Akkuyu’s first back-up diesel generator being commissioned

Friday, 21 February 2025

Akkuyu's first back-up diesel generator being commissioned
(Image: Akkuyu NPP)

Each of the four units at the Akkuyu plant will have three diesel generators, which will be ready to operate within 15 seconds of being required to provide power if the mains power supply is lost.

The first diesel generator was started at idle and there will now be tests of its operation under load, with around 50 checks to take place in various operating modes. Once these tests are successfully passed it will be put into “standby” mode, where it will be ready to automatically start to provide back-up power when required.

The commissioning of diesel generators is required before the cold-hot testing phase of the reactor unit.

Andrei Zhukov, Deputy Director and Technical Director of the NPP Under Construction at Akkuyu Nuclearsaid: “Backup diesel power plants are one of the basic elements of nuclear power plant safety systems. These plants serve as independent power sources for the nuclear power plant in case of a main power supply failure. Together, the three diesel generators in each unit will be able to provide power to all designed systems of the unit for at least 72 hours without refuelling.”

The Russian VVER-1200 reactors at Akkuyu are each designed to have three diesel generators – two for the emergency power supply and one for the normal operation system. Each plant has a capacity of 6.3 MW and are located in independent buildings. They each have a back-up start-up system which allows remote start-up from the nuclear power plant or from the back-up control centre. In total a fuel reserve for six days of backup power is stored on site.

Background
 

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December, and in February it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system in 2025. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs, with the aim that all four units will be operational by the end of 2028.

   

  • Related Posts

    KHNP, Southern to cooperate on nuclear engineering

    Under the agreement – signed at KHNP’s headquarters in Gyeongju in South Korea – both companies plan to strengthen their partnership by operating technology exchange programmes, holding workshops, and sharing…

    World Nuclear Fuel Cycle: How best to meet growing demand?

    The first panel of the two-day conference saw industry leaders set the scene, outlining accelerating plans for new nuclear deployment from countries with long-established nuclear programmes to newcomer countries and…

    Have You Seen?

    US Government’s Energy Arm Assumes Strait of Hormuz Will Stay Shut Through Late May

    • May 12, 2026
    US Government’s Energy Arm Assumes Strait of Hormuz Will Stay Shut Through Late May

    US Power Use to Beat Record Highs in 2026 and 2027 as AI Use Surges, EIA Says

    • May 12, 2026
    US Power Use to Beat Record Highs in 2026 and 2027 as AI Use Surges, EIA Says

    Asia’s Major LNG Importers Japan and Korea Turn to Coal

    • May 12, 2026
    Asia’s Major LNG Importers Japan and Korea Turn to Coal

    Brazil’s Oil Exports to China Double as Iran War Upends Crude Flows

    • May 12, 2026
    Brazil’s Oil Exports to China Double as Iran War Upends Crude Flows

    Qatar Asks Vessels at Key LNG Port To Go Dark for Safety

    • May 12, 2026
    Qatar Asks Vessels at Key LNG Port To Go Dark for Safety

    Analysis: Counting the costs of the Middle East crisis

    • May 12, 2026
    Analysis: Counting the costs of the Middle East crisis

    LanzaTech to develop ‘Europe’s first’ ethanol-based SAF facility in Belgium

    • May 12, 2026
    LanzaTech to develop ‘Europe’s first’ ethanol-based SAF facility in Belgium

    Nikkiso signs long-term marine service agreement with Maran Tankers

    • May 12, 2026
    Nikkiso signs long-term marine service agreement with Maran Tankers

    ISS Recommends Shareholders Vote Against Exxon Moving its Registration to Texas

    • May 12, 2026
    ISS Recommends Shareholders Vote Against Exxon Moving its Registration to Texas

    A Trump-Xi Deal Could Revive US Energy Exports to China

    • May 12, 2026
    A Trump-Xi Deal Could Revive US Energy Exports to China