Milestone for Palisades restart

Establishing and maintaining these conditions allowed for precise control of water chemistry and restoration of the system’s protective surfaces following the extensive maintenance, inspection, and component upgrades completed over the past two years, the company said.

Restoration work across the primary system has included steam generator tube repairs, pressure boundary weld restorations, and a “first-ever comprehensive system cleaning” that has also significantly reduced dose rates in sensitive areas of the plant.

The system will now be cooled and prepared for additional testing, equipment upgrades, and preparations for fuel loading. Activities still under way include upgrades to the fuel handling system, switchyard restoration work, and the completion of required inspections and other major maintenance works.

“The completion of primary system passivation reflects the diligence and technical rigour our team is bringing to position the plant for safe, reliable operation for decades,” Holtec International President Kelly Trice said. “Ensuring long-term safety and reliability remains the central focus of our restart mission, and we continue to execute this work with the care and precision it warrants.”

Palisades, a single-unit pressurised water reactor, ceased operations in May 2022 and was defuelled the following month, although it was licensed to operate until March 2031. The unit’s licence was transferred from previous operator Entergy Nuclear Operations to Holtec Decommissioning International, LLC and Holtec Palisades, LLC, for decommissioning, but in late 2023, Holtec began the process of obtaining the licensing approvals needed to return the plant to operational status for the remainder of its licensing term.

Holtec is also advancing plans for the future deployment of its Pioneer 1 and 2 SMR-300 units at the Palisades site.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Why Has Oil Not Rallied to $150 or Higher?

    • August 17, 2026
    Why Has Oil Not Rallied to $150 or Higher?

    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    • August 17, 2026
    Podcast | Gas distribution done right: design, reliability, and performance from source to point-of-use

    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    • August 17, 2026
    Bangladesh tragedy shines spotlight on LNG shipbreaking safety

    AWG appoints Vice-President of Operations for the North Region

    • August 17, 2026
    AWG appoints Vice-President of Operations for the North Region

    Tencent drives carbon utilisation ‘out of the lab’

    • August 17, 2026
    Tencent drives carbon utilisation ‘out of the lab’

    US CO2 Outlook Report H1 2026

    • August 17, 2026
    US CO2 Outlook Report H1 2026

    U.S. West Coast Refiners Tap Malaysian Supply

    • August 17, 2026
    U.S. West Coast Refiners Tap Malaysian Supply

    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    • August 17, 2026
    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On