Outer containment work under way for Leningrad’s seventh unit

The new phase of the plant – known as Leningrad II – features two VVER-1200 units, commissioned in 2018 and 2021 respectively, with a third and fourth new unit currently under construction. Together, they will replace the four RBMK-1000 units from the original 1970s phase of the Leningrad nuclear power plant.

The outer containment work involves successively constructing and erecting tiers of a reinforced steel ‘cage’ which will then be filled with concrete. When complete, it will be 70 metres high, 52 metres in diameter and 80 centimetres thick.

Containment buildings for nuclear power units are safety features, with the VVER-1200 involving an internal and an outer containment building as part of a double containment protection system – with the outer containment designed to provide extra protection from external hazards such as earthquakes and aircraft crashes.

Leningrad NPP-2’s Evgeny Milushkin, said: “The outer containment shell will be constructed in tiers. We plan to have the first one ready as early as November.  The structure, approximately four metres high, will require over 200 tonnes of steel reinforcement and nearly 600 cubic metres of concrete. Early next year, the shell will grow another four metres. The entire outer containment shell will be ready in 2028.”

Construction of the inner containment is taking place at the same time as the outer containment. The lower tier of the inner containment building – with a 44-metre diameter, measuring 10 metres high and weighing 227 tonnes – was lowered into place last month. Work is also taking place on the reactor building and core catcher.

Rosatom says there are more than 1,000 people involved in the construction of the unit and the fourth new unit. The new units are scheduled to be commissioned in 2030 and 2032.

Background

The Leningrad nuclear power plant is one of the largest in Russia, with an installed capacity of 4,400 MWe, and provides more than 55% of the electricity demand of St Petersburg and the Leningrad region, or 30% of all the electricity in northwest Russia.

Leningrad 1 shut down in 2018 after 45 years of operation. Leningrad 2, also a 1,000 MWe RBMK unit, started up in 1975 and was permanently shut down in November 2020. As the first two of the plant’s four RBMK-1000 units shut down, new VVER-1200 units started up at the neighbouring Leningrad II plant. The 60-year service life of these fifth and sixth units (also known as Leningrad II-1 and Leningrad II-2) secures power supply until the 2080s. Units 7 and 8 (also known as Leningrad II-3 and Leningrad II-4) will replace units 3 and 4 as they are shut in the coming years.

The pouring of the first concrete for unit 7 in March 2024 marked the start of the main phase of construction of the new power unit, which is expected to generate power for 60 years, with the possibility of a 20-year extension.

   

  • Related Posts

    Kaleidos microreactor begins journey to Idaho

    “We said we’d make a microreactor that is transportable by land, sea and air. We did. Kaleidos is traveling more than 1,000 miles on a trailer bed,” the company said. …

    Detritiation facility reopens at Culham

    In the last three years of plasma operations, the Joint European Torus’s (JET’s) deuterium-tritium experiments resulted in residual tritium being retained within the tokamak’s walls and internal components. This reflected…

    Have You Seen?

    Podcast | Industrial gases financials: headwinds, growth and what comes next?

    • August 19, 2026
    Podcast | Industrial gases financials: headwinds, growth and what comes next?

    Gaza’s medical oxygen system could be close to collapse

    • August 19, 2026
    Gaza’s medical oxygen system could be close to collapse

    Sri Lanka Clean Energy Week 2026 Set to Unite the Industry in Just 2 Days  

    • August 19, 2026
    Sri Lanka Clean Energy Week 2026 Set to Unite the Industry in Just 2 Days  

    Saudi Arabia’s Renewable Energy Investment Reaches SAR 36.11 Billion As Capacity Surges 88%

    • August 19, 2026
    Saudi Arabia’s Renewable Energy Investment Reaches SAR 36.11 Billion As Capacity Surges 88%

    Kino Aski LNG targets North America-Europe energy corridor

    • August 19, 2026
    Kino Aski LNG targets North America-Europe energy corridor

    SJVN Green Energy Invites Bids For 1,000 MW Solar Projects In Punjab And Rajasthan

    • August 19, 2026
    SJVN Green Energy Invites Bids For 1,000 MW Solar Projects In Punjab And Rajasthan

    South Africa Unveils Revised Electricity Pricing Policy To Cut Costs And Boost Market Competition

    • August 19, 2026
    South Africa Unveils Revised Electricity Pricing Policy To Cut Costs And Boost Market Competition

    Jeff Currie: Forget $91 Brent, The Real Crisis Is $170 Diesel

    • August 19, 2026
    Jeff Currie: Forget $91 Brent, The Real Crisis Is $170 Diesel

    Aramco Puts VLCCs Back Into Hormuz After Three-Week Pause

    • August 19, 2026
    Aramco Puts VLCCs Back Into Hormuz After Three-Week Pause

    Distillate Stocks Sink Further as U.S. Crude Inventories Barely Budge

    • August 19, 2026
    Distillate Stocks Sink Further as U.S. Crude Inventories Barely Budge