In Pictures: Akkuyu 2’s polar crane installed

The 282-tonne bridge is part of the polar crane, a circular overhead crane which is mounted under the reactor building’s inner containment dome. Its circular design means that it can transport heavy items within the reactor building.


(Image: Akkuyu Nuclear)

It will be used for handling large equipment, reactor plant maintenance, and fuel reloading. The total weight of the crane, when all parts are included, is approximately 500 tonnes.


The crane’s trolley moves along the bridge, and the crane itself rotates along a circular rail above the reactor shaft ​(Image: Akkuyu Nuclear)

Sergei Butckikh, Akkuyu Nuclear CEO, said: “Alongside the pre-commissioning operations at unit 1, construction, thermal and mechanical equipment installation works are being intensively carried out at the other Akkuyu NPP Units. Recently, the builders have completed the concreting of the fifth tier of the inner containment. The operation took about six hours, and 240 cubic metres of self-sealing concrete were laid continuously. After the structure acquired strength, we installed the polar crane bridge metal structures.”

Akkuyu Nuclear added: “The installation of the polar crane structures and the further installation of the safety system tanks using the Open Top method will provide for preparations for the installation of the inner containment dome of Akkuyu NPP Unit 2 reactor compartment.”

Background

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December 2023. The aim is for unit 1 to begin supplying Turkey’s energy system during 2026. When the 4,800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs. All four units are under construction – first concrete for the fourth unit was poured in July 2022.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    • August 17, 2026
    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    • August 17, 2026
    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    AWG appoints Vice-President of Operations for the North Region

    • August 17, 2026
    AWG appoints Vice-President of Operations for the North Region

    Tencent drives carbon utilisation ‘out of the lab’

    • August 17, 2026
    Tencent drives carbon utilisation ‘out of the lab’

    US CO2 Outlook Report H1 2026

    • August 17, 2026
    US CO2 Outlook Report H1 2026

    U.S. West Coast Refiners Tap Malaysian Supply

    • August 17, 2026
    U.S. West Coast Refiners Tap Malaysian Supply

    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    • August 17, 2026
    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War