Nuclear island completed at third Haiyang unit

China National Nuclear Corporation subsidiary CNNC 24 completed the concrete pouring of the inner and outer ring walls and top plate of the CB20 module on 20 October, “laying a solid foundation for the subsequent containment sealing test and hot functional test”.

The containment water tank, the final module, was hoisted into place on top of the containment building roof at Haiyang 3 on 4 August. The hoisting of the module – measuring 26 metres in diameter, 10 metres in height and weighing about 419 tonnes – took one hour and 52 minutes to complete.

The CB-20 module will store more than 3,000 tonnes of water, which can be used to help cool the reactor in an emergency. The water can also be directed into the reactor’s used fuel pool, while the tank itself can be refilled from water stored elsewhere on site. The tank is part of the plant’s passive safety systems which require no operator actions to mitigate potential emergency situations, using natural forces such as gravity, natural circulation and compressed gas to achieve their safety function. In conjunction with other passive safety features, the CB-20 module can maintain unit safety for 72 hours without human intervention.

The construction of two CAP1000 reactors – the Chinese version of the Westinghouse AP1000 – at each of the Haiyang, Sanmen and Lufeng nuclear power plant sites in China was approved by the country’s State Council on 20 April 2022. The approvals were for Haiyang 3 and 4, Sanmen units 3 and 4 and units 5 and 6 of the Lufeng plant. The Sanmen and Haiyang plants are already home to two AP1000 units each.

Unit 1 of the Haiyang plant entered commercial operation in October 2018, with unit 2 following in January 2019.

The first safety-related concrete was poured for the nuclear island of Haiyang unit 3 in July 2022, and in March the outer steel dome of the nuclear island containment building was hoisted into place. Construction of Haiyang 4 began in April last year. The planned construction period for Haiyang 3 and 4 was 56 months, with the two units scheduled to be fully operational in 2027.

   

  • Related Posts

    Kaleidos microreactor begins journey to Idaho

    “We said we’d make a microreactor that is transportable by land, sea and air. We did. Kaleidos is traveling more than 1,000 miles on a trailer bed,” the company said. …

    Detritiation facility reopens at Culham

    In the last three years of plasma operations, the Joint European Torus’s (JET’s) deuterium-tritium experiments resulted in residual tritium being retained within the tokamak’s walls and internal components. This reflected…

    Have You Seen?

    Kino Aski LNG targets North America-Europe energy corridor

    • August 19, 2026
    Kino Aski LNG targets North America-Europe energy corridor

    SJVN Green Energy Invites Bids For 1,000 MW Solar Projects In Punjab And Rajasthan

    • August 19, 2026
    SJVN Green Energy Invites Bids For 1,000 MW Solar Projects In Punjab And Rajasthan

    South Africa Unveils Revised Electricity Pricing Policy To Cut Costs And Boost Market Competition

    • August 19, 2026
    South Africa Unveils Revised Electricity Pricing Policy To Cut Costs And Boost Market Competition

    Jeff Currie: Forget $91 Brent, The Real Crisis Is $170 Diesel

    • August 19, 2026
    Jeff Currie: Forget $91 Brent, The Real Crisis Is $170 Diesel

    Aramco Puts VLCCs Back Into Hormuz After Three-Week Pause

    • August 19, 2026
    Aramco Puts VLCCs Back Into Hormuz After Three-Week Pause

    Distillate Stocks Sink Further as U.S. Crude Inventories Barely Budge

    • August 19, 2026
    Distillate Stocks Sink Further as U.S. Crude Inventories Barely Budge

    Oil Prices Rise for Fourth Day as Hormuz Traffic Slows

    • August 19, 2026
    Oil Prices Rise for Fourth Day as Hormuz Traffic Slows

    UERC Proposes 2026 DSM Rules To Strengthen Grid Discipline And Financial Settlement In Uttarakhand

    • August 19, 2026
    UERC Proposes 2026 DSM Rules To Strengthen Grid Discipline And Financial Settlement In Uttarakhand

    Skymax Infrapower Signs MoU With Odisha Government for INR 5,000 Crore Solar Manufacturing Facility

    • August 19, 2026
    Skymax Infrapower Signs MoU With Odisha Government for INR 5,000 Crore Solar Manufacturing Facility

    JVVNL Floats Tender For 2 MW/4 MWh Distributed BESS Pilot Project In Rajasthan

    • August 19, 2026
    JVVNL Floats Tender For 2 MW/4 MWh Distributed BESS Pilot Project In Rajasthan