GETCO Faces Petition Over Delay And Continued Use Of Temporary Bay At Kalavad Sub-Station In Gujarat

Representational image. Credit: Canva

The Gujarat Electricity Regulatory Commission recently heard a petition involving M/s Morjar Renewables Private Limited and Gujarat Energy Transmission Corporation Limited (GETCO). The case concerns two main issues: the extension of time for building and commissioning a permanent 220 KV GIS bay at the Kalavad sub-station, and the continued use of a temporary bay provided by GETCO until the permanent bay becomes operational.

M/s Morjar Renewables explained that delays in constructing the permanent bay are due to factors beyond their control. They requested permission to keep using the temporary bay until three other renewable energy companies—Cleanmax, Suzlon, and OP Wind—finish their own bay constructions at the same substation. The petitioner said their permanent bay is expected to be ready by June 30, 2025, but it cannot become functional until the bays of the other three generators are also completed. This is because all four bays connect to a common bus bar that must be energized together.

The petitioner also mentioned repeated attempts to organize a joint meeting with GETCO and the other renewable developers since January 13, 2025, to coordinate their work and ensure timely commissioning. They added that another company, M/s Jamnagar Renewables Two Private Limited, plans to evacuate power through their permanent bay, making the timely completion or continued use of the temporary bay more urgent.

On the other side, GETCO acknowledged the two issues but expressed reluctance to extend the temporary bay usage beyond March 31, 2025, which they had previously permitted. However, the Commission issued an interim order on March 29, 2025, allowing the petitioner to continue using the temporary bay until the next hearing. GETCO noted that if the petitioner completes their bay by the end of June, many delay reasons would no longer be relevant.

GETCO also pointed out that due to the sub-station’s current design, all four renewable energy developers must commission their GIS bays simultaneously for the system to operate. They requested permission from the Commission to hold a meeting and inspect the progress of all four generators’ work, as suggested by the petitioner. GETCO clarified that the temporary bay usage was granted only to Morjar Renewables and not to Jamnagar Renewables Two Private Limited.

During the hearing, the Commission asked GETCO to provide detailed information on several important matters. These included the energization date of the Kalavad 220 KV sub-station, its power transformation capacity and how it is allocated, a full list of dates and documents concerning connectivity and open access approvals for all developers connected to the sub-station, the status of transmission infrastructure work completed by the developers, and data on connectivity applications, allocation timelines, and power evacuation volumes. The Commission also wanted to know if there had been any cancellations or changes in connectivity and the reasons behind them.

Both parties completed their oral arguments and were given 10 days to submit written statements. The Commission reserved the final decision, while the previous interim order allowing temporary bay use remains in effect until further notice.

 

  • Related Posts

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Enviromena has started construction of the Longpasture Solar Farm in County Durham, UK, marking a major milestone for the company’s second-largest UK project to date. The company acquired the project…

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    Indian stock markets ended lower on August 24, 2026, as investors remained cautious amid selling pressure across benchmark indices. The S&P BSE SENSEX closed at 77,369.11, declining 0.22%, or around…

    Have You Seen?

    Texas Oil Regulator Elects New Chairman

    • August 24, 2026
    Texas Oil Regulator Elects New Chairman

    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    • August 24, 2026
    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    • August 24, 2026
    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    • August 24, 2026
    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    Japan Power Prices Surge to Highest Since 2023

    • August 24, 2026
    Japan Power Prices Surge to Highest Since 2023

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    • August 24, 2026
    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    • August 24, 2026
    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    • August 24, 2026
    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    • August 24, 2026
    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia

    • August 24, 2026
    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia