Constellation seeks regulator’s help for 2027 plant restart

CEO Joseph Dominguez told investors that the company was intending to file a request to the Federal Electricity Regulatory Commission (FERC) to transfer capacity rights from its Eddystone plant to enable the restart.

Constellation announced in 2024 that it would restart the pressurised water reactor, which closed down in 1999, after signing a 20-year power purchase agreement with Microsoft. Last year, the company filed an interconnection request with regional transmission operator PJM to allow Crane to add its 835 megawatts of emissions-free power to the grid.

Initially aiming for a 2028 restart, the company had brought its target date forward to 2027 following PJM’s approval of its early interconnection request. However, at last week’s CERA Week conference in Houston, Constellation’s chief external affairs and growth officer David Dardis told Reuters that PJM had said it would take until 2031 to complete some of the transmission upgrades needed for the plant to connect to the grid.

Speaking in Constellation’s 2026 Business and Earnings Outlook call, Dominguez said the company still expected to be able to start the unit in 2027.

“We talked this week about PJM studies that indicate interconnection could be delayed into the 2030s,” Dominguez said. “I want to assure you we are working on that with PJM and we continue to expect to start this unit in 2027. Today, we will be filing a FERC request to be able to transfer capacity injection rights from our Eddystone unit to Crane to facilitate restart in ’27, according to our plan.”

Eddystone is a six-unit, dual-fuelled plant in Pennsylvania, with two 380 MW capacity subcritical steam boiler-turbine generator units that can run on either natural gas or oil, depending on market conditions, and two pairs of oil-fuelled peaking units that run during periods of high demand with a total capacity of 60 MW. The 380 MW units – Eddystone 3 and 4 – had been scheduled for closure last year, but have been kept online beyond their planned retirement date to ensure grid reliability under a series of emergency orders issued by US Energy Secretary Chris Wright. The most recent order was issued in February and remains in force until 24 May.

The Crane Clean Energy Center restart project is receiving federal support through the US Department of Energy’s loan programme.

   

  • Related Posts

    EC launches investigation into French nuclear funding plans

    France has plans for six new EPR2 reactors – two each at Penly, Gravelines and Bugey – which will have a total generation capacity of nearly 10 GW. Commissioning is…

    Amentum, Cavendish Nuclear joint venture gets key UK SMRs role

    The joint venture – Litmus Nuclear – will deliver “independent assurance and expert technical guidance across critical areas, including design, safety, engineering, construction, and commissioning”. The agreement has a maximum…

    Have You Seen?

    Trump Tells Allies to Fight for Jet Fuel or Buy From the U.S.

    • April 1, 2026
    Trump Tells Allies to Fight for Jet Fuel or Buy From the U.S.

    US Natural Gas Supply Outlook Hinges on Three Key Shale Basins: Maguire

    • April 1, 2026
    US Natural Gas Supply Outlook Hinges on Three Key Shale Basins: Maguire

    US Crude Stocks Rise, Gasoline and Distillate Inventories Fall – EIA

    • April 1, 2026
    US Crude Stocks Rise, Gasoline and Distillate Inventories Fall – EIA

    Trump Says Iranian Leader Has Asked for a Ceasefire

    • April 1, 2026
    Trump Says Iranian Leader Has Asked for a Ceasefire

    US to Leave Iran ‘Pretty Quickly’ and Return if Needed, Trump Tells Reuters

    • April 1, 2026
    US to Leave Iran ‘Pretty Quickly’ and Return if Needed, Trump Tells Reuters

    US Gulf Coast Tanker Market Tightens as Asia Seeks to Replace Lost Supply

    • April 1, 2026
    US Gulf Coast Tanker Market Tightens as Asia Seeks to Replace Lost Supply

    EU Warns Energy Prices Won’t Fall Even If Iran War Ends Tomorrow

    • April 1, 2026
    EU Warns Energy Prices Won’t Fall Even If Iran War Ends Tomorrow

    BP’s New CEO Pledges Consistency as Company Tries to Rebuild Investor Trust

    • April 1, 2026
    BP’s New CEO Pledges Consistency as Company Tries to Rebuild Investor Trust

    IMI appoints new APAC managing director for industrial automation

    • April 1, 2026
    IMI appoints new APAC managing director for industrial automation

    Quantum Helium gets approval for Sagebrush-1 testing in Colorado

    • April 1, 2026
    Quantum Helium gets approval for Sagebrush-1 testing in Colorado