Rooppur unit 1 progressesing though commissioning tests

Tuesday, 5 August 2025

A blowdown of the fresh steam pipelines in the turbine compartment has been completed at the first unit of the Rooppur nuclear power plant being built in Bangladesh.

Rooppur unit 1 progressesing though commissioning tests
(Image: Rosatom)

The blowdown was carried out using fresh steam under 2.0 MPa pressure at 200 degrees Celsius. Rosatom described it as one of the key stages of cold and hot functional tests during the commissioning process and shows the readiness of the unit’s steam lines to supply steam to the turbine.

The tests, during which the steam was discharged into the atmosphere, clean the pipelines and “will be followed by the repeated blowdown of the steam pipelines with an increased volume of fresh steam which will allow for the final cleaning of the main lines and specify the equipment operating parameters under a near-operational load”.

Hot testing of the unit began last month and it is designed as a general check of the reliability of the reactor unit “before moving on to the next, more important stages … and shows where the system is ready to function under conditions close to real operation”.

Atomstroyexport, part of Rosatom, explained last month that “during the tests, the reactor unit is heated up, and our specialists check step-by-step how key elements operate under these conditions: pumps, pipelines, heat exchange equipment. It is important to record how the equipment behaves under load – after all, it will be the one that will ensure reliable operation of the plant later”.

Leak tests on the containment building for Rooppur 1 were successfully completed in June.

Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh, said: “With the completion of this stage of commissioning works, the Rooppur NPP takes another step towards the pivotal event, such as launching of power unit No 1 and its subsequent connection to the power grid, which will supply the country’s residents with additional energy, vital for both the economy and industry. In the future, the Rooppur NPP built according to the latest Russian VVER-1200 design, is expected to supply Bangladesh with up to 10% of clean energy for decades to come.”

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Kaleidos microreactor begins journey to Idaho

    “We said we’d make a microreactor that is transportable by land, sea and air. We did. Kaleidos is traveling more than 1,000 miles on a trailer bed,” the company said. …

    Detritiation facility reopens at Culham

    In the last three years of plasma operations, the Joint European Torus’s (JET’s) deuterium-tritium experiments resulted in residual tritium being retained within the tokamak’s walls and internal components. This reflected…

    Have You Seen?

    Gulf-to-China Supertanker Rates Hit $510,000 a Day

    • August 18, 2026
    Gulf-to-China Supertanker Rates Hit $510,000 a Day

    Romania Restarts Coal Plant as Danube Drought Forces Nuclear Shutdown

    • August 18, 2026
    Romania Restarts Coal Plant as Danube Drought Forces Nuclear Shutdown

    China’s Solar Exports Fell 21.4% in July

    • August 18, 2026
    China’s Solar Exports Fell 21.4% in July

    UK researchers make MOF for capturing heavy metals from wastewater

    • August 18, 2026
    UK researchers make MOF for capturing heavy metals from wastewater

    US semiconductor investment tops $820bn since 2020

    • August 18, 2026
    US semiconductor investment tops $820bn since 2020

    UK biogas plant gets green light for CO2 capture and liquefaction

    • August 18, 2026
    UK biogas plant gets green light for CO2 capture and liquefaction

    Outlook for electronic specialty gases

    • August 18, 2026
    Outlook for electronic specialty gases

    U.S.-Iran Tensions Push Oil Prices Higher as Diesel Margins Hit Records

    • August 18, 2026
    U.S.-Iran Tensions Push Oil Prices Higher as Diesel Margins Hit Records

    Libya Seeks Up to $40 Billion to Boost Oil Output to 2 Million Bpd

    • August 18, 2026
    Libya Seeks Up to $40 Billion to Boost Oil Output to 2 Million Bpd

    China Boosts Fuel Exports as Domestic Stockpiles Swell

    • August 18, 2026
    China Boosts Fuel Exports as Domestic Stockpiles Swell