Leak tests completed for Rooppur I’s containment structure

Wednesday, 25 June 2025

Leak tests completed for Rooppur I's containment structure
(Image: Rosatom)

During the process a compressor was used and the pressure was increased to the design value of 4.6kgf/cm2 and a series of tests was carried out to “confirm the tightness of the structure and its ability to withstand internal loads that occur in abnormal conditions”.

Rosatom describes the reactor’s hermetic enclosure as “a physical barrier made of prestressed reinforced concrete with an internal sealing steel lining. It is designed to prevent the release of radioactive substances into the environment in the event of an emergency and to localise them, as well as to protect against possible external influences. The enclosure serves as the last protective barrier in the event of a hypothetical accident”.

Alexey Deriy, vice president for projects in Bangladesh at Atomstroyexport JSC, said: “A number of operations carried out during these tests are unique and are carried out once, only after the full completion of construction and installation work in the reactor building. The results of the tests confirm that the hermetic enclosure system fully complies with all design and regulatory requirements. This is an important step towards commissioning the first power unit and evidence of the high quality of work at all stages of construction.”

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Trump threatens Hormuz blockade as Iran talks fail, oil flows at risk

    • April 12, 2026
    Trump threatens Hormuz blockade as Iran talks fail, oil flows at risk

    Recalibration and resilience to go the distance

    • April 11, 2026
    Recalibration and resilience to go the distance

    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    • April 11, 2026
    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War