RERC Dismisses Petition Over Disputed Grid Connectivity Charges And Substation Bay Construction Costs

The Rajasthan Electricity Regulatory Commission (RERC) reviewed a petition filed by M/s Saraf Export Palace, disputing charges related to grid connectivity and the construction of a dedicated 33 kV bay at RVPNL’s 132 kV Grid Substation Kolayat, Bikaner. The petitioner sought a refund or adjustment of ₹12 lakhs previously paid as grid connectivity charges, alongside contesting a subsequent demand of ₹19,74,458 for the new bay construction.

The petitioner argued that the initial grid connectivity charges, paid when setting up two solar power plants, should have been adjusted against the new demand. The petitioner emphasized that their request for a revised connectivity plan arose due to operational issues, as their O&M contractor, M/s Rays Power Experts Pvt. Ltd., refused to evacuate power through the existing transmission line. This led them to seek direct connectivity to RVPNL’s substation.

RVPNL, the respondent, maintained that the grid connectivity charges are one-time and non-refundable, as per the Solar Policy, 2019, and that the demand for the bay construction cost was justified. They argued that the petitioner voluntarily sought revised connectivity and explicitly agreed to bear the associated costs.

The Commission examined the Solar Policy, 2019, and relevant regulations, noting no explicit provision for adjusting or refunding grid connectivity charges in cases of revised connectivity. The policy outlines that infrastructure costs for new or modified connectivity are recoverable from the power producer requesting the changes. The Commission held that the petitioner’s reliance on internal correspondence to support their claim was misplaced, as those communications lacked binding authority.

The Commission concluded that the demand for ₹19,74,458 by RVPNL was consistent with the principles of cost recovery under the Solar Policy, 2019. It emphasized that infrastructure costs arising from revised connectivity should be borne by the beneficiary and not distributed among other consumers. Consequently, the petitioner’s request for a refund or adjustment of ₹12 lakhs was denied, and the petition was dismissed without costs.

 

  • Related Posts

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Enviromena has started construction of the Longpasture Solar Farm in County Durham, UK, marking a major milestone for the company’s second-largest UK project to date. The company acquired the project…

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    Indian stock markets ended lower on August 24, 2026, as investors remained cautious amid selling pressure across benchmark indices. The S&P BSE SENSEX closed at 77,369.11, declining 0.22%, or around…

    Have You Seen?

    Texas Oil Regulator Elects New Chairman

    • August 24, 2026
    Texas Oil Regulator Elects New Chairman

    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    • August 24, 2026
    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    • August 24, 2026
    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    • August 24, 2026
    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    Japan Power Prices Surge to Highest Since 2023

    • August 24, 2026
    Japan Power Prices Surge to Highest Since 2023

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    • August 24, 2026
    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    • August 24, 2026
    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    • August 24, 2026
    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    • August 24, 2026
    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia

    • August 24, 2026
    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia