CEZ completing Temelin SMR boreholes survey

The first survey related to the small modular reactor (SMR) project was carried out three years ago with four boreholes to a depth of 30 metres.

The current round of drilling is in the southwestern edge of the existing nuclear power plant site and involves nine exploratory core boreholes drilled to a depth of between 50 metres and 200 metres.

A diamond crown has been used which can drill through the hardest rocks – the hard rocks means progress can be limited at times to two metres per hour. The aim is to refine data on the geological environment.

Silvana Jirotková, Director of the SMR development department at ČEZ, said: “Geologically, it is a very mapped location, suitable for nuclear energy. The surveys were carried out by workers in the 1980s before the construction of Temelín units 1 and 2. Other surveys were in connection with the preparation of the third and fourth units. In the case of the modular reactor, this is the second exploration, others will follow.”

The premitting process is already under way for the project, with an environmental impact assessment currently under way, with CEZ hoping to submit it within the next year.

The Czech Republic selected Rolls-Royce SMR as its partner for up to 3 GW of new nuclear capacity last year and CEZ has taken a 20% shareholding in the UK-based company.

Background

The Rolls-Royce SMR is a 470 MWe design based on a small pressurised water reactor. It will provide consistent baseload generation for at least 60 years. 90% of the SMR – measuring about 16 metres by 4 metres – will be built in factory conditions, limiting on-site activity primarily to assembly of pre-fabricated, pre-tested, modules which significantly reduces project risk and has the potential to drastically shorten build schedules.

Last month CEZ and Rolls-Royce SMR signed an Early Works Agreement to start site-specific work for potential small modular reactors at the Temelin nuclear power plant. The aim is to build the first SMR in the Czech Republic there in the mid-2030s. There are also plans being developed for their deployment at the location of current coal-fired power plants.

In the Czech Republic four VVER-440 units are currently in operation at the Dukovany site, which began operating between 1985 and 1987. There are also two units at Temelin and between them the six units generate about one-third of its electricity. A CZK407 billion (USD18.6 billion) contract was signed with Korea Hydro & Nuclear Power in June for two of its APR1000 reactors near the existing Dukovany units. The aim is to start construction in 2029. A further two APR1000 units may follow at Temelin.

   

  • Related Posts

    Czech SMR environmental impact assessment submitted

    The submission of the Environmental Impact Assessment (EIA) is a key part of the permitting process and assesses the potential impact on the area from the proposed small modular reactor…

    IAEA carries out fresh LTO review mission to Oskarshamn

    The Safety Aspects of Long Term Operation mission took place from 6 to 9 October and included two members of International Atomic Energy Agency (IAEA) staff and two experts from Argentina…

    Have You Seen?

    Podcast | Too many what ifs: North America CO2 Summit 2026

    • October 13, 2026
    Podcast | Too many what ifs: North America CO2 Summit 2026

    IMF Warns Middle East War Could Derail Global Economic Growth

    • October 13, 2026
    IMF Warns Middle East War Could Derail Global Economic Growth

    Saudi Arabia Plans Massive Expansion of Oil Pipeline to Bypass Hormuz

    • October 13, 2026
    Saudi Arabia Plans Massive Expansion of Oil Pipeline to Bypass Hormuz

    Saudi Arabia Shoots Down Houthi Missiles as Regional Conflict Escalates

    • October 13, 2026
    Saudi Arabia Shoots Down Houthi Missiles as Regional Conflict Escalates

    Philippines Clean Energy Week 2026 Sets New Momentum for the Country’s Energy Transition  

    • October 13, 2026
    Philippines Clean Energy Week 2026 Sets New Momentum for the Country’s Energy Transition  

    GasBuddy Flags Fragile Calm at the Pump

    • October 13, 2026
    GasBuddy Flags Fragile Calm at the Pump

    Indian Stock Markets Rally 1.54% As Green Energy Stocks Deliver Mixed Performance On October 13

    • October 13, 2026
    Indian Stock Markets Rally 1.54% As Green Energy Stocks Deliver Mixed Performance On October 13

    Sungrow to Introduce Latest SG510HX Grid-Forming Utility-Scale Inverter in India at REI 2026

    • October 13, 2026

    SARCO And Go Energy Sign MoU To Explore Green Hydrogen And Ammonia Facility In Saudi Arabia

    • October 13, 2026
    SARCO And Go Energy Sign MoU To Explore Green Hydrogen And Ammonia Facility In Saudi Arabia

    Japan strengthens LNG security as Middle East conflict disrupts supplies

    • October 13, 2026
    Japan strengthens LNG security as Middle East conflict disrupts supplies