Hot testing of second Zhangzhou unit completed

Wednesday, 9 April 2025

Hot testing of second Zhangzhou unit completed
Workers in the control room of Zhangzhou 2 (Image: CNNC)

Hot functional tests involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Carried out before the loading of nuclear fuel, such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

During the tests, the steam turbine generator of the unit was run to 1500 rpm for the first time and ran stably. “After inspection and confirmation by on-site staff, all systems on the conventional island ran smoothly during this run-in process, and all key technical indicators of the steam turbine met the acceptance standards, marking the successful completion of the non-nuclear run-in test,” China National Nuclear Corporation (CNNC) said.

CNNC added that completion of the hot testing of Zhangzhou 2 “lays a solid foundation for the subsequent work of nuclear fuel loading, grid-connected power generation and other work of the unit”.

Cold functional tests – which are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition – were completed earlier at Zhangzhou 2. The main purpose of those tests – which marked the first time the reactor systems were operated together with the auxiliary systems – was to verify the leak-tightness of the primary circuit.


Zhangzhou units 1 and 2 (Image: CNNC)

China’s Ministry of Ecology and Environment issued construction licences for Zhangzhou units 1 and 2 on 9 October 2019 to CNNC-Guodian Zhangzhou Energy Company, the owner of the Zhangzhou nuclear power project, which was created by CNNC (51%) and China Guodian Corporation (49%) in 2011. Construction of unit 1 began one week after the issuance of the construction licence, with that of unit 2 starting in September 2020.

In September 2022, China’s State Council approved the construction of two further Hualong One units as Phase II of the Zhangzhou plant. First concrete for the nuclear island of unit 3 was poured in February last year, with that for unit 4 following in September.

Six Hualong One units are planned for the Zhangzhou site.

“Currently, unit 1 has been put into commercial operation, and unit 2 is scheduled to be put into commercial operation in the fourth quarter of this year,” CNNC said. “Units 3 and 4 have started construction in 2024, and the preliminary work of units 5 and 6 is being carried out in an orderly manner.”

   

  • Related Posts

    Bruce Power to share nuclear knowledge with Energy Alberta

    The Bruce Power site in Ontario was home to Canada’s first commercial reactor, Douglas Point, which operated from 1967 to 1984, and its current fleet of eight Candu pressurised heavy…

    Adani launches nuclear subsidiary

    Adani Power has notified the National Stock Exchange of India Limited that its wholly owned Adani Atomic Energy Limited subsidiary incorporated Coastal-Maha Atomic Energy Limited on 13 April. The Certificate of…

    Have You Seen?

    Ukraine Strike Halts Oil Processing at Novokuibyshevsk Refinery

    • April 22, 2026
    Ukraine Strike Halts Oil Processing at Novokuibyshevsk Refinery

    Oilfield Service Firm Halliburton is Discussing Commercial Terms With Customers for Venezuela Operations

    • April 22, 2026
    Oilfield Service Firm Halliburton is Discussing Commercial Terms With Customers for Venezuela Operations

    North Dakota Crude Output to Rise as Operators Eye High Oil Prices

    • April 22, 2026
    North Dakota Crude Output to Rise as Operators Eye High Oil Prices

    China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    • April 22, 2026
    China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    Norway Pumps Near Capacity as Spare Output Buffer Disappears

    • April 21, 2026
    Norway Pumps Near Capacity as Spare Output Buffer Disappears

    Sanctioned Iranian VLCC Crosses Hormuz Line Hours Before Ceasefire Deadline

    • April 21, 2026
    Sanctioned Iranian VLCC Crosses Hormuz Line Hours Before Ceasefire Deadline

    Activists Sue Shell Over Emissions, Again

    • April 21, 2026
    Activists Sue Shell Over Emissions, Again

    Long-Haul Flight Fares Soar as Iran War Hits European Aviation Hard

    • April 21, 2026
    Long-Haul Flight Fares Soar as Iran War Hits European Aviation Hard

    Iran, US Talks Hit Impasse as Truce Nears Expiry

    • April 21, 2026
    Iran, US Talks Hit Impasse as Truce Nears Expiry

    US Crude and Fuel Exports Surge to Record Highs, But it’s Not Enough: Russell

    • April 21, 2026
    US Crude and Fuel Exports Surge to Record Highs, But it’s Not Enough: Russell