertaking necessary repairs.

The petition was accompanied by an Interim Application (IA No. 16 of 2025), seeking interim directions from the Commission. The matter was heard on June 26, 2025. The respondent submitted that the petitioner had not provided some critical information.

Despite notices served through RPAD and email, the objector, did not appear, nor did he notify the Commission of any inability to attend.

During the hearing, the Commission raised several queries regarding the documentation required from the petitioner. These include the information memorandum prepared by the resolution professional, the deed of confirmation for the handover of physical possession, the resolution plan proposal and submitted bid, the decision of the Committee of Creditors, and relevant orders from the NCLT, NCLAT, and higher forums. The Commission also requested a contour report of the project site to understand issues related to waterlogging caused by heavy rainfall, including the natural flow of rainwater, site levelling, and measures to avoid flooding. Additionally, technical specifications of the modules and inverters were also sought.

The petitioner agreed to provide the required documents and information. The Commission noted that arguments from both sides were complete and gave both parties the liberty to file any further written submissions within four weeks. The Commission directed the petitioner to submit the pending documents within this same timeframe, with a copy also sent to the respondents.

The matter has been scheduled for the next hearing on August 19, 2025, at 11:30 AM. This hearing will focus on the documents submitted and any issues that may arise.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Top Stories Of The Day: NTPC REL Issues 1,000 MWh BESS Tender; TPL Acquires 26% Solar SPV Stake

    NTPC Renewable Energy Limited has issued a global tender for a 1,000 MWh battery energy storage system at its Bikaner solar plant. The project aims to enhance grid stability, enable…

    MAHAPREIT Invites RFP For 2 MW Rooftop Solar Project At Amul Dairy Plant In Nagpur

    Representational image. Credit: Canva The Mahatma Phule Renewable Energy & Infrastructure Technology Limited (MAHAPREIT), a Government of Maharashtra undertaking and a subsidiary of MPBCDC, has invited a Request for Proposal…

    Have You Seen?

    Saudi, US Firms to Partner on Northeast Syria Energy Project

    • February 10, 2026
    Saudi, US Firms to Partner on Northeast Syria Energy Project

    Chevron Buys West Texas Ranch in ‘Zombie’ Oil Well Settlement

    • February 10, 2026
    Chevron Buys West Texas Ranch in ‘Zombie’ Oil Well Settlement

    BP’s Buyback Cut is Short-Term Pain That Could Be Shell’s Gain: Bousso

    • February 10, 2026
    BP’s Buyback Cut is Short-Term Pain That Could Be Shell’s Gain: Bousso

    Queensland Opens Up Australia’s First Major New Oil Province in 50 Years

    • February 10, 2026
    Queensland Opens Up Australia’s First Major New Oil Province in 50 Years

    BP Suspends Buybacks to Strengthen Balance Sheet

    • February 10, 2026
    BP Suspends Buybacks to Strengthen Balance Sheet

    Britain Bets Big on Renewables with Record Solar and Onshore Wind Awards

    • February 10, 2026
    Britain Bets Big on Renewables with Record Solar and Onshore Wind Awards

    China’s LNG Imports Are Poised for a Rebound This Year

    • February 10, 2026
    China’s LNG Imports Are Poised for a Rebound This Year

    Waste NOx canister explosions ‘cause £7m’ in EfW plant costs

    • February 10, 2026
    Waste NOx canister explosions ‘cause £7m’ in EfW plant costs

    Morocco agrees $4.5bn green ammonia project with ORNX consortium

    • February 10, 2026
    Morocco agrees $4.5bn green ammonia project with ORNX consortium

    Oil Gains as Traders Weigh Supply Risks Linked to US–Iran Tensions

    • February 10, 2026
    Oil Gains as Traders Weigh Supply Risks Linked to US–Iran Tensions