Nuclear island completed at third Haiyang unit

China National Nuclear Corporation subsidiary CNNC 24 completed the concrete pouring of the inner and outer ring walls and top plate of the CB20 module on 20 October, “laying a solid foundation for the subsequent containment sealing test and hot functional test”.

The containment water tank, the final module, was hoisted into place on top of the containment building roof at Haiyang 3 on 4 August. The hoisting of the module – measuring 26 metres in diameter, 10 metres in height and weighing about 419 tonnes – took one hour and 52 minutes to complete.

The CB-20 module will store more than 3,000 tonnes of water, which can be used to help cool the reactor in an emergency. The water can also be directed into the reactor’s used fuel pool, while the tank itself can be refilled from water stored elsewhere on site. The tank is part of the plant’s passive safety systems which require no operator actions to mitigate potential emergency situations, using natural forces such as gravity, natural circulation and compressed gas to achieve their safety function. In conjunction with other passive safety features, the CB-20 module can maintain unit safety for 72 hours without human intervention.

The construction of two CAP1000 reactors – the Chinese version of the Westinghouse AP1000 – at each of the Haiyang, Sanmen and Lufeng nuclear power plant sites in China was approved by the country’s State Council on 20 April 2022. The approvals were for Haiyang 3 and 4, Sanmen units 3 and 4 and units 5 and 6 of the Lufeng plant. The Sanmen and Haiyang plants are already home to two AP1000 units each.

Unit 1 of the Haiyang plant entered commercial operation in October 2018, with unit 2 following in January 2019.

The first safety-related concrete was poured for the nuclear island of Haiyang unit 3 in July 2022, and in March the outer steel dome of the nuclear island containment building was hoisted into place. Construction of Haiyang 4 began in April last year. The planned construction period for Haiyang 3 and 4 was 56 months, with the two units scheduled to be fully operational in 2027.

   

  • Related Posts

    US uranium production up again

    US mines produced 1,388,000 pounds U3O8 (534 tU) in 2025, up from 677,000 pounds U3O8 in 2024. The 2025 figure was the highest since 2016’s production of 2,545,000 pounds, according…

    Sogin begins re-encapsulation of uranium-thorium fuel

    Between 1968 and 1970, 84 elements of irradiated fuel from the uranium-thorium cycle from the Elk River experimental reactor in Minnesota, USA, were shipped to the Rotondella plant for reprocessing…

    Have You Seen?

    Qatar Offers First Crude Loadings to Buyers Since War Began

    • June 26, 2026
    Qatar Offers First Crude Loadings to Buyers Since War Began

    China’s Crude Imports Set to Hit Weakest Level Since 2016

    • June 26, 2026
    China’s Crude Imports Set to Hit Weakest Level Since 2016

    Kazakhstan Cuts Gas Output after Drone Strike on Russian Processing Plant

    • June 26, 2026
    Kazakhstan Cuts Gas Output after Drone Strike on Russian Processing Plant

    Hormuz Shipping Confidence Is Still Shaky

    • June 26, 2026
    Hormuz Shipping Confidence Is Still Shaky

    Saudi Arabia Set to Slash Oil Prices as Hormuz Reopens

    • June 26, 2026
    Saudi Arabia Set to Slash Oil Prices as Hormuz Reopens

    Baghdad Hosting EU Energy Talks After Iraq Floats OPEC Exit

    • June 26, 2026
    Baghdad Hosting EU Energy Talks After Iraq Floats OPEC Exit

    US electricity demand to rise 21% by 2030

    • June 26, 2026
    US electricity demand to rise 21% by 2030

    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    • June 26, 2026
    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    • June 26, 2026
    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    Podcast | AI, semiconductor growth & the future of specialty gases

    • June 26, 2026
    Podcast | AI, semiconductor growth & the future of specialty gases