MNRE Clarifies ALMM List-II Compliance Rules For Government Rooftop Solar Projects

The Ministry of New and Renewable Energy (MNRE) has issued an important clarification on the implementation of the Approved List of Models & Manufacturers (ALMM) List-II requirements for solar PV cells used in rooftop solar projects on government buildings. The clarification was released through an official memorandum dated July 6, 2026, with the objective of removing confusion over the compliance requirements and ensuring uniform implementation across government-backed rooftop solar projects.

The ALMM framework has been introduced to promote the use of domestically manufactured solar equipment in India. Under this framework, ALMM List-I covers solar PV modules, while ALMM List-II applies to solar PV cells. The mandatory use of ALMM List-II compliant solar cells was originally scheduled to come into effect from June 1, 2026. However, following feedback and representations from industry stakeholders, the ministry has now clarified how the rules will apply to different categories of rooftop solar projects.

For rooftop solar projects on government buildings that were awarded through a competitive bidding process, MNRE has specified different compliance requirements based on the last date of bid submission. Projects where the final bid submission date was on or before December 9, 2024, will remain fully exempt from the ALMM List-II requirement. This means such projects can continue using solar cells that are not listed under ALMM List-II.

For projects with bid submission dates between December 9, 2024, and July 28, 2025, the applicable rules will be those mentioned in the original tender documents. The ministry has clarified that these projects will follow the conditions already specified at the time of bidding rather than any new compliance requirement.

Projects with bid submission dates between July 28, 2025, and August 31, 2025, have also been granted an exemption from the mandatory use of ALMM List-II compliant solar cells. However, any rooftop solar project where the last date for bid submission falls after August 31, 2025, must fully comply with ALMM List-II. Such projects will be required to procure solar PV cells only from manufacturers included in the approved list.

The ministry has also provided separate guidelines for rooftop solar projects on government buildings that are not awarded through competitive bidding. These include projects developed under Net-Metering and Open Access arrangements.

According to the clarification, projects commissioned before June 1, 2026, are exempt from the mandatory domestic solar cell requirement. However, projects commissioned on or after June 1, 2026, will generally have to comply with ALMM List-II.

MNRE has also referred to its earlier guidelines issued on May 25, 2026, which allow developers to seek a formal extension if their projects cannot meet the compliance deadline. If a competent authority approves the extension request, the concerned project will continue to remain exempt from the ALMM List-II requirement. If the extension is not approved, the project must use ALMM List-II-compliant solar PV cells.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    Tata Power Delhi Distribution Limited (Tata Power-DDL) has intensified its monsoon preparedness programme with network maintenance, safety inspections and emergency response measures aimed at ensuring uninterrupted power supply and enhancing…

    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    TP Saurya Limited has received relief from the Central Electricity Regulatory Commission (CERC), which has allowed the company to continue injecting infirm power from the 100 MW solar component of…

    Have You Seen?

    Icelandic tech firm installs record reactor at Chinese e-methanol plant

    • July 7, 2026
    Icelandic tech firm installs record reactor at Chinese e-methanol plant

    Ineos lines up blue hydrogen supply from Equinor-Engie for Antwerp cracker

    • July 7, 2026
    Ineos lines up blue hydrogen supply from Equinor-Engie for Antwerp cracker

    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    • July 7, 2026
    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    • July 7, 2026
    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    What Natural Gas Ascendancy Says About the US

    • July 7, 2026
    What Natural Gas Ascendancy Says About the US

    Russia’s Oil Windfall Vanishes as Urals Crashes to $42 a Barrel

    • July 7, 2026
    Russia’s Oil Windfall Vanishes as Urals Crashes to $42 a Barrel

    UAE Oil Production Nears Record High After OPEC Exit

    • July 7, 2026
    UAE Oil Production Nears Record High After OPEC Exit

    Jupiter International Wins ₹108 Crore LoE from MSEDCL for 5,000 Solar-Powered Agricultural Pumps

    • July 7, 2026
    Jupiter International Wins ₹108 Crore LoE from MSEDCL for 5,000 Solar-Powered Agricultural Pumps

    CEA Directs Discoms to Strengthen Distribution Networks to Prevent Summer Power Outages

    • July 7, 2026
    CEA Directs Discoms to Strengthen Distribution Networks to Prevent Summer Power Outages

    Serentica Renewables Signs PPA with SECI for 600 MW FDRE Project

    • July 7, 2026
    Serentica Renewables Signs PPA with SECI for 600 MW FDRE Project