Petition For Extension And Interim Relief In 100 MW Wind-Solar Hybrid Project In Gujarat Due To Delays In Commissioning

Representational image. Credit: Canva

The petition under Section 86 (1) (c) & (f) of the Electricity Act, 2003, seeks an extension for the commissioning of the evacuation line, bays, and metering system for a 100 MW Wind Solar Hybrid Project in Gujarat. The petitioner, a renewable energy developer, had been given Stage-I connectivity in April 2023 and Stage-II connectivity in July 2023. However, delays in finalizing agreements for sharing bays with other developers have caused setbacks. The petitioner approached the Gujarat Energy Transmission Corporation (GETCO) for clarification, but due to unforeseen delays, the project may face penalties if not commissioned by January 2025.

The petitioner argues that, under the provisions of the Wind Solar Tariff Order, extensions are possible in cases of unforeseen delays. The project’s progress was stalled due to missing details from GETCO regarding the substation bays and delays in finalizing agreements with lead generators like Morjar Renewables Pvt. Ltd. The petitioner’s request to GETCO for status as a lead generator was delayed by a legal dispute between GETCO and Morjar Renewables. Meanwhile, discussions with Suzlon Global Services also failed to progress, and the project faced delays due to these issues.

During the hearing, GETCO was asked to provide crucial information related to the energization of the Kalavad 220 KV substation, including available power transformation capacity, the number of bays, and the procedures followed for sharing bays with developers. Other points raised during the hearing included the specifics of GETCO’s allocation of bays to private renewable energy developers and whether approval from the Commission is necessary for such allocation.

The respondent agreed to provide further submissions on these issues by January 22, 2025. The petitioner also filed an interlocutory application requesting interim relief, asking the Commission to prevent GETCO from taking coercive actions, such as revoking connectivity or encashing the bank guarantee, until the matter is resolved. The next hearing is scheduled for January 23, 2025. The case remains under review, with both parties expected to submit additional documents to clarify these issues.

 

  • Related Posts

    Protests Erupt Over Renewable Energy Project Near Indo-Pak Border, Security Concerns Raised

    Representational image. Credit: Canva India’s clean energy ambitions have taken center stage with the approval of a large-scale renewable energy project in Khavda, Gujarat. The project, which will harness both…

    CERC Considers Transmission License For Barmer I Project To Evacuate 5.5 GW Renewable Energy From Rajasthan REZ

    Representational image. Credit: Canva On 12th March 2025, the Central Electricity Regulatory Commission (CERC) issued an order in response to the petition which was filed by Barmer I Transmission Limited,…

    Have You Seen?

    Protests Erupt Over Renewable Energy Project Near Indo-Pak Border, Security Concerns Raised

    • March 13, 2025
    Protests Erupt Over Renewable Energy Project Near Indo-Pak Border, Security Concerns Raised

    CERC Considers Transmission License For Barmer I Project To Evacuate 5.5 GW Renewable Energy From Rajasthan REZ

    • March 13, 2025
    CERC Considers Transmission License For Barmer I Project To Evacuate 5.5 GW Renewable Energy From Rajasthan REZ

    Value Leadership! Hi-MO 9’s Power Generation Demonstration in Hainan Achieves a Gain of Over 30%

    • March 13, 2025
    Value Leadership! Hi-MO 9’s Power Generation Demonstration in Hainan Achieves a Gain of Over 30%

    India’s Solar Capacity Surpasses 102.566 MW, Contributing Over 61% to the Country’s Renewable Energy Mix

    • March 13, 2025
    India’s Solar Capacity Surpasses 102.566 MW, Contributing Over 61% to the Country’s Renewable Energy Mix

    Recurrent Energy and Qualcomm Sign PPA to Advance Renewable Energy in Spain

    • March 13, 2025
    Recurrent Energy and Qualcomm Sign PPA to Advance Renewable Energy in Spain

    Gunkul Engineering Appoints Naruechon Dhumrongpiyawut as New CEO, Targets Aggressive Growth in Renewable Energy

    • March 13, 2025
    Gunkul Engineering Appoints Naruechon Dhumrongpiyawut as New CEO, Targets Aggressive Growth in Renewable Energy

    ITI Limited Invites Proposals For 10 MW Solar Power Plant In Prayagraj

    • March 13, 2025
    ITI Limited Invites Proposals For 10 MW Solar Power Plant In Prayagraj

    Shri Anupam Shukla, Director of UPNEDA and MD of UP Renewable & EV Infrastructure Ltd., to be Guest of Honor at UPEX 2025

    • March 13, 2025
    Shri Anupam Shukla, Director of UPNEDA and MD of UP Renewable & EV Infrastructure Ltd., to be Guest of Honor at UPEX 2025

    SECI Wins Double Honours At Governancenow 11th PSU Awards

    • March 13, 2025
    SECI Wins Double Honours At Governancenow 11th PSU Awards

    UAE and Denmark Sign MoU on Sustainable Agriculture and Food Systems

    • March 13, 2025
    UAE and Denmark Sign MoU on Sustainable Agriculture and Food Systems