NextEra updates NRC on Duane Arnold plans

The company presented an overview of the current status and its plans for the proposed restart of the shuttered plant in submitted to the US Nuclear Regulatory Commission (NRC) ahead of a 7 August Pre-Submittal Meeting.

The 610 MWe boiling water reactor plant, owned and operated by NextEra Energy Duane Arnold, LLC in Linn County, Iowa, commenced commercial operation in 1974. Although currently licensed for operations until 2034, the Duane Arnold plant ceased operations in 2020 and is currently “idled and in decommissioning status”, but in January, the company submitted documents including a restart overview and regulatory path to reauthorisation of power operations.

Since it was shut, all the plant’s used fuel has been transferred to its Independent Spent Fuel Storage Installation, and most major plant systems have been drained and deenergised. Training and administrative buildings have been removed, as have the mechanical draft cooling towers, and generator output transformer and in-scope transmission lines, but the main power block buildings remain intact.

Planned restart activities will restore the plant to its previous operating licence condition at 2020 shutdown. Planned plant modifications include new cooling towers, restoration of in-scope transmission lines, new office and warehouse buildings, and upgrades to the sewage treatment system upgrade. Plans also include dredging of the water intake from the Cedar River.

“Under NEPA [the National Environmental Policy Act], it is anticipated that NRC will prepare an Environmental Assessment (EA) for this restart,” the company said in the slides. NextEra Energy Duane Arnold, LLC will coordinate with the NRC Environmental Project Manager regarding the need for an environmental review document, and the subject areas to cover; and “submit an environmental review document (tentatively in October 2025) that focuses on restart activities useful for the NRC’s NEPA review”.

It anticipates that a final EA and Finding of No Significant Impact “will be issued within 12 months of acceptance of an environmental submittal”.

NextEra Energy recently filed a request with the US Federal Energy Regulatory Commission seeking to reclaim interconnection rights that were previously transferred from the shut down Duane Arnold nuclear power plant in Iowa to a solar energy project: about 40 acres of the Duane Arnold site are now occupied by a solar farm.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Recalibration and resilience to go the distance

    • April 11, 2026
    Recalibration and resilience to go the distance

    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    • April 11, 2026
    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022