GETCO Faces Petition Over Delay And Continued Use Of Temporary Bay At Kalavad Sub-Station In Gujarat

Representational image. Credit: Canva

The Gujarat Electricity Regulatory Commission recently heard a petition involving M/s Morjar Renewables Private Limited and Gujarat Energy Transmission Corporation Limited (GETCO). The case concerns two main issues: the extension of time for building and commissioning a permanent 220 KV GIS bay at the Kalavad sub-station, and the continued use of a temporary bay provided by GETCO until the permanent bay becomes operational.

M/s Morjar Renewables explained that delays in constructing the permanent bay are due to factors beyond their control. They requested permission to keep using the temporary bay until three other renewable energy companies—Cleanmax, Suzlon, and OP Wind—finish their own bay constructions at the same substation. The petitioner said their permanent bay is expected to be ready by June 30, 2025, but it cannot become functional until the bays of the other three generators are also completed. This is because all four bays connect to a common bus bar that must be energized together.

The petitioner also mentioned repeated attempts to organize a joint meeting with GETCO and the other renewable developers since January 13, 2025, to coordinate their work and ensure timely commissioning. They added that another company, M/s Jamnagar Renewables Two Private Limited, plans to evacuate power through their permanent bay, making the timely completion or continued use of the temporary bay more urgent.

On the other side, GETCO acknowledged the two issues but expressed reluctance to extend the temporary bay usage beyond March 31, 2025, which they had previously permitted. However, the Commission issued an interim order on March 29, 2025, allowing the petitioner to continue using the temporary bay until the next hearing. GETCO noted that if the petitioner completes their bay by the end of June, many delay reasons would no longer be relevant.

GETCO also pointed out that due to the sub-station’s current design, all four renewable energy developers must commission their GIS bays simultaneously for the system to operate. They requested permission from the Commission to hold a meeting and inspect the progress of all four generators’ work, as suggested by the petitioner. GETCO clarified that the temporary bay usage was granted only to Morjar Renewables and not to Jamnagar Renewables Two Private Limited.

During the hearing, the Commission asked GETCO to provide detailed information on several important matters. These included the energization date of the Kalavad 220 KV sub-station, its power transformation capacity and how it is allocated, a full list of dates and documents concerning connectivity and open access approvals for all developers connected to the sub-station, the status of transmission infrastructure work completed by the developers, and data on connectivity applications, allocation timelines, and power evacuation volumes. The Commission also wanted to know if there had been any cancellations or changes in connectivity and the reasons behind them.

Both parties completed their oral arguments and were given 10 days to submit written statements. The Commission reserved the final decision, while the previous interim order allowing temporary bay use remains in effect until further notice.

 

  • Related Posts

    Top Stories Of The Day: PM Surya Ghar Rules Simplified; Smart Grid Tender Opens; MNRE Adds New Solar Partners and More…

    The Rajasthan government has clarified the implementation of the PM Surya Ghar Muft Bijli Yojana’s “Give It Up” provision, addressing consumer concerns regarding subsidy eligibility and participation requirements. The clarification…

    Green Energy Stocks Drive Market Momentum As Sensex And Nifty End Higher (18 June 2026)

    Monitors display rising green energy stocks in the Indian market with a city skyline in the background. Indian equity markets ended higher on June 18, 2026, with benchmark indices maintaining…

    Have You Seen?

    Oil Falls to Lowest Since Start of Iran War After Ceasefire Deal Signed

    • June 18, 2026
    Oil Falls to Lowest Since Start of Iran War After Ceasefire Deal Signed

    Hormuz Reopening to Release Wave of Oil Supply, Depress Prices

    • June 18, 2026
    Hormuz Reopening to Release Wave of Oil Supply, Depress Prices

    US Signs $725 Million Loan Pact with Energy Fuels to Boost Domestic Rare Earth Production

    • June 18, 2026
    US Signs $725 Million Loan Pact with Energy Fuels to Boost Domestic Rare Earth Production

    Gulf Exporters’ Quest to Bypass Hormuz Will Reshape the Region: Bousso

    • June 18, 2026
    Gulf Exporters’ Quest to Bypass Hormuz Will Reshape the Region: Bousso

    Top Stories Of The Day: PM Surya Ghar Rules Simplified; Smart Grid Tender Opens; MNRE Adds New Solar Partners and More…

    • June 18, 2026
    Top Stories Of The Day: PM Surya Ghar Rules Simplified; Smart Grid Tender Opens; MNRE Adds New Solar Partners and More…

    Acme’s Oman green ammonia project set for $4.2bn expansion

    • June 18, 2026
    Acme’s Oman green ammonia project set for $4.2bn expansion

    Quantum Helium confirms 2.5% helium concentrations in Colorado

    • June 18, 2026
    Quantum Helium confirms 2.5% helium concentrations in Colorado

    Green Energy Stocks Drive Market Momentum As Sensex And Nifty End Higher (18 June 2026)

    • June 18, 2026
    Green Energy Stocks Drive Market Momentum As Sensex And Nifty End Higher (18 June 2026)

    Philippines And Indonesia Firms Accelerate Electric Transition Amid Infrastructure Concerns

    • June 18, 2026
    Philippines And Indonesia Firms Accelerate Electric Transition Amid Infrastructure Concerns

    Burckhardt supplies tech for Northern Lights first liquefied CO2 carrier

    • June 18, 2026
    Burckhardt supplies tech for Northern Lights first liquefied CO2 carrier