UPERC Declines Transmission Land Compensation Claim, Cites Pending Civil Court Ownership Dispute In Uttar Pradesh

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has dismissed a revision petition concerning compensation for land used for a transmission tower, ruling that disputes over land ownership and title must be decided by civil courts.

The case relates to the construction of the 400 kV NTPC (Tanda)-Basti transmission line by Uttar Pradesh Power Transmission Corporation Limited (UPPTCL). A transmission tower was erected on Gata No. 99 in Khairpur village, Ambedkar Nagar district. The petitioners claimed ownership of the land based on civil court decrees issued in 1946 and 1990 and sought compensation at the prevailing circle rate along with interest.

Following directions from the High Court, the District Magistrate of Ambedkar Nagar examined the compensation claim and issued an order on November 5, 2024. The District Magistrate declined to release the compensation, noting that revenue records classified the disputed land as public settlement/abadi land rather than recording it in the names of the claimants.

The authorities also noted that several legal proceedings concerning ownership of the land remained pending before civil courts. These included recall and restoration applications related to the 1990 ex-parte decree.

The petitioners challenged the District Magistrate’s decision before UPERC under the Works of Licensees Rules, 2006. They argued that the revenue authorities had failed to update the land records despite the civil court judgments. They also contended that the pending recall applications did not stay the operation of the decree and should not prevent payment of compensation.

UPPTCL clarified that it did not dispute its liability to pay compensation for the transmission tower constructed on Gata No. 99. However, the corporation stated that the payment had been withheld because ownership of the land had not been conclusively established by the competent authority.

A UPERC bench comprising Chairman Arvind Kumar, Member Sanjay Kumar Singh and Member (Law) Griesh Kumar Vaish examined the submissions. The Commission held that although it has jurisdiction to decide compensation disputes arising from works undertaken by electricity licensees, it cannot adjudicate questions relating to land title, ownership or revenue records.

The Commission observed that proceedings concerning ownership of the disputed land were still pending before civil courts. It therefore found the District Magistrate’s decision to withhold compensation at this stage to be justified.

UPERC rejected the revision petition and held that compensation could be considered only after ownership of the land is conclusively determined by the competent civil court.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    UAE-Backed 20 MW Solar Projects Inaugurated Across Comoros Islands

    Three solar photovoltaic (PV) plants with a combined capacity of approximately 20 MW have been inaugurated in the Union of the Comoros, supported by AED 84.4 million in financing from…

    Punjab Regulator Approves Digital Net Metering Agreements For Rooftop Solar Connections

    The Punjab State Electricity Regulatory Commission (PSERC) has simplified the process for consumers seeking to install rooftop solar systems in the state. In an order issued on August 19, 2026,…

    Have You Seen?

    UAE-Backed 20 MW Solar Projects Inaugurated Across Comoros Islands

    • September 7, 2026
    UAE-Backed 20 MW Solar Projects Inaugurated Across Comoros Islands

    Punjab Regulator Approves Digital Net Metering Agreements For Rooftop Solar Connections

    • September 7, 2026
    Punjab Regulator Approves Digital Net Metering Agreements For Rooftop Solar Connections

    Suzlon Energy Appoints Manjari Upadhye as President – Renewable Energy Asset Management Services

    • September 7, 2026
    Suzlon Energy Appoints Manjari Upadhye as President – Renewable Energy Asset Management Services

    Roofsol Energy Secures 4.48 MWp Repeat Solar Project Order From Metro Decorative

    • September 7, 2026
    Roofsol Energy Secures 4.48 MWp Repeat Solar Project Order From Metro Decorative

    Kajaria Ceramics to Invest Up to INR 12.15 Crore in Sunsure Solar Project for Captive Power

    • September 7, 2026
    Kajaria Ceramics to Invest Up to INR 12.15 Crore in Sunsure Solar Project for Captive Power

    UPERC Declines Transmission Land Compensation Claim, Cites Pending Civil Court Ownership Dispute In Uttar Pradesh

    • September 7, 2026
    UPERC Declines Transmission Land Compensation Claim, Cites Pending Civil Court Ownership Dispute In Uttar Pradesh

    Rosneft CEO: China Calls The Shots in Oil Markets, Not OPEC

    • September 7, 2026
    Rosneft CEO: China Calls The Shots in Oil Markets, Not OPEC

    MERC Approves INR 1,445.56 Million Annual Tariff For Dharashiv-Beed Power Evacuation Project In Maharashtra

    • September 7, 2026
    MERC Approves INR 1,445.56 Million Annual Tariff For Dharashiv-Beed Power Evacuation Project In Maharashtra

    BP Appoints Ian Tyler as Chair With Immediate Effect as Company Moves to Strengthen Governance and Strategic Oversight

    • September 7, 2026
    BP Appoints Ian Tyler as Chair With Immediate Effect as Company Moves to Strengthen Governance and Strategic Oversight

    DERC Mandates Energy Compliance For NDMC, Waives INR 12.54 Crore Penalty In Delhi

    • September 7, 2026
    DERC Mandates Energy Compliance For NDMC, Waives INR 12.54 Crore Penalty In Delhi