Holtec SMR project gets regulatory nod for early site work

Palisades SMR, LLC, a wholly-owned subsidiary of Holtec International, submitted the first part of a phased construction permit application for the dual-unit SMR-300 plant – Pioneer units 1 and 2 – to the US Nuclear Regulatory Commission (NRC) in December. This included a limited work authorisation (LWA) request. An LWA allows certain construction activities to commence before a construction permit or combined construction and operating licence has been issued. The NRC accepted it for review and docketed it in February.

The exemption granted by the NRC on 28 August authorises installation of permanent support-of-excavation (SOE) and cutoff-wall systems for Pioneer units 1 and 2. These systems include diaphragm walls, soldier-pile soil-mix walls, and perimeter cutoff walls, with tiebacks or struts as needed, Holtec said. These early works will establish the stable excavation and foundation conditions needed to support and accelerate subsequent plant construction following LWA approval. The SOE walls will eventually be “retired in place”, with the space between the walls and permanent structures backfilled to grade, it added.

Ahead of issuing the exemption, the NRC issued an Environmental Assessment and Finding of No Significant Impact for the authorised activities concluding that the granting of the exemption would not have any detrimental effects on the quality of the environment. The regulator determined that installation and retirement of the SOE walls would not adversely affect the safe design or siting of Pioneer units 1 and 2.

Holtec will perform geologic mapping and data collection during excavation, notify the NRC when the excavation is open for inspection, and account for the retired SOE walls in soil-structure interaction analyses. 

The SMR-300 is a pressurised water reactor producing about 300 MW of electrical power or 1050 MW of thermal power for process applications.

“The approval reflects Holtec’s disciplined, risk-informed approach to advancing the Palisades project and marks another step toward deploying 680 megawatts of clean, reliable energy through Pioneer Units 1 and 2,” the company said.

The Palisades site is also home to a single-unit 805 MWe pressurised water reactor, which closed in 2022 and Holtec is now in the process of bringing back into service.


An illustrative view of the permanent SOE system (Image: Holtec)

   

  • Related Posts

    Copenhagen Atomics to build deconversion facility

    Under the agreement, Urenco will help design a dedicated facility for the deconversion of uranium hexafluoride (UF6) into uranium tetrafluoride (UF4) at Copenhagen Atomics’ fuel facility in Copenhagen. Copenhagen Atomics…

    Belgian nuclear power plant negotiations extended

    Engie, the French parent of Belgian power company Electrabel, and the Belgian government began negotiations in late April. At that time, they said their Letter of Intent covered a proposed…

    Have You Seen?

    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    • November 5, 2026
    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    EU Not Planning to Resume Russian Gas Purchases

    • November 5, 2026
    EU Not Planning to Resume Russian Gas Purchases

    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    • November 5, 2026
    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    Iran Reports More Tanker Fires in Strait of Hormuz

    • November 5, 2026
    Iran Reports More Tanker Fires in Strait of Hormuz

    India to Require State Utilities to Add Energy Storage Capacity

    • November 5, 2026
    India to Require State Utilities to Add Energy Storage Capacity

    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    • November 5, 2026
    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    • November 5, 2026
    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    Samsung ramps up neon recycling to strengthen supply security

    • November 5, 2026
    Samsung ramps up neon recycling to strengthen supply security

    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    • November 5, 2026
    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    Air Products exits two Chinese coal gasification projects

    • November 5, 2026
    Air Products exits two Chinese coal gasification projects