Judge Says Dominion Energy Can Resume Wind Project U.S. Halted

The U.S. offshore wind industry has faced other difficulties, including soaring inflation and supply chain snarls

Bloomberg News

Dominion said in court papers that it is losing about US$5 million a day on vessel contracts alone because of the


Get the Latest US Focused Energy News Delivered to You! It’s FREE:


Dominion Energy Inc. can restart construction of a wind project off the coast of Virginia while it continues a legal fight over the Trump administration’s order to stop the US$11 billion development, a federal judge ruled.

United States District Judge Jamar Walker in Norfolk, Virginia, issued a preliminary injunction Friday. It blocks the government from enforcing its stop-work order after Dominion claimed it was suffering irreparable harm and losing millions of dollars every day the project sits idle. Walker is the third federal judge this week to allow a halted wind development to resume construction.

The Virginia unit of Dominion Energy is among several companies suing the U.S. Department of the Interior over a Dec. 22 order suspending five East Coast wind projects for 90 days over unspecified national security concerns. But the developers sued, with some winning temporary reprieves. Earlier this week, a federal judge ruled Norway’s Orsted A/S can resume development of its project off Rhode Island while its lawsuit proceeds and a different judge issued a similar ruling for Equinor ASA’s Empire Wind project near New York.

The Virginia judge echoed concerns expressed in the other cases. Walker, who was appointed by former President Joe Biden, said the government had failed to demonstrate that the “national security risk is so imminent” that the Dominion project should be halted. He added that department’s order was likely arbitrary and capricious and that further delays would cause irreparable harm to the company.

The White House didn’t immediately comment on the decision.

Dominion shares rose 0.6 per cent after the ruling to touch an intraday high of US$61.50.

President Donald Trump has sought to aggressively thwart the growth of the industry as he rolls back Biden-era climate policies and champions fossil fuels. This latest move also comes after Trump froze permitting for all wind projects on federal land and oceans on his first day back in office, though a federal judge ruled that his decree was illegal.

The U.S. offshore wind industry has faced other difficulties, including soaring inflation and supply chain snarls in recent years. And even after some of those problems subsided, developers have since been hit by rising costs from Trump’s tariffs. All told, that’s led to project cancellations, delays and writedowns.

Dominion said in court papers that it is losing about US$5 million a day on vessel contracts alone because of the construction halt, with more costs from idled workers and contractual penalties. The company says more than two-thirds of the expected US$11.2 billion total cost has already been spent on the Virginia project, which was expected to be completed this year and provide power for 660,000 homes.

Alternative investment firm Stonepeak Partners acquired a 50 per cent stake in the wind project in 2024 and has agreed to fund 50 per cent of project costs up to US$11.3 billion, with additional sharing of costs in excess of that amount. According to analysts at Jefferies Financial Group Inc., Dominion and Stonepeak are sharing about US$225 million in monthly costs associated with the stop-work order.

Dominion said in a statement last month that the project is “essential for American national security and meeting Virginia’s dramatically growing energy needs.” That includes electricity for the “world’s largest concentration of data centres” and many federal government and military facilities, including the Pentagon, attorneys for the company wrote in court records.

In a court filing, the operator of the 13-state power grid that includes Virginia said the Dominion project is important to meeting the rapidly increasing electricity demand and that further delay will cause “irreparable harm” to the 67 million people who live in the region.

The U.S. government has argued the move to pause construction was valid because it was done for national security reasons. The stop-work order adequately explained that the Department of Defense provided new classified information about advances in “adversary technologies” that “could raise national security issues with offshore wind projects,” government lawyers said in a December court filing.

Attorneys for Dominion contend in court papers the agency’s reasons for the pause weren’t “plausible” because national security considerations were already addressed during the permitting process. They also claimed the government infringed on Dominion’s constitutional due process rights by failing to give notice and an opportunity for a hearing before issuing the order.

—With assistance from Mark Chediak and Skylar Woodhouse.

Share This:


More News Articles

 

  • Related Posts

    Top US Refiners See Profits Soar, Step Up Investor Rewards

    By Nicole Jao Top refiners post combined second-quarter profit of $12.6 billion Capital returns to shareholders hit $6.3 billion in second quarter TD Cowen sees Marathon and Valero each repurchasing…

    BofA to Plow $250 Billion Into Critical Infrastructure Projects

    By Paula Seligson and Katherine Doherty Bank of America Corp. unveiled a $250 billion initiative to invest in critical infrastructure across the US over the next year, joining its peers…

    Have You Seen?

    ADBA says UK energy plan overlooks biomethane cost savings

    • September 30, 2026
    ADBA says UK energy plan overlooks biomethane cost savings

    Oil Prices Climb as Trump Rules Out Easing Iran Sanctions

    • September 30, 2026
    Oil Prices Climb as Trump Rules Out Easing Iran Sanctions

    JP Morgan, Goldman Diverge on Hormuz Oil Flow Estimates

    • September 30, 2026
    JP Morgan, Goldman Diverge on Hormuz Oil Flow Estimates

    India Boosts Middle East Oil Imports, Cuts Russian Flows

    • September 30, 2026
    India Boosts Middle East Oil Imports, Cuts Russian Flows

    WTI Discount to Brent Deepens

    • September 30, 2026
    WTI Discount to Brent Deepens

    Indian Green Energy Stocks Trade Mixed As Renewable Energy Shares See Divergent Moves (30 September 2026)

    • September 30, 2026
    Indian Green Energy Stocks Trade Mixed As Renewable Energy Shares See Divergent Moves (30 September 2026)

    ADNEC Group Expands Clean Energy Initiatives With 5 MWp Rooftop Solar Project In UAE

    • September 30, 2026
    ADNEC Group Expands Clean Energy Initiatives With 5 MWp Rooftop Solar Project In UAE

    AM Green Secures €585 Million 10-Year Renewable Ammonia Supply Deal to Germany Through H2Global Auction

    • September 30, 2026
    AM Green Secures €585 Million 10-Year Renewable Ammonia Supply Deal to Germany Through H2Global Auction

    Sono-Tek Secures Record $7.19 Million Order for 10 Clean Energy Coating Systems

    • September 30, 2026
    Sono-Tek Secures Record $7.19 Million Order for 10 Clean Energy Coating Systems

    South Africa Launches Consultation On Revised Electricity Pricing Policy And Market Reforms

    • September 30, 2026
    South Africa Launches Consultation On Revised Electricity Pricing Policy And Market Reforms