(Image: ChNPP)

Workers from the State Emergency Service of Ukraine have been working at the site since the drone strike on Friday 14 February damaged the roof of the giant structure built to cover Chernobyl’s unit 4.

The Chernobyl plant company (ChNPP) said that the external cladding of the arch-shaped New Safe Confinement (NSC) had a 15 square metre area of damage from the drone, with further damage in areas up to 200 square metres. It said there was also damage to the internal cladding filler and to some bolted connections in the structure.

It says that radiation levels remain within their normal levels at the site – the NSC was built to cover a wide area, including the original rapidly built shelter over the remnants of unit 4 following the accident in 1986. 

In its update on Thursday, the International Atomic Energy Agency, which has experts based at Chernobyl, said: “Firefighters are continuing to put out small fires that keep smouldering and spreading on the roof of the New Safe Confinement.” It added that agency staff’s “measurements continue to show normal gamma radiation dose rate values near the NSC compared to those recorded by the IAEA since it established a continuous presence at the site just over two years ago”.

What is the New Safe Confinement?
 

Chernobyl Nuclear Power Plant’s unit 4 was destroyed in the April 1986 accident (you can read more about it in the ) with a shelter constructed in a matter of months to encase the damaged unit, which allowed the other units at the plant to continue operating. It still contains the molten core of the reactor and an estimated 200 tonnes of highly radioactive material. 

However it was not designed for the very long-term, and so the New Safe Confinement – the largest moveable land-based structure ever built – was constructed to cover a much larger area including the original shelter. The New Safe Confinement has a span of 257 metres, a length of 162 metres, a height of 108 metres and a total weight of 36,000 tonnes and was designed for a lifetime of about 100 years. It was built nearby in two halves which were moved on specially constructed rail tracks to the current position, where it was completed in 2019.

It has two layers of internal and external cladding around the main steel structure – about 12 metres apart – with the IAEA confirming that both had been breached in the incident. The NSC was designed to allow for the eventual dismantling of the ageing makeshift shelter from 1986 and the management of radioactive waste. It is also designed to withstand temperatures ranging from -43°C to +45°C, a class-three tornado, and an earthquake with a magnitude of 6 on the Richter scale.

According to World Nuclear Association, the hermetically-sealed New Safe Confinement allows “engineers to remotely dismantle the 1986 structure that has shielded the remains of the reactor from the weather since the weeks after the accident. It will enable the eventual removal of the fuel-containing materials in the bottom of the reactor building and accommodate their characterisation, compaction, and packing for disposal. This task represents the most important step in eliminating nuclear hazard at the site – and the real start of dismantling”.

The wider context
 

Chernobyl nuclear power plant lies about 130 kilometres north of Ukraine’s capital Kyiv, and about 20 kilometres south of Belarus. A 30-kilometre exclusion zone remains around the plant, although some areas have been progressively resettled. Three other reactors at the site, which was built during Soviet times, continued to operate after the accident, with unit 3 the last one operating, until December 2000.

When Russia launched its invasion of Ukraine in February 2022 it rapidly took control of the Chernobyl plant. Its forces remained there until withdrawing on 31 March 2022 and control returned to Ukrainian personnel. The IAEA has had experts stationed at the site as the war has continued, seeking to help ensure the safety and security of the site.

IAEA teams are also in place at Ukraine’s three operating nuclear power plants and the Zaporizhzhia nuclear power plant, which has been under the control of Russian forces since early March 2022.

Ukraine has blamed Russia for the drone strike, while Russia denied it was responsible and blamed Ukraine. The IAEA has not attributed blame to either side during the war, with Director General Grossi explaining in a press conference at the United Nations in April last year that this was particularly the case with drones, saying “we are not commentators. We are not political speculators or analysts, we are an international agency of inspectors. And in order to say something like that, we must have proof, indisputable evidence, that an attack, or remnants of ammunition or any other weapon, is coming from a certain place. And in this case it is simply impossible”.

   

  • Related Posts

    Darlington 4 back in service, completing refurb project

    Ontario Power Generation (OPG) said the four-unit CAD12.8 billion (USD9.4 billion) Darlington Refurbishment Project – which extends the plant’s operation by another 30 years – had been completed CAD150 million…

    GE Vernova, Hitachi explore Southeast Asia market for BWRX-300

    The two companies have agreed to collaborate to identify commercial opportunities for their joint venture GE Vernova Hitachi Nuclear Energy’s BWRX-300 in Southeast Asia, as well as exploring opportunities to incorporate…

    Have You Seen?

    Hormuz Crisis Sparks Urgent Call to Boost UK Gas Storage

    • March 16, 2026
    Hormuz Crisis Sparks Urgent Call to Boost UK Gas Storage

    Iraq To Restore Kirkuk-Turkey Pipeline as Iran War Chokes Off Exports

    • March 16, 2026
    Iraq To Restore Kirkuk-Turkey Pipeline as Iran War Chokes Off Exports

    Middle East War Revives Interest in Alaska LNG

    • March 16, 2026
    Middle East War Revives Interest in Alaska LNG

    EU Considers Naval Action to Reopen Vital Strait of Hormuz

    • March 16, 2026
    EU Considers Naval Action to Reopen Vital Strait of Hormuz

    Pakistan Oil Tanker Transits Hormuz

    • March 16, 2026
    Pakistan Oil Tanker Transits Hormuz

    Kent wins engineering and design contract for Prinos CO2 storage project

    • March 16, 2026
    Kent wins engineering and design contract for Prinos CO2 storage project

    COMMENTARY: US is Quickly Exhausting Tools to Absorb Iran War Oil Shock – Ron Bousso

    • March 16, 2026
    COMMENTARY: US is Quickly Exhausting Tools to Absorb Iran War Oil Shock – Ron Bousso

    Trump Adviser Says Iran ‘Terror Premium’ Inflated Oil Prices for Decades

    • March 16, 2026
    Trump Adviser Says Iran ‘Terror Premium’ Inflated Oil Prices for Decades

    Japan Taps Emergency Oil Reserves

    • March 16, 2026
    Japan Taps Emergency Oil Reserves

    Fujairah Suspends Oil Loadings After Another Attack

    • March 16, 2026
    Fujairah Suspends Oil Loadings After Another Attack