Larsen & Toubro (L&T) has secured major engineering, procurement, and construction (EPC) orders in India and the Middle East for strengthening power transmission infrastructure. The orders fall under the company’s Power Transmission & Distribution (PT&D) vertical and are classified as “Major,” indicating a value between ₹5,000 crore and ₹10,000 crore.

In India, L&T has received an order to design, supply, and construct two 220 kV Gas Insulated Substations in the Durgapur–Raniganj–Asansol industrial belt in West Bengal. The project scope also includes associated transmission line segments equipped with advanced conductors and multi-circuit towers. These developments are part of grid modernisation efforts aimed at improving voltage stability and enhancing the overall reliability of the region’s power network. The upgraded infrastructure is expected to support growing industrial and infrastructure activities in the belt, which is a key economic zone in the state.

Apart from its domestic wins, L&T has also secured significant contracts in the Middle East. The company has received turnkey orders from key utilities in three different countries in the region. The projects involve the construction of five substations and more than 250 kilometres of transmission lines. These transmission systems will operate at voltage levels reaching up to 500 kV, reflecting the high-capacity requirements of the region’s expanding power networks.

In one of the Middle East projects, L&T’s scope includes the supply and installation of a 400 kV underground cable system. Such high-voltage underground cable systems are typically deployed in urban or environmentally sensitive areas where overhead lines may not be feasible. The projects are expected to strengthen cross-regional power flows and ensure a reliable electricity supply amid rising demand and evolving energy mixes.

The company stated that increasing electricity demand, changing generation patterns, and energy security priorities have made grid investments a high-technology and strategic focus area for leading economies. Modern transmission infrastructure is essential to integrate renewable energy, manage load growth, and maintain grid stability.

L&T said these orders demonstrate continued customer trust in its capability to deliver safe, sustainable and timely grid infrastructure solutions. Larsen & Toubro is a USD 30 billion Indian multinational engaged in EPC projects, high-tech manufacturing and services across multiple geographies. With a strong customer-focused approach and emphasis on quality, the company has maintained leadership in its key business segments for over eight decades.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Ventura County Partners with ForeFront Power for 7.7 MW Solar and Storage Project

    The County of Ventura has partnered with ForeFront Power to develop a 7.7 MW-DC solar energy and battery storage project at the Ventura County Government Center in California. The project…

    Greenvolt Secures €218 Million UniCredit Financing for 400 MW BESS Projects in Poland

    Greenvolt Group has secured a €218 million financing package from UniCredit to support the development of its Ełk and Turośń battery energy storage system (BESS) projects in Poland. The financing…

    Have You Seen?

    Thailand Accelerates Clean Energy Push to Cut LNG Dependence

    • August 27, 2026
    Thailand Accelerates Clean Energy Push to Cut LNG Dependence

    Qatar and Kuwait Restore 70% of Pre-War Oil Exports Through Hormuz

    • August 27, 2026
    Qatar and Kuwait Restore 70% of Pre-War Oil Exports Through Hormuz

    Weak Asian Oil Imports Challenge Claims of Surge in Hormuz Transits

    • August 27, 2026
    Weak Asian Oil Imports Challenge Claims of Surge in Hormuz Transits

    TotalEnergies Exits Russia’s Sanctioned Arctic LNG 2 Project

    • August 27, 2026
    TotalEnergies Exits Russia’s Sanctioned Arctic LNG 2 Project

    Fortum Seeks State Aid for Major New Nuclear Project in Sweden

    • August 27, 2026
    Fortum Seeks State Aid for Major New Nuclear Project in Sweden

    Messer and Ambrian win approval for German CO2 export terminal

    • August 27, 2026
    Messer and Ambrian win approval for German CO2 export terminal

    Pulsar Helium net losses widen in exploration push

    • August 27, 2026
    Pulsar Helium net losses widen in exploration push

    Korea moves towards first domestic green methanol supply for shipping

    • August 27, 2026
    Korea moves towards first domestic green methanol supply for shipping

    The Netherlands to Miss Natural Gas Filling Target for Winter

    • August 27, 2026
    The Netherlands to Miss Natural Gas Filling Target for Winter

    CNOOC Posts Record Profit as China Pumps More Oil at Home

    • August 27, 2026
    CNOOC Posts Record Profit as China Pumps More Oil at Home