Cold testing of Chinese SMR completed

Cold functional tests are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition. The main purpose of these tests is to verify the leak-tightness of the primary circuit and components – such as pressure vessels, pipelines and valves of both the nuclear and conventional islands – and to clean the main circulation pipes. The tests mark the first time the reactor systems are operated together with the auxiliary systems.

The cold functional tests were completed at the ACP100 – also referred to as the Linglong One – on 16 October.

“The successful cold functional test of the primary circuit of the Linglong One small reactor demonstration project demonstrates the integrity and sealing of the primary circuit pressure boundaries,” CNNC said. “It also verifies the installation quality of the relevant equipment and piping, ensuring subsequent safe and stable operation.” It added that completion of the tests “lays a solid foundation for the project’s subsequent hot trials, reactor loading, and commercial operation”.

Hot functional tests involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Carried out before the loading of nuclear fuel, such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.


(Image: CNNC)

CNNC announced in July 2019 the launch of a project to construct an ACP100 SMR at Changjiang. The site is already home to two operating CNP600 pressurised water reactors (PWRs), while the construction of two Hualong One units began in March and December 2021. Both those units are due to enter commercial operation by the end of 2026.

First concrete for the ACP100 was poured on 13 July 2021, with a planned total construction period of 58 months. Equipment installation work commenced in December 2022 and the main internal structure of the reactor building was completed in March 2023. The outer containment dome was hoisted into place in February this year.

Under development since 2010, the 125 MWe ACP100 integrated PWR’s preliminary design was completed in 2014. In 2016, the design became the first SMR to pass a safety review by the International Atomic Energy Agency.

Once completed, the Changjiang ACP100 reactor will be capable of producing 1 billion kilowatt-hours of electricity annually, enough to meet the needs of 526,000 households. The reactor is designed for electricity production, heating, steam production or seawater desalination.

   

  • Related Posts

    Copenhagen Atomics to build deconversion facility

    Under the agreement, Urenco will help design a dedicated facility for the deconversion of uranium hexafluoride (UF6) into uranium tetrafluoride (UF4) at Copenhagen Atomics’ fuel facility in Copenhagen. Copenhagen Atomics…

    Belgian nuclear power plant negotiations extended

    Engie, the French parent of Belgian power company Electrabel, and the Belgian government began negotiations in late April. At that time, they said their Letter of Intent covered a proposed…

    Have You Seen?

    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    • November 5, 2026
    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    EU Not Planning to Resume Russian Gas Purchases

    • November 5, 2026
    EU Not Planning to Resume Russian Gas Purchases

    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    • November 5, 2026
    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    Iran Reports More Tanker Fires in Strait of Hormuz

    • November 5, 2026
    Iran Reports More Tanker Fires in Strait of Hormuz

    India to Require State Utilities to Add Energy Storage Capacity

    • November 5, 2026
    India to Require State Utilities to Add Energy Storage Capacity

    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    • November 5, 2026
    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    • November 5, 2026
    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    Samsung ramps up neon recycling to strengthen supply security

    • November 5, 2026
    Samsung ramps up neon recycling to strengthen supply security

    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    • November 5, 2026
    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    Air Products exits two Chinese coal gasification projects

    • November 5, 2026
    Air Products exits two Chinese coal gasification projects