Milestone for Palisades restart

Establishing and maintaining these conditions allowed for precise control of water chemistry and restoration of the system’s protective surfaces following the extensive maintenance, inspection, and component upgrades completed over the past two years, the company said.

Restoration work across the primary system has included steam generator tube repairs, pressure boundary weld restorations, and a “first-ever comprehensive system cleaning” that has also significantly reduced dose rates in sensitive areas of the plant.

The system will now be cooled and prepared for additional testing, equipment upgrades, and preparations for fuel loading. Activities still under way include upgrades to the fuel handling system, switchyard restoration work, and the completion of required inspections and other major maintenance works.

“The completion of primary system passivation reflects the diligence and technical rigour our team is bringing to position the plant for safe, reliable operation for decades,” Holtec International President Kelly Trice said. “Ensuring long-term safety and reliability remains the central focus of our restart mission, and we continue to execute this work with the care and precision it warrants.”

Palisades, a single-unit pressurised water reactor, ceased operations in May 2022 and was defuelled the following month, although it was licensed to operate until March 2031. The unit’s licence was transferred from previous operator Entergy Nuclear Operations to Holtec Decommissioning International, LLC and Holtec Palisades, LLC, for decommissioning, but in late 2023, Holtec began the process of obtaining the licensing approvals needed to return the plant to operational status for the remainder of its licensing term.

Holtec is also advancing plans for the future deployment of its Pioneer 1 and 2 SMR-300 units at the Palisades site.

   

  • Related Posts

    Concreting milestones at Chinese Hualong One units

    China National Nuclear Corporation (CNNC) said the last batch of concrete was poured for the inner dome of Zhangzhou unit 3 on 30 September. “This key milestone marks the completion…

    DOE offers Vistra loan for reactor upgrades and uprates

    Vistra’s planned investments at Beaver Valley in Pennsylvania and Davis-Besse and Perry in Ohio will produce more electricity from existing nuclear plants without requiring new transmission corridors or equivalent new…

    Have You Seen?

    Air Liquide sees structural healthcare trends boosting gas demand

    • October 7, 2026
    Air Liquide sees structural healthcare trends boosting gas demand

    US Crude Inventories Slide

    • October 7, 2026
    US Crude Inventories Slide

    Brent Back Above $100 as Houthis Hit Saudi Infrastructure

    • October 7, 2026
    Brent Back Above $100 as Houthis Hit Saudi Infrastructure

    Eskom Launches RFQ to Select Partners for 6 GW Renewable Energy and Battery Portfolio by 2030 In South Africa

    • October 7, 2026
    Eskom Launches RFQ to Select Partners for 6 GW Renewable Energy and Battery Portfolio by 2030 In South Africa

    SECI Invites Bids for 3.68 MW Rooftop Solar Projects On NDMC Buildings At Tariff Below INR 5.13/kWh

    • October 7, 2026
    SECI Invites Bids for 3.68 MW Rooftop Solar Projects On NDMC Buildings At Tariff Below INR 5.13/kWh

    U-Solar Targets 200 MW Renewable Asset Delivery as Revenue Crosses INR 1,000 Crore

    • October 7, 2026
    U-Solar Targets 200 MW Renewable Asset Delivery as Revenue Crosses INR 1,000 Crore

    Zelestra Secures $350 Million Green Financing for 203 MW Reclamation Solar Project in Indiana

    • October 7, 2026
    Zelestra Secures $350 Million Green Financing for 203 MW Reclamation Solar Project in Indiana

    MERC Orders Compensation To Rooftop Solar Developer Over Grid Availability Dispute

    • October 7, 2026
    MERC Orders Compensation To Rooftop Solar Developer Over Grid Availability Dispute

    New Fortress Energy’s Altamira LNG unit offline after turbine fault

    • October 7, 2026
    New Fortress Energy’s Altamira LNG unit offline after turbine fault

    MERC Disposes 730 MW Solar Project Dispute Between CMOPL And MSEDCL In Maharashtra

    • October 7, 2026
    MERC Disposes 730 MW Solar Project Dispute Between CMOPL And MSEDCL In Maharashtra