TerraPower submits Natrium for UK regulatory assessment

The Generic Design Assessment – or GDA – process allows UK regulators to assess the safety, security and environmental implications of new reactor designs, separately from applications to build them at specific sites. The three-step process – which is voluntary – is carried out by the UK’s regulators: the Office for Nuclear Regulation (ONR), the Environment Agency (EA) and Natural Resources Wales (NRW). Successful completion of the process culminates in the issue of a Design Acceptance Confirmation from the ONR and a Statement of Design Acceptability from the EA.

TerraPower formally notified UK regulators of its plans to begin the GDA approval process for its Natrium sodium-cooled fast reactor in May, and in September, it announced plans to evaluate potential UK sites for the Natrium reactor in partnership with KBR Inc.

Submission of the Natrium technology into the GDA process is a substantial step towards bringing the reactor and energy storage system to the UK, TerraPower President and CEO Chris Levesque said. “TerraPower is committed to delivering Natrium units across the globe, and our industry-leading regulatory team is setting the standard on how to license and deploy advanced nuclear technologies. We look forward to working with the UK government as we work through the review process,” he added.

The first-of-a-kind Natrium sodium-cooled fast reactor plant is to be built in the USA at Kemmerer, Wyoming. TerraPower submitted an application to the US regulator in March 2024 for a construction permit for Kemmerer Unit 1. The US Nuclear Regulatory Commission recently completed its Environmental Impact Statement for the project and recommended that a construction permit be issued. Construction of the non-nuclear portions of the site are already underway.

The UK’s GDA process will build on the company’s experience and efforts in the USA, and will allow for TerraPower to establish deployment timelines for Natrium sites in the country, the company said.

In September, UK and US nuclear regulators announced a new initiative to streamline regulation and accelerate the deployment of advanced nuclear reactors across UK and US markets. The Atlantic Partnership for Advanced Nuclear Energy includes commitments from the regulators to significantly accelerate timeframes for decisions, by working much closer together on specific technologies where timeframes align.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Peak Energy Korea Starts Power Supply From 1.19 MW Youngjin SP Rooftop Solar Plant After Successful Completion

    • April 13, 2026
    Peak Energy Korea Starts Power Supply From 1.19 MW Youngjin SP Rooftop Solar Plant After Successful Completion

    Electrification Key to India’s Energy Security, Says Incoming ELECRAMA 2027 Chairman

    • April 13, 2026
    Electrification Key to India’s Energy Security, Says Incoming ELECRAMA 2027 Chairman

    APTEL Orders Interest on Refund in Solar Delay Case, Limits Scope of Review Petition

    • April 13, 2026
    APTEL Orders Interest on Refund in Solar Delay Case, Limits Scope of Review Petition

    AdventEnergy Aggregates 746 kW For Two Frabelle Cold Storage Facilities In Navotas Under ERC’s Retail Aggregation Program To Deliver Lower-Priced Power

    • April 13, 2026
    AdventEnergy Aggregates 746 kW For Two Frabelle Cold Storage Facilities In Navotas Under ERC’s Retail Aggregation Program To Deliver Lower-Priced Power

    Telangana Electricity Regulatory Commission Tariff Order FY27 Balancing DISCOM Finances, Consumer Tariffs, And Power Supply Stability

    • April 13, 2026
    Telangana Electricity Regulatory Commission Tariff Order FY27 Balancing DISCOM Finances, Consumer Tariffs, And Power Supply Stability

    NISO Reduces Transmission Losses to 7.05%, Advances Grid Stability Reforms

    • April 13, 2026
    NISO Reduces Transmission Losses to 7.05%, Advances Grid Stability Reforms

    EVN, Quang Tri Authorities Review Progress of Power and Grid Projects in Hanoi

    • April 13, 2026
    EVN, Quang Tri Authorities Review Progress of Power and Grid Projects in Hanoi

    HPERC Finalizes 2026 Conduct Of Business Amendment, Retains Revised Filing Fee Structure Despite Stakeholder Objections In Himachal Pradesh

    • April 13, 2026
    HPERC Finalizes 2026 Conduct Of Business Amendment, Retains Revised Filing Fee Structure Despite Stakeholder Objections In Himachal Pradesh

    OERC Draft 2026 Introduces Renewable Consumption Obligation And Boosts Distributed Solar Adoption In Odisha

    • April 13, 2026
    OERC Draft 2026 Introduces Renewable Consumption Obligation And Boosts Distributed Solar Adoption In Odisha

    PM Narendra Modi Highlights Record Solar Capacity Addition in India

    • April 13, 2026
    PM Narendra Modi Highlights Record Solar Capacity Addition in India