Kashiwazaki-Kariwa 6 resumes commercial operation

The 1,356 MWe Advanced Boiling Water Reactor (ABWR) in Japan’s Niigata Prefecture, which had been offline since March 2012, was restarted in the evening of 21 January. Tepco aimed to return the reactor to commercial operation on 18 March. However, shortly after midnight on 22 January, “an alarm was triggered in the control rod operation monitoring system for one control rod during the control rod withdrawal operation, causing the withdrawal operation to be suspended”. The unit’s restart was subsequently suspended while an investigation into the cause of the alarm was carried out.

After replacing parts, the reactor was again restarted on 9 February. It was taken offline between 20 and 24 February for inspections as part of procedures for its full-scale restart. The unit was taken offline again in mid-March after a damaged electric conductor was discovered.

A comprehensive load performance test was carried out on Tuesday, observed by the Nuclear Regulation Authority (NRA).

“Today, following the issuance by the Nuclear Regulation Authority of a pre-operational confirmation certificate and a certificate of passing for the pre-operational inspection for Kashiwazaki-Kariwa Nuclear Power Station Unit 6, Tepco recommenced commercial operation at 4:00pm [local time],” Tepco said.

The seven-unit Kashiwazaki-Kariwa plant was unaffected by the March 2011 earthquake and tsunami that damaged Tepco’s Fukushima Daiichi plant, although the plant’s reactors were previously all offline for up to three years following the 2007 Niigata-Chuetsu earthquake, which caused damage to the site but did not damage the reactors themselves. While the units were offline, work was carried out to improve the plant’s earthquake resistance. All units have remained offline since the Fukushima Daiichi accident.

Although it has worked on the other units at the Kashiwazaki-Kariwa site, Tepco is concentrating its resources on units 6 and 7 while it deals with the clean-up at Fukushima Daiichi. These 1,356 MWe ABWRs began commercial operation in 1996 and 1997, respectively, and were the first Japanese boiling water reactors to be put forward for restart. Tepco received permission from the NRA to restart units 6 and 7 in December 2017. Restarting those two Kashiwazaki-Kariwa units – which have been offline for periodic inspections since March 2012 and August 2011, respectively – would increase the company’s earnings by an estimated JPY100 billion (USD633 million) per year.

Since the Fukushima Daiichi accident, 14 Japanese reactors have gradually resumed operation.

   

  • Related Posts

    Application lodged to build microreactor at US university

    The (CPA) was submitted on 31 March by The Grainger College of Engineering at the University of Illinois Urbana-Champaign, NANO Nuclear Energy Inc’s partner for the KRONOS MMR deployment at…

    Growing recognition of nuclear fuel cycle’s importance, WNFC hears

    Speakers at the event co-organised by the Nuclear Energy Institute and World Nuclear Association highlighted the challenges and opportunities at a time when geopolitical uncertainty means nuclear energy – underpinned by…

    Have You Seen?

    Rural Co-ops Navigate a New Era of Load Growth, Rising Costs, and Policy Pressure

    • April 16, 2026
    Rural Co-ops Navigate a New Era of Load Growth, Rising Costs, and Policy Pressure

    ERCOT Sees Surge in Power Demand by 2030s Amid Data Center Growth

    • April 16, 2026
    ERCOT Sees Surge in Power Demand by 2030s Amid Data Center Growth

    Equinor Signals Trading Windfall as War-Driven Volatility Lifts Results

    • April 16, 2026
    Equinor Signals Trading Windfall as War-Driven Volatility Lifts Results

    TotalEnergies Sees Q1 Profit Surge on High Prices, Strong Trading

    • April 16, 2026
    TotalEnergies Sees Q1 Profit Surge on High Prices, Strong Trading

    Industry takes measures to shore up CO2 amid rising supply concerns

    • April 16, 2026
    Industry takes measures to shore up CO2 amid rising supply concerns

    US Forces Ready to Restart Combat if Iran Doesn’t Agree to a deal, Says Hegseth

    • April 16, 2026
    US Forces Ready to Restart Combat if Iran Doesn’t Agree to a deal, Says Hegseth

    LNG ramp-up drives record volumes at Corpus Christi in Texas

    • April 16, 2026
    LNG ramp-up drives record volumes at Corpus Christi in Texas

    TSMC warns of gas cost pressures as AI demand outpaces chip supply

    • April 16, 2026
    TSMC warns of gas cost pressures as AI demand outpaces chip supply

    India’s Cooking Gas Crisis Could Persist for Years

    • April 16, 2026
    India’s Cooking Gas Crisis Could Persist for Years

    Iran-Linked Tankers Test Limits of U.S. Hormuz Blockade

    • April 16, 2026
    Iran-Linked Tankers Test Limits of U.S. Hormuz Blockade