Sogin begins re-encapsulation of uranium-thorium fuel

Between 1968 and 1970, 84 elements of irradiated fuel from the uranium-thorium cycle from the Elk River experimental reactor in Minnesota, USA, were shipped to the Rotondella plant for reprocessing as part of a thorium fuel cycle research programme.

Between 1975 and 1978, a nuclear testing campaign was conducted on 20 of these elements, which produced three different radioactive liquid outcomes; one of these was the so-called final product, consisting of recovered fuel and fission elements in a nitric-based solution. Currently, the liquid radioactive waste present at the site is safely stored in a steel tank contained, in turn, in a very thick reinforced concrete structure.

Societa Gestione Impianti Nucleari (Sogin) has now begun the process of re-encapsulating the remaining 64 elements.

The operation involves transferring each fuel element from its current containment capsules into new capsules suitable for insertion into the two special casks already on-site. The fuel will then be loaded ‘dry’ into the two casks, which will be safely stored in the Rotondella site’s temporary storage facility pending their eventual transfer to the national radioactive waste repository, once it becomes available.

The operations will take place within the plant’s fuel storage pool, submerged under a layer of water to ensure natural radiation shielding. Activities will be carried out according to specific engineering procedures designed to guarantee safety throughout all operational phases and to allow for the visual inspection of all elements to verify their structural integrity. The re-encapsulation operations are scheduled for completion by mid-2027.

Sogin said the start of re-encapsulation operations “marks a significant milestone in the ‘dry storage’ process for this fuel – a key objective of the decommissioning programme for the Basilicata-based facility”.

In June 2023, Sogin awarded a contract worth EUR43 million (USD49 million) to a consortium comprising Ansaldo Nucleare and construction firm Monsud SpA for the construction of the Finished Product Cementation Plant (ICPF) at the Itrec facility. The ICPF facility is intended for the cementation of about 3 cubic metres of liquid uranium-thorium solution, referred to as ‘final product’, resulting from the experimental reprocessing operations performed on fuel during the Rotondella plant’s operation.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    • October 2, 2026
    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    Oil Prices Come Under Pressure

    • October 2, 2026
    Oil Prices Come Under Pressure