GETCO Faces Petition Over Delay And Continued Use Of Temporary Bay At Kalavad Sub-Station In Gujarat

Representational image. Credit: Canva

The Gujarat Electricity Regulatory Commission recently heard a petition involving M/s Morjar Renewables Private Limited and Gujarat Energy Transmission Corporation Limited (GETCO). The case concerns two main issues: the extension of time for building and commissioning a permanent 220 KV GIS bay at the Kalavad sub-station, and the continued use of a temporary bay provided by GETCO until the permanent bay becomes operational.

M/s Morjar Renewables explained that delays in constructing the permanent bay are due to factors beyond their control. They requested permission to keep using the temporary bay until three other renewable energy companies—Cleanmax, Suzlon, and OP Wind—finish their own bay constructions at the same substation. The petitioner said their permanent bay is expected to be ready by June 30, 2025, but it cannot become functional until the bays of the other three generators are also completed. This is because all four bays connect to a common bus bar that must be energized together.

The petitioner also mentioned repeated attempts to organize a joint meeting with GETCO and the other renewable developers since January 13, 2025, to coordinate their work and ensure timely commissioning. They added that another company, M/s Jamnagar Renewables Two Private Limited, plans to evacuate power through their permanent bay, making the timely completion or continued use of the temporary bay more urgent.

On the other side, GETCO acknowledged the two issues but expressed reluctance to extend the temporary bay usage beyond March 31, 2025, which they had previously permitted. However, the Commission issued an interim order on March 29, 2025, allowing the petitioner to continue using the temporary bay until the next hearing. GETCO noted that if the petitioner completes their bay by the end of June, many delay reasons would no longer be relevant.

GETCO also pointed out that due to the sub-station’s current design, all four renewable energy developers must commission their GIS bays simultaneously for the system to operate. They requested permission from the Commission to hold a meeting and inspect the progress of all four generators’ work, as suggested by the petitioner. GETCO clarified that the temporary bay usage was granted only to Morjar Renewables and not to Jamnagar Renewables Two Private Limited.

During the hearing, the Commission asked GETCO to provide detailed information on several important matters. These included the energization date of the Kalavad 220 KV sub-station, its power transformation capacity and how it is allocated, a full list of dates and documents concerning connectivity and open access approvals for all developers connected to the sub-station, the status of transmission infrastructure work completed by the developers, and data on connectivity applications, allocation timelines, and power evacuation volumes. The Commission also wanted to know if there had been any cancellations or changes in connectivity and the reasons behind them.

Both parties completed their oral arguments and were given 10 days to submit written statements. The Commission reserved the final decision, while the previous interim order allowing temporary bay use remains in effect until further notice.

 

  • Related Posts

    WindForce PLC Secures 120 MW Grid-Scale Battery Storage Projects In Sri Lanka

    Representational image. Credit: Canva WindForce PLC has secured 12 standalone Battery Energy Storage System (BESS) projects in Sri Lanka, marking a major development in the country’s power sector. The projects…

    Japan Advances Space-Based Solar Power Project To Beam Energy From Orbit

    Japan is moving ahead with an ambitious plan to transmit solar power from space to Earth for commercial use. The country aims to become the first in the world to…

    Have You Seen?

    Trump Tariff Reversal Could Cut Costs for US Energy Firms But Will Likely Leave Broader Flows Unchanged

    • February 21, 2026
    Trump Tariff Reversal Could Cut Costs for US Energy Firms But Will Likely Leave Broader Flows Unchanged

    Oil Rises Late, Settles Higher and With Weekly Gain on Iran-US Jitters

    • February 21, 2026
    Oil Rises Late, Settles Higher and With Weekly Gain on Iran-US Jitters

    US Judge Upholds $243 Million Verdict Against Tesla Over Fatal Autopilot Crash

    • February 21, 2026
    US Judge Upholds $243 Million Verdict Against Tesla Over Fatal Autopilot Crash

    TXNM Energy Gets FERC Approval for $11.5 Billion Blackstone Deal

    • February 21, 2026
    TXNM Energy Gets FERC Approval for $11.5 Billion Blackstone Deal

    WindForce PLC Secures 120 MW Grid-Scale Battery Storage Projects In Sri Lanka

    • February 21, 2026
    WindForce PLC Secures 120 MW Grid-Scale Battery Storage Projects In Sri Lanka

    Japan Advances Space-Based Solar Power Project To Beam Energy From Orbit

    • February 21, 2026
    Japan Advances Space-Based Solar Power Project To Beam Energy From Orbit

    Türkiye And Saudi Arabia Sign 2,000 MW Solar Power Deal To Boost Clean Energy Cooperation

    • February 21, 2026
    Türkiye And Saudi Arabia Sign 2,000 MW Solar Power Deal To Boost Clean Energy Cooperation

    Rwanda Secures $300 Million Boost To Expand Solar Access, Clean Cooking, And Grid Connections

    • February 21, 2026
    Rwanda Secures $300 Million Boost To Expand Solar Access, Clean Cooking, And Grid Connections

    NTPC Invites Bids For Solar High Mast Project At Vindhyachal Plant Under CSR 2025–26 In Madhya Pradesh

    • February 21, 2026
    NTPC Invites Bids For Solar High Mast Project At Vindhyachal Plant Under CSR 2025–26 In Madhya Pradesh

    ConocoPhillips Considers Selling Permian Assets Worth $2 Billion, Bloomberg News Reports

    • February 21, 2026
    ConocoPhillips Considers Selling Permian Assets Worth $2 Billion, Bloomberg News Reports