US Regulator Makes ‘Interventionist’ Pivot to Speed Data Centers

  • FERC approved orders to pressure grids to handle hyperscalers’ connection requests within 90 days, and is requiring data centers to pay for their own power and be flexible with electricity consumption.
  • Utilities must now disclose the cost of adding major new consumers to the grid, and grids covering almost two thirds of the US population must submit reports to FERC within 30 days to ensure enough power to meet data center demand.
  • FERC’s new approach is described as interventionist and unprecedented, with Chairman Laura Swett stating that the regulator will vigorously protect Americans and is aware of the economic benefit of data centers to the country.

The chairman of the US Federal Energy Regulatory Commission said moves to help AI data centers accelerate hook ups to the country’s electric grids reflect a new and more interventionist approach by the regulator.

FERC on Thursday approved a series of orders to pressure grids to handle hyperscalers’ connection requests within 90 days. The current process can take years.

The commission also said it’s requiring data centers to pay for their own power, and to be flexible with the amount of electricity that they consume. And utilities must now disclose the cost of adding major new consumers to the grid.


Get the Latest US Focused Energy News Delivered to You! It’s FREE:


“The way that our electric grid is now, with the generation that we have today, it is not going to work,” Laura Swett, FERC’s chairman, said in an interview with Bloomberg TV. “We have to be aggressive. We have to look at everything with fresh eyes and make interventionist and unprecedented action.”

The chair of the Federal Energy Regulatory Commission Laura Swett joined Balance of Power joined to discuss the power demand for data centers. She said interventionist and unprecedented action will be needed to connect power-hungry data centers to US grids while protecting consumers. Without changes, the country’s electric grids are “not going to work.”

Under Swett’s leadership, FERC is undergoing a sharp pivot. Formed in the late 1970s in response to that decade’s oil crisis, the regulator had developed a reputation as a sleepy steward of interstate electricity and natural gas markets. It also monitors prices for the transport of oil products by pipeline and approves natural gas projects.

FERC’s new posture comes as the Trump administration prioritizes AI as a key driver of American economic growth and a major factor in its geopolitical ambitions.

It’s also happening as electric demand spikes in the US — and after surging utility bills became a political lightning rod. Data centers are key contributors to both trends.

Under the moves FERC approved Thursday, grids that cover almost two thirds of the US population will need to submit reports to FERC within 30 days that ensure there’s enough power to meet data center demand. In less than 60 days, they’ll also have to justify why their existing pricing structures can accommodate new facilities, or propose changes.

“We are getting out of the doom loop,” said Arushi Sharma Frank, founder of Washington, D.C.-based venture studio Luminary Strategies LLC. “This is a first of its kind accountability framework for data centers.”

Under Swett, FERC has also been pressuring PJM Interconnection LLC, the largest grid in the US, to reform itself or face the risk of break up. PJM has been criticized for a slow response to the data center boom. A key conference to debate reforms is scheduled for next month.

“We are going to vigorously protect Americans more than we ever have before,” Swett said. “For the first time, the electric regulator in this country is very aware of the economic benefit that we may give to our country because data centers are the intersection of not just energy, but also national security and jobs.”

— With assistance from Ari Natter

Share This:


More News Articles

 

  • Related Posts

    Top US Refiners See Profits Soar, Step Up Investor Rewards

    By Nicole Jao Top refiners post combined second-quarter profit of $12.6 billion Capital returns to shareholders hit $6.3 billion in second quarter TD Cowen sees Marathon and Valero each repurchasing…

    BofA to Plow $250 Billion Into Critical Infrastructure Projects

    By Paula Seligson and Katherine Doherty Bank of America Corp. unveiled a $250 billion initiative to invest in critical infrastructure across the US over the next year, joining its peers…

    Have You Seen?

    PetroChina Q3 Profit Jumps to $7.78 Billion

    • October 28, 2026
    PetroChina Q3 Profit Jumps to $7.78 Billion

    Bahri Profit Hits $1.36 Billion as the World Scrambles for Tankers

    • October 28, 2026
    Bahri Profit Hits $1.36 Billion as the World Scrambles for Tankers

    QatarEnergy Extends LNG Force Majeure to End of 2026

    • October 28, 2026
    QatarEnergy Extends LNG Force Majeure to End of 2026

    China’s Refiners Turn to Africa and Brazil Crude as Freight Rates Ease

    • October 28, 2026
    China’s Refiners Turn to Africa and Brazil Crude as Freight Rates Ease

    ErreDue to supply two PEM electrolysers to jewellery firm

    • October 28, 2026
    ErreDue to supply two PEM electrolysers to jewellery firm

    Biomethane ‘left behind’ in UK Budget, says trade association

    • October 28, 2026
    Biomethane ‘left behind’ in UK Budget, says trade association

    UK-Taiwan launch CCUS partnership

    • October 28, 2026
    UK-Taiwan launch CCUS partnership

    UK Budget cuts carbon capture grants as Acorn faces funding uncertainty

    • October 28, 2026
    UK Budget cuts carbon capture grants as Acorn faces funding uncertainty

    Equinor Profits Triple as Oil and Gas Prices Surge

    • October 28, 2026
    Equinor Profits Triple as Oil and Gas Prices Surge

    China’s Wind and Solar Power Capacity Surpasses 2 Terawatts

    • October 28, 2026
    China’s Wind and Solar Power Capacity Surpasses 2 Terawatts