Third unit at Changjiang site commissioned

First concrete was poured for the base slab of unit 3’s nuclear island in March 2021, with that of unit 4 being poured in the December of that year. Changjiang Phase II – units 3 and 4 – represents a total estimated investment of CNY40 billion (USD5.9 billion), according to China Huaneng, which holds a 51% share in the project. Both units are scheduled to be fully operational in early 2027.

Changjiang 3 achieved first criticality – a sustained chain reaction – on 10 July this year and was connected to the grid on 1 August.

The Changjiang nuclear site is already home to two operating CNP-600 PWRs – Changjiang 1 and 2 – which entered commercial operation in 2015 and 2016, respectively. In 2021, China National Nuclear Corporation (CNNC) also began construction of a demonstration ACP100 small modular reactor at the site. The multi-purpose 125 MWe PWR – also referred to as the Linglong One – is designed for electricity production, heating, steam production or seawater desalination. It is currently undergoing pre-commissioning tests.

The island province of Hainan is China’s southernmost point. Energy policies published in 2019 by Hainan Province Development and Reform Commission specify that nuclear power will become the primary source of electricity for the island, which has a population of close to 10 million.

“Upon full completion, the Phase II project is expected to generate 18 billion kilowatt-hours of clean electricity annually, replacing more than 6.32 million metric tons of standard coal and reducing carbon dioxide emissions by about 11.6 million tons every year,” Liu Bin, general manager of Huaneng Hainan Changjiang Nuclear Power Company Ltd was quoted as saying by China Daily. “This will provide a clean, safe, and efficient power supply to anchor the construction of the Hainan Free Trade Port while accelerating the nation’s progress toward its dual-carbon targets.”

Changjiang 3 becomes the first large-scale power reactor that China Huaneng Group has constructed and operated as the controlling stakeholder. The company holds a controlling stake in the demonstration High Temperature Gas-Cooled Reactor-Pebble-bed Module (HTR-PM) at the Shidaowan site in Shandong Province, which entered commercial operation in December 2023. China Huaneng also holds minority stakes in a number of other units.

   

  • Related Posts

    Copenhagen Atomics to build deconversion facility

    Under the agreement, Urenco will help design a dedicated facility for the deconversion of uranium hexafluoride (UF6) into uranium tetrafluoride (UF4) at Copenhagen Atomics’ fuel facility in Copenhagen. Copenhagen Atomics…

    Belgian nuclear power plant negotiations extended

    Engie, the French parent of Belgian power company Electrabel, and the Belgian government began negotiations in late April. At that time, they said their Letter of Intent covered a proposed…

    Have You Seen?

    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    • November 5, 2026
    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    EU Not Planning to Resume Russian Gas Purchases

    • November 5, 2026
    EU Not Planning to Resume Russian Gas Purchases

    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    • November 5, 2026
    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    Iran Reports More Tanker Fires in Strait of Hormuz

    • November 5, 2026
    Iran Reports More Tanker Fires in Strait of Hormuz

    India to Require State Utilities to Add Energy Storage Capacity

    • November 5, 2026
    India to Require State Utilities to Add Energy Storage Capacity

    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    • November 5, 2026
    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    • November 5, 2026
    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    Samsung ramps up neon recycling to strengthen supply security

    • November 5, 2026
    Samsung ramps up neon recycling to strengthen supply security

    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    • November 5, 2026
    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    Air Products exits two Chinese coal gasification projects

    • November 5, 2026
    Air Products exits two Chinese coal gasification projects