OPG applies for operating licence for BWRX-300 SMR

The application by Ontario Power Generation (OPG) is for a 20-year licence to operate what looks set to be the first small modular reactor (SMR) in a G7 country, as well as an associated low- and intermediate-level waste storage structure.

The Canadian Nuclear Safety Commission (CNSC), confirming the receipt of the application, said: “The application for a licence to operate is subject to a decision by the Commission following a public hearing, to be announced at a later date.”

A licence to operate will be needed to complete commissioning and safely operate the reactor once construction is completed, OPG said.

OPG already holds a construction licence for the site, which has three regulatory hold points (RHP). The first of these was the installation of the reactor building foundation, a hold point which was lifted on Monday.

Ramzi Jammal, CNSC Executive Vice-President and Chief Regulatory Operations Officer, said in a letter to OPG: “The Canadian Nuclear Safety Commission staff assessment of OPG’s submission, as well as all supporting documentation, concludes that OPG has met all the pre-requisites established by the Commission to remove RHP-1.”

The removal of this hold point means OPG “can place the foundation for the reactor building and commence civil construction of the reactor building structure, internal civil structures, and internal reactor building systems and components”.

The next hold point will be the installation of the reactor pressure vessel.

Background

GE Vernova Hitachi Nuclear Energy’s BWRX-300 is a 300 MWe water-cooled, natural circulation SMR with passive safety systems that leverages the design and licensing basis of GE Vernova Hitachi Nuclear Energy’s US Nuclear Regulatory Commission-certified ESBWR boiling water reactor design and its existing, licensed GNF2 fuel design. 

The Darlington New Nuclear Project will be the first new nuclear build in Ontario in more than three decades. OPG received a Licence to Construct the first of four planned BWRX-300s at Darlington from the CNSC in April 2025. The following month the Province of Ontario approved the CAD20.9 billion (USD15 billion) budget and the start of construction for the first of the proposed four SMRs at the site.

Ontario’s Ministry of Energy and Mines said its approval of OPG’s plan would create up to 18,000 Canadian jobs and inject CAD500 million annually into the Ontario economy, with the construction, operation and maintenance of the four units set to add CAD38.5 billion to the country’s GDP over 65 years. It said the provincial government and OPG have worked together to ensure that 80% of project spending goes to companies in Ontario.

Site preparation works began in the autumn of 2022, and several long-lead items, including the reactor pressure vessel, have already been procured. The plan is to connect the first unit to the grid by the end of 2030.

   

  • Related Posts

    Concreting completed of Kursk II’s third reactor building foundation

    About 200 workers were involved in the pouring of concrete to form the 5,400-square-metre slab, a process which took four months, said Rosatom, Russia’s state nuclear corporation. It added that throughout…

    Site of Polish plant deemed suitable

    The preliminary site assessment covered: seismic, tectonic, geological-engineering, hydrogeological, hydrological and meteorological conditions of the site area; external events resulting from human activity in the area; external events resulting from…

    Have You Seen?

    India’s Inflation Accelerates as High Energy Prices Start to Bite

    • May 8, 2026
    India’s Inflation Accelerates as High Energy Prices Start to Bite

    First Mexican Fuel Oil Cargo in 9 Months Arrives in Asia

    • May 8, 2026
    First Mexican Fuel Oil Cargo in 9 Months Arrives in Asia

    Iraq Denies U.S. Claim Deputy Minister Helped Iran’s Oil Sales

    • May 8, 2026
    Iraq Denies U.S. Claim Deputy Minister Helped Iran’s Oil Sales

    CF Industries warns LNG shortages could extend ammonia crunch into 2027

    • May 8, 2026
    CF Industries warns LNG shortages could extend ammonia crunch into 2027

    German state could build 800MW hydrogen-ready gas plant

    • May 8, 2026
    German state could build 800MW hydrogen-ready gas plant

    Trump’s Crackdown on China-Linked Solar Firms stalls U.S. Factory Boom

    • May 8, 2026
    Trump’s Crackdown on China-Linked Solar Firms stalls U.S. Factory Boom

    Shale Producer Devon Energy Approves $8 Billion Share Buyback Plan

    • May 8, 2026
    Shale Producer Devon Energy Approves $8 Billion Share Buyback Plan

    Latvia greenlights €5m biomethane grid project

    • May 8, 2026
    Latvia greenlights €5m biomethane grid project

    More Than 40 India-Bound Ships Remain Trapped Near Hormuz

    • May 8, 2026
    More Than 40 India-Bound Ships Remain Trapped Near Hormuz

    Global Jet Fuel Exports Hit 10-Year Seasonal Low in April

    • May 8, 2026
    Global Jet Fuel Exports Hit 10-Year Seasonal Low in April