Hot testing of second Zhangzhou unit completed

Wednesday, 9 April 2025

Hot testing of second Zhangzhou unit completed
Workers in the control room of Zhangzhou 2 (Image: CNNC)

Hot functional tests involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Carried out before the loading of nuclear fuel, such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

During the tests, the steam turbine generator of the unit was run to 1500 rpm for the first time and ran stably. “After inspection and confirmation by on-site staff, all systems on the conventional island ran smoothly during this run-in process, and all key technical indicators of the steam turbine met the acceptance standards, marking the successful completion of the non-nuclear run-in test,” China National Nuclear Corporation (CNNC) said.

CNNC added that completion of the hot testing of Zhangzhou 2 “lays a solid foundation for the subsequent work of nuclear fuel loading, grid-connected power generation and other work of the unit”.

Cold functional tests – which are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition – were completed earlier at Zhangzhou 2. The main purpose of those tests – which marked the first time the reactor systems were operated together with the auxiliary systems – was to verify the leak-tightness of the primary circuit.


Zhangzhou units 1 and 2 (Image: CNNC)

China’s Ministry of Ecology and Environment issued construction licences for Zhangzhou units 1 and 2 on 9 October 2019 to CNNC-Guodian Zhangzhou Energy Company, the owner of the Zhangzhou nuclear power project, which was created by CNNC (51%) and China Guodian Corporation (49%) in 2011. Construction of unit 1 began one week after the issuance of the construction licence, with that of unit 2 starting in September 2020.

In September 2022, China’s State Council approved the construction of two further Hualong One units as Phase II of the Zhangzhou plant. First concrete for the nuclear island of unit 3 was poured in February last year, with that for unit 4 following in September.

Six Hualong One units are planned for the Zhangzhou site.

“Currently, unit 1 has been put into commercial operation, and unit 2 is scheduled to be put into commercial operation in the fourth quarter of this year,” CNNC said. “Units 3 and 4 have started construction in 2024, and the preliminary work of units 5 and 6 is being carried out in an orderly manner.”

   

  • Related Posts

    The challenge of securing uranium from seawater – podcast

    There’s enough uranium in the world’s oceans to power humans’ current energy needs for hundreds of thousands of years. The challenge is finding a way to extract it at a…

    Radiant microreactor selected for deployment by US Navy

    Radiant has already been selected to partner with the US Army and the US Air Force in their microreactor deployment programmes, making it the only company to be selected by all…

    Have You Seen?

    India’s Middle East Oil Imports Jumped 32% in September

    • October 22, 2026
    India’s Middle East Oil Imports Jumped 32% in September

    Grid Constraints Curtailed 119 GW of Renewables in India in September

    • October 22, 2026
    Grid Constraints Curtailed 119 GW of Renewables in India in September

    European Natural Gas Prices Rise on Middle East Escalation

    • October 22, 2026
    European Natural Gas Prices Rise on Middle East Escalation

    Delorean advances Australia biomethane project towards first gas injection

    • October 22, 2026
    Delorean advances Australia biomethane project towards first gas injection

    Iran Claims Seven Ships Hit in Persian Gulf as Oil Prices Surge

    • October 22, 2026
    Iran Claims Seven Ships Hit in Persian Gulf as Oil Prices Surge

    Record Fuel Prices Accelerate Europe’s EV Sales

    • October 22, 2026
    Record Fuel Prices Accelerate Europe’s EV Sales

    Waga Energy launches Indiana landfill RNG facility

    • October 22, 2026
    Waga Energy launches Indiana landfill RNG facility

    DAC project in Kenya targets tens of kilotonnes of CO2 for e-fuel production

    • October 22, 2026
    DAC project in Kenya targets tens of kilotonnes of CO2 for e-fuel production

    Iraq Removes Customs Duties On Imported Solar Energy Systems To Boost Renewable Energy Adoption

    • October 22, 2026
    Iraq Removes Customs Duties On Imported Solar Energy Systems To Boost Renewable Energy Adoption

    Solarcentury Africa Commissions 34.5 MWp Mailo 2 Solar Plant in Zambia, Raising Operational Capacity to 59.5 MWp

    • October 22, 2026
    Solarcentury Africa Commissions 34.5 MWp Mailo 2 Solar Plant in Zambia, Raising Operational Capacity to 59.5 MWp