Zambia Launches Implementation of $292 Million Power Interconnector Project with Tanzania

Representational image. Credit: Canva

The Zambian government has officially launched the implementation phase of the Zambia-Tanzania Interconnector project, a major cross-border electricity initiative set to boost regional energy trade and power grid stability across Eastern and Southern Africa. The project is part of the broader Zambia-Tanzania-Kenya (ZTK) interconnector, aimed at linking the Southern Africa Power Pool (SAPP) with the East Africa Power Pool (EAPP), creating a unified electricity market across the continent.

The project, backed by $292 million in grant financing, was unveiled at a high-level launch event held at the Mulungushi International Conference Centre in Lusaka. The event was attended by representatives from the Zambian government, World Bank, European Union (EU), United Kingdom Foreign Commonwealth & Development Office (FCDO), COMESA, and officials from Kenya and Tanzania.

The financing package includes:

  • $245 million from the World Bank’s International Development Association (IDA)
  • $17 million from the UK FCDO through the Energy Sector Management Assistance Program (ESMAP)
  • $30 million from the European Union

The interconnector project involves the construction of a 620-kilometre, 400 kV double circuit transmission line stretching from Iringa in Tanzania to the Zambian border, and onwards to Sumbawanga, integrating both countries’ national power grids. A new substation will also be built in Tunduma, near the Zambia-Tanzania border.

Tanzania’s Ministry of Energy, represented by Innocent Luoga, reaffirmed the commitment of the heads of state from Zambia, Tanzania, and Kenya to advancing energy integration in the region. Luoga announced that Tanzania’s segment of the interconnector is expected to be commissioned by May 26, 2026, with power exports to Zambia projected to begin the following year.

Zambia’s Energy Minister, Makozo Chikote, hailed the interconnector as a milestone in Zambia’s regional energy strategy, stating:
“The Zambia-Tanzania interconnector is just the beginning. We are exploring additional interconnections with Mozambique, Malawi, Angola, and Zimbabwe to expand regional energy access and market integration.”

World Bank Country Manager for Zambia, Ackim Fock, described the project as a transformative initiative:
“The Zambia-Tanzania Interconnector will not only enhance the resilience of Zambia’s power system, but also contribute to broader African energy security.”

COMESA Assistant Secretary General, Ambassador Dr. Mohamed Kadah, emphasized the strategic importance of the project in advancing regional renewable energy development, saying:
“Full energy interconnectivity and increased renewable generation have been prioritized as essential goals for the COMESA region.”

EU Special Advisor Henrik Hololei added that the initiative will support regional growth and connectivity:
“This project will drive economic growth, enhance energy security, and strengthen cross-regional cooperation.”

Once completed, the ZTK interconnector will form the final link in the Ethiopia–Kenya–Tanzania–Zambia transmission corridor, paving the way for large-scale power exchange between East and Southern Africa. It is expected to unlock new investments in generation, transmission, and rural electrification, while promoting climate-resilient infrastructure and regional energy trade.

 

  • Related Posts

    Australia Awards 15 Battery Storage Projects Under CIS Tender 8, Adding 4.2 GW/16.1 GWh Capacity

    Representational image. Credit: Canva The Albanese Government has announced 15 successful large-scale battery energy storage projects under Capacity Investment Scheme (CIS) Tender 8, marking a major step in Australia’s transition…

    B.Grimm Power Subsidiary Acquires Future Green Tech to Expand Solar Power Portfolio

    Representational image. Credit: Canva B.Grimm Power Public Company Limited has announced that its subsidiary, B.Grimm Greenery Company Limited (BGG), has acquired 100% of the shares of Future Green Tech Company…

    Have You Seen?

    Qatar Offers First Crude Loadings to Buyers Since War Began

    • June 26, 2026
    Qatar Offers First Crude Loadings to Buyers Since War Began

    China’s Crude Imports Set to Hit Weakest Level Since 2016

    • June 26, 2026
    China’s Crude Imports Set to Hit Weakest Level Since 2016

    Kazakhstan Cuts Gas Output after Drone Strike on Russian Processing Plant

    • June 26, 2026
    Kazakhstan Cuts Gas Output after Drone Strike on Russian Processing Plant

    Hormuz Shipping Confidence Is Still Shaky

    • June 26, 2026
    Hormuz Shipping Confidence Is Still Shaky

    Saudi Arabia Set to Slash Oil Prices as Hormuz Reopens

    • June 26, 2026
    Saudi Arabia Set to Slash Oil Prices as Hormuz Reopens

    Baghdad Hosting EU Energy Talks After Iraq Floats OPEC Exit

    • June 26, 2026
    Baghdad Hosting EU Energy Talks After Iraq Floats OPEC Exit

    US electricity demand to rise 21% by 2030

    • June 26, 2026
    US electricity demand to rise 21% by 2030

    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    • June 26, 2026
    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    • June 26, 2026
    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    Podcast | AI, semiconductor growth & the future of specialty gases

    • June 26, 2026
    Podcast | AI, semiconductor growth & the future of specialty gases