GERC Reserves Final Order On Extension Request For 9 MW Hybrid Project Evacuation Delay

Representational image. Credit: Canva

JSW Renewable Energy (Anjar) Limited filed a petition before the Gujarat Electricity Regulatory Commission (GERC) seeking an extension for completing the evacuation system of its 9 MW hybrid power project. The project is being developed under JSW Neo Energy Limited at the 66/11 kV Gangiyavadar substation of GETCO in Surendranagar district. The petitioner had earlier obtained Stage-I connectivity approval on 30.09.2023 and Stage-II approval on 31.03.2024 after submitting a bank guarantee of ₹90 lakhs.

A connection agreement was executed between the petitioner and GETCO on 23.05.2024. However, on 18.02.2025, GETCO issued a letter instructing the petitioner to commission the evacuation system within 12 months, i.e., by 30.03.2025, failing which actions like encashment of bank guarantee or cancellation of connectivity would be initiated. The petitioner then sought an extension, citing various unforeseen challenges.

The petitioner submitted that delays were primarily due to Right of Way (ROW) issues, heavy rainfall, and Cyclone Asana in August 2024, which impacted project activities until October 2024. Other factors included delays in raw material deliveries due to market demand crises and global supply chain disruptions. Specific ROW disputes included intervention by local authorities, legal cases filed by landowners, and disputes between vendors and sub-vendors. These issues resulted in the obstruction of site access and delayed construction.

The petitioner referred to several legal judgments to support its request and argued that the evacuation line could not be completed due to factors beyond its control. It requested an extension of 158 days to commission the full system.

In response, GETCO’s counsel argued that the company was reminded only of its obligations as per the approved procedure and that the extension could only be granted by the Commission, not GETCO. The respondent emphasized that many of the petitioner’s claims were not substantiated with evidence, such as the exact timing of supply delays or court-ordered restrictions. GETCO also pointed out that Cyclone Asana lasted from 25 August to 2 September 2024 and did not justify delays claimed from July to October 2024.

Further, GETCO argued that regular monsoon disruptions were already factored into project timelines and that delays due to vendor-related issues did not qualify as unforeseen. It also noted that the petitioner’s own status report dated January 2025 projected commissioning by 31.03.2025, indicating it did not anticipate delays at that time.

After hearing both sides, the Commission stated that arguments were completed and directed both parties to file written submissions within four weeks. The matter is now reserved for final order, as recorded in the daily order dated 24.07.2025.

 

  • Related Posts

    Top Stories Of The Day: Cosmic PV Files ₹640 Cr IPO; Neuron Launches BESS Facility and More…

    Surat-based Cosmic PV Power has filed its draft red herring prospectus with SEBI for a proposed ₹640 crore IPO. The issue is expected to include a fresh issue of ₹540…

    US Utility-Scale Solar Developers Rush To Safe Harbor Massive Capacity Ahead Of Internal Revenue Service (IRS) And Policy Deadlines

    Representational image. Credit: Canva The US utility-scale solar sector has gone through an extraordinary period of “safe harboring” activity over the past 18 months, as developers worked urgently to secure…

    Have You Seen?

    Oil Giants Show Early Interest in US Gulf Deepwater Field Stake

    • April 3, 2026
    Oil Giants Show Early Interest in US Gulf Deepwater Field Stake

    Europe Braces for Prolonged Energy Crisis as Supplies Tighten

    • April 3, 2026
    Europe Braces for Prolonged Energy Crisis as Supplies Tighten

    JP Morgan Sees $150 Oil if Hormuz Remains Closed Through Mid-May

    • April 3, 2026
    JP Morgan Sees $150 Oil if Hormuz Remains Closed Through Mid-May

    Canada’s Synthetic Crude Soars 200% as War Chokes Diesel Supply

    • April 3, 2026
    Canada’s Synthetic Crude Soars 200% as War Chokes Diesel Supply

    Why Has the WTI Oil Price Surpassed Brent?

    • April 3, 2026
    Why Has the WTI Oil Price Surpassed Brent?

    Top Stories Of The Day: Cosmic PV Files ₹640 Cr IPO; Neuron Launches BESS Facility and More…

    • April 3, 2026
    Top Stories Of The Day: Cosmic PV Files ₹640 Cr IPO; Neuron Launches BESS Facility and More…

    OPEC+ Prepares Paper Oil Barrels While Exports Stall

    • April 3, 2026
    OPEC+ Prepares Paper Oil Barrels While Exports Stall

    Oil Majors Eye U.S. Offshore Asset as Supply Crunch Intensifies

    • April 3, 2026
    Oil Majors Eye U.S. Offshore Asset as Supply Crunch Intensifies

    Japan’s JERA Cancels Long-Term LNG Deal With Commonwealth

    • April 3, 2026
    Japan’s JERA Cancels Long-Term LNG Deal With Commonwealth

    US Utility-Scale Solar Developers Rush To Safe Harbor Massive Capacity Ahead Of Internal Revenue Service (IRS) And Policy Deadlines

    • April 3, 2026
    US Utility-Scale Solar Developers Rush To Safe Harbor Massive Capacity Ahead Of Internal Revenue Service (IRS) And Policy Deadlines