Turbogenerator for Russian fast reactor delivered

The delivery of the turbogenerator – comprising a steam turbine rotor and a stator – was carried out via the Northern Sea Route and then along the Ob and Tom rivers, after transshipment at the river port by special road transport.

The stator weighs 245 tonnes and measures 8 metres long, about 4.5 metres high and 4.8 metres wide. The turbine rotor, also delivered by water, weighs 98 tonnes. The generator rotor was also delivered by rail.


(Image: TVEL)

“The turbogenerator of the BREST-OD-300 power unit is a unique Russian development with fully air cooling,” said Ivan Babich, director of the power unit project. “The design is distinguished by increased safety and productivity. For the Tomsk energy system, this will be the most powerful power plant.”

Russia’s state nuclear corporation Rosatom announced in November last year that installation work had begun for the condenser in the turbine hall for the BREST-OD-300. At that time, it said installation of the turbine and generator was planned to start in 2025.

The background

The BREST-OD-300 fast reactor is part of Rosatom’s Proryv, or Breakthrough, project to enable a closed nuclear fuel cycle. The 300 MWe unit will be the main facility of the Pilot Demonstration Energy Complex at the Siberian Chemical Combine site. The complex will demonstrate an on-site closed nuclear fuel cycle with a facility for the fabrication/re-fabrication of mixed uranium-plutonium nitride nuclear fuel, as well as a used fuel reprocessing facility.

A progress update in November said that the cooling tower had been built, the walls of the reactor containment building erected and the reactor shaft and the enclosing structure of the reactor vessel have also been installed.

Earlier this month, Rosatom announced that the Atommash plant in Volgodonsk – part of its Mechanical Engineering Division – had shipped to the BREST-OD-300 construction site the central void shell and inner casing for the core support barrel, components which will hold nuclear fuel once installed. The Izhora plant in St Petersburg – also part of the same Rosatom division – shipped four peripheral cavity shells which will house steam generators and pumps for circulation of the coolant.

Initial operation of the demonstration unit will be focused on performance and after 10 years or so it will be commercially oriented. The plan has been that if it is successful as a 300 MWe (700 MWt) unit, a 1200 MWe (2800 MWt) version will follow – the BR-1200.

   

  • Related Posts

    Concreting milestones at Chinese Hualong One units

    China National Nuclear Corporation (CNNC) said the last batch of concrete was poured for the inner dome of Zhangzhou unit 3 on 30 September. “This key milestone marks the completion…

    DOE offers Vistra loan for reactor upgrades and uprates

    Vistra’s planned investments at Beaver Valley in Pennsylvania and Davis-Besse and Perry in Ohio will produce more electricity from existing nuclear plants without requiring new transmission corridors or equivalent new…

    Have You Seen?

    MNRE Proposes Standardized 14-Digit Naming System For ALMM List-II Solar Cells

    • October 7, 2026
    MNRE Proposes Standardized 14-Digit Naming System For ALMM List-II Solar Cells

    Australia Commits $7.29 Million To Strengthen Pacific Renewable Energy Security

    • October 7, 2026
    Australia Commits $7.29 Million To Strengthen Pacific Renewable Energy Security

    HPSEBL Floats Tender for 1 MW Green Hydrogen Plant and 33 kV Feeder Strengthening In Himachal Pradesh

    • October 7, 2026
    HPSEBL Floats Tender for 1 MW Green Hydrogen Plant and 33 kV Feeder Strengthening In Himachal Pradesh

    JWL Secures 41 MW/102.5 MWh BESS Project In Uttarakhand, Receives 50 MW/200 MWh West Bengal LoA

    • October 7, 2026
    JWL Secures 41 MW/102.5 MWh BESS Project In Uttarakhand, Receives 50 MW/200 MWh West Bengal LoA

    Gulf Producers Say Importers Should Share the Cost of Hormuz Workarounds

    • October 6, 2026
    Gulf Producers Say Importers Should Share the Cost of Hormuz Workarounds

    Low Wind Generation Prompts Another Power Margin Warning in UK

    • October 6, 2026
    Low Wind Generation Prompts Another Power Margin Warning in UK

    India Could Boost Crude and Critical Minerals Supply from Ecuador

    • October 6, 2026
    India Could Boost Crude and Critical Minerals Supply from Ecuador

    EU Delays Methane Rules, Opens Refinery Talks as Fuel Prices Hit Records

    • October 6, 2026
    EU Delays Methane Rules, Opens Refinery Talks as Fuel Prices Hit Records

    100+ Oil Execs Predict Future WTI Oil Prices

    • October 6, 2026
    100+ Oil Execs Predict Future WTI Oil Prices

    At Least 50 Iranian Tankers Are Stuck in the Gulf as U.S. Blockade Holds

    • October 6, 2026
    At Least 50 Iranian Tankers Are Stuck in the Gulf as U.S. Blockade Holds