MERC Orders Compensation To Rooftop Solar Developer Over Grid Availability Dispute

The Maharashtra Electricity Regulatory Commission (MERC) has ruled in favour of M/s Karnataka Resco Rooftop Solar Private Limited (KRRSPL) in a dispute involving Maharashtra State Power Generation Company Limited (MSPGCL) and Maharashtra State Electricity Distribution Co. Ltd. (MSEDCL). The Commission has directed MSPGCL to pay ₹1,11,03,214 to KRRSPL as Deemed Generation Compensation for the financial year 2022-23.

MERC has ordered MSPGCL to release the amount within 30 days. The Commission has also directed MSPGCL to pay a Late Payment Surcharge (LPS) on the outstanding amount from the date it became due until the date of actual payment.

The dispute relates to five solar power projects developed by KRRSPL at Bori, Goregaon, Hatta, Pedgaon and Rani Unchegaon under the Mukhyamantri Saur Krishi Vahini Yojana (MSKVY). KRRSPL had entered into back-to-back Power Purchase Agreements (PPAs) with MSPGCL for the supply of electricity generated from these projects. The electricity was ultimately procured by MSEDCL.

Under the PPAs, KRRSPL was entitled to compensation when grid availability during the specified generation period fell below the guaranteed 98% level. The relevant operational period was from 8:00 AM to 6:00 PM. KRRSPL submitted its claim under Article 4.7 of the PPA after recording instances of lower grid availability.

MSPGCL initially verified KRRSPL’s compensation claim of ₹1,11,03,214 in June 2023. However, MSEDCL subsequently reduced the admissible amount to ₹17,45,089, which was later revised to ₹17,69,702.

MSEDCL had primarily relied on two arguments for reducing the compensation. First, it calculated the total hours of generation in the contract year using a 24-hour daily period based on standard Capacity Utilization Factor (CUF) calculations. Second, it excluded certain interruptions, including over-voltage, under-voltage and scheduled maintenance outages, from the calculation of grid unavailability.

MERC rejected this approach and clarified that the calculation under Article 4.7 must reflect the actual operational window of the solar projects. The Commission held that the total hours of generation should be calculated using the 10-hour period between 8:00 AM and 6:00 PM. According to MERC, applying a 24-hour period would artificially reduce the average generation per hour and undermine the purpose of the compensation mechanism provided under the PPA.

The Commission also held that over-voltage, under-voltage and scheduled maintenance interruptions on the distribution system cannot automatically be excluded while calculating grid unavailability. Such events can be excluded only if MSEDCL establishes that they resulted from an act or default of the generator.

MERC further clarified that MSPGCL’s payment obligation under its direct PPA with KRRSPL is unconditional. MSPGCL cannot delay payment on the ground that MSEDCL has not completed verification or released funds under the separate Power Sale Agreement. MSPGCL, however, can recover the corresponding amount from MSEDCL in accordance with the back-to-back PSA provisions.

With these findings, MERC allowed KRRSPL’s petition and granted the developer full relief, with no order as to costs.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    “Integrated Fluid Control Solutions Are Key to Reliable Hydrogen Applications”: Dongshin Oh of Bürkert Korea

    Hydrogen projects rely on precise control of pressure, flow and other process conditions. In this interview, conducted at World Hydrogen Expo 2026 in South Korea, Mr. Dongshin Oh, Account Sales…

    Just 7 Days to Go! Tamil Nadu Energy Expo 2026 Set to Bring Together 3,000+ Industry Professionals in Coimbatore  

    The countdown is on! With just 7 days to go, Coimbatore is gearing up to welcome the clean energy industry’s key players, innovators and decision-makers for Tamil Nadu Energy Expo…

    Have You Seen?

    Iran Rules Out Return of UN Nuclear Inspectors as U.S. War Talks Stall

    • November 13, 2026
    Iran Rules Out Return of UN Nuclear Inspectors as U.S. War Talks Stall

    India’s Road Fuel Demand Won’t Peak Until 2034

    • November 13, 2026
    India’s Road Fuel Demand Won’t Peak Until 2034

    Appalachian Power Investing Nearly $25 Billion For Gas and Coal Power Plants

    • November 13, 2026
    Appalachian Power Investing Nearly $25 Billion For Gas and Coal Power Plants

    Asian Refiners Turn Back to Gulf Oil Despite War Risks

    • November 13, 2026
    Asian Refiners Turn Back to Gulf Oil Despite War Risks

    Iran Says Gas Tanker Hit Mine in Strait of Hormuz

    • November 13, 2026
    Iran Says Gas Tanker Hit Mine in Strait of Hormuz

    Pakistan Scrambles for LNG as Winter Gas Crisis Deepens

    • November 13, 2026
    Pakistan Scrambles for LNG as Winter Gas Crisis Deepens

    COP31 declaration targets global scale-up of biogas and biomethane

    • November 13, 2026
    COP31 declaration targets global scale-up of biogas and biomethane

    Oil Prices Head for Second Weekly Loss Despite Fresh Middle East Attacks

    • November 13, 2026
    Oil Prices Head for Second Weekly Loss Despite Fresh Middle East Attacks

    Asian Airlines Face a $148-a-Barrel Fuel Gamble

    • November 13, 2026
    Asian Airlines Face a $148-a-Barrel Fuel Gamble

    India Seeks Private Investors for $910 Million Oil Reserve

    • November 13, 2026
    India Seeks Private Investors for $910 Million Oil Reserve