UPNEDA Invites Bids For 5 MW Solar Project In Mau, Uttar Pradesh

Representational image. Credit: Canva

Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) has issued a Request for Selection (RfS) for the development of a 5 MW grid-connected solar PV power project in Mau district, Uttar Pradesh. The project will be executed under a Build-Own-Operate (BOO) model, with the selected developer responsible for supplying solar power as per the terms outlined in the RfS document.

The RfS document was released on February 8, 2025. The project is expected to be developed on UPNEDA-owned land spanning approximately 29.2 acres in Saraisadi village. The land will be provided on lease to the selected developer at a rate of ₹15,000 per acre per annum for 30 years.

The bidding process follows a single-stage, two-envelope system, with both techno-commercial and financial bids required. The document fee for participation in the tender is ₹29,500, inclusive of GST, while the document processing fee is ₹2 lakh plus 18% GST. Bidders must also submit an Earnest Money Deposit (EMD) of ₹40 lakh, calculated at ₹8 lakh per MW. Additionally, the selected developer will need to furnish a Performance Bank Guarantee (PBG) of ₹20 lakh per MW within 30 days of receiving the Letter of Intent (LoI).

The deadline for online and offline bid submission is set for March 10, 2025, at 6:00 PM, with the techno-commercial bid opening scheduled for March 11, 2025, at 12:30 PM. A reverse auction will follow, with the date to be communicated to eligible bidders via email.

Uttar Pradesh Power Corporation Limited (UPPCL), on behalf of state distribution companies, will sign a 25-year Power Purchase Agreement (PPA) with the selected bidder. The maximum tariff payable under the contract is fixed at ₹2.98 per kWh, inclusive of all statutory taxes and levies.

The project developer must ensure connectivity with the 132/33 kV substation at Ghosi, and the cost of transmission infrastructure up to the grid connection point will be borne by the developer. As per the state’s Solar Energy Policy 2022, UPNEDA will reimburse the cost of constructing a transmission line up to 10 km.

The financial closure of the project must be achieved within nine months from the PPA signing date, and the scheduled commencement of supply (SCSD) is set for 15 months from the effective date of the PPA, which is expected to be February 6, 2025.

In case of delays, liquidated damages will be levied. A delay of up to six months beyond SCSD will result in encashment of the PBG on a per-day basis, while delays beyond six months will lead to a reduction in contracted capacity, and the PPA for the uncommissioned portion may be terminated.

 

  • Related Posts

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    Representational image. Credit: Canva The Northern Power Corporation is taking major steps to stabilize the electricity supply across Northern Vietnam as demand is expected to grow sharply in 2026. With…

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    Representational image. Credit: Canva Gujarat State Electricity Corporation Limited (GSECL) has filed Petition No. 2620 of 2026 before the Gujarat Electricity Regulatory Commission (GERC) seeking approval for a project-specific tariff…

    Have You Seen?

    Trump threatens Hormuz blockade as Iran talks fail, oil flows at risk

    • April 12, 2026
    Trump threatens Hormuz blockade as Iran talks fail, oil flows at risk

    Recalibration and resilience to go the distance

    • April 11, 2026
    Recalibration and resilience to go the distance

    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    • April 11, 2026
    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War