Containment tests completed at Sanmen 3

The two-part tests confirm that the containment vessel meets design and construction quality requirements. The first part – the structural integrity test (SIT) – involved the vessel being pressurised and monitored to confirm that its design and construction meet all applicable industry codes and standards at 110% of design pressure.

The vessel was then pressurised to design pressure and the integrated leak rate test (ILRT) was performed to demonstrate its ability to prevent the release of radioactive materials in the event of an emergency.

During the containment pressure test, the containment leakage is checked through the acoustic leak detection test, and the changes in the containment structure performance are monitored through internal visual inspection and external visual inspection tests.

“Conducting SIT and ILRT tests before commissioning a new unit is a core step in verifying the reliability of the barrier,” China National Nuclear Corporation (CNNC). “These tests simulate the pressure conditions under a design baseline accident by injecting compressed air into the steel containment vessel, comprehensively verifying the structural integrity and overall sealing performance of the containment’s pressure-bearing boundaries.”

It added: “The successful completion of this test fully verified the manufacturing and installation quality of the containment vessel, laying a solid foundation for subsequent similar tests and hot-testing of the unit.”

The construction of two new reactors at each of the Sanmen, Haiyang and Lufeng sites in China was approved by China’s State Council in April 2021. The approvals were for Sanmen units 3 and 4, Haiyang 3 and 4 and units 5 and 6 of the Lufeng plant. The Sanmen and Haiyang plants are already home to two Westinghouse AP1000 units each, and two CAP1000 units – the Chinese version of the AP1000 – were approved for Phase II (units 3 and 4) of each plant.

The first safety-related concrete was poured for the nuclear island of Sanmen 3 on 28 June 2022, marking the official start of its construction. The first concrete for that of unit 4 was poured on 22 March last year. The units are expected to be connected to the grid in 2027 and 2028, respectively.

Cold functional tests – carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition – were completed in February.

Hot functional tests – which involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should = will be carried out before the loading of nuclear fuel. Such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

Two Hualong One (HPR1000) reactors are planned for Phase III (units 5 and 6) of the Sanmen plant.

   

  • Related Posts

    Concreting milestones at Chinese Hualong One units

    China National Nuclear Corporation (CNNC) said the last batch of concrete was poured for the inner dome of Zhangzhou unit 3 on 30 September. “This key milestone marks the completion…

    DOE offers Vistra loan for reactor upgrades and uprates

    Vistra’s planned investments at Beaver Valley in Pennsylvania and Davis-Besse and Perry in Ohio will produce more electricity from existing nuclear plants without requiring new transmission corridors or equivalent new…

    Have You Seen?

    MNRE Proposes Standardized 14-Digit Naming System For ALMM List-II Solar Cells

    • October 7, 2026
    MNRE Proposes Standardized 14-Digit Naming System For ALMM List-II Solar Cells

    Australia Commits $7.29 Million To Strengthen Pacific Renewable Energy Security

    • October 7, 2026
    Australia Commits $7.29 Million To Strengthen Pacific Renewable Energy Security

    HPSEBL Floats Tender for 1 MW Green Hydrogen Plant and 33 kV Feeder Strengthening In Himachal Pradesh

    • October 7, 2026
    HPSEBL Floats Tender for 1 MW Green Hydrogen Plant and 33 kV Feeder Strengthening In Himachal Pradesh

    JWL Secures 41 MW/102.5 MWh BESS Project In Uttarakhand, Receives 50 MW/200 MWh West Bengal LoA

    • October 7, 2026
    JWL Secures 41 MW/102.5 MWh BESS Project In Uttarakhand, Receives 50 MW/200 MWh West Bengal LoA

    Gulf Producers Say Importers Should Share the Cost of Hormuz Workarounds

    • October 6, 2026
    Gulf Producers Say Importers Should Share the Cost of Hormuz Workarounds

    Low Wind Generation Prompts Another Power Margin Warning in UK

    • October 6, 2026
    Low Wind Generation Prompts Another Power Margin Warning in UK

    India Could Boost Crude and Critical Minerals Supply from Ecuador

    • October 6, 2026
    India Could Boost Crude and Critical Minerals Supply from Ecuador

    EU Delays Methane Rules, Opens Refinery Talks as Fuel Prices Hit Records

    • October 6, 2026
    EU Delays Methane Rules, Opens Refinery Talks as Fuel Prices Hit Records

    100+ Oil Execs Predict Future WTI Oil Prices

    • October 6, 2026
    100+ Oil Execs Predict Future WTI Oil Prices

    At Least 50 Iranian Tankers Are Stuck in the Gulf as U.S. Blockade Holds

    • October 6, 2026
    At Least 50 Iranian Tankers Are Stuck in the Gulf as U.S. Blockade Holds