HERC Orders Full Open Access Approval For 100 MW Renewable Energy Procurement In Haryana

The Haryana Electricity Regulatory Commission (HERC) has ruled in favor of Jindal Stainless Limited (JSL) in a major case involving renewable energy procurement through open access. In its order dated June 23, 2026, the commission directed the Haryana state power utilities to grant the necessary regulatory clearance for the company’s renewable power supply after completing the required operational formalities.

The dispute began after JSL approached HERC when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited (HVPNL), and the Grid Co-ordination Committee refused to issue a full No Objection Certificate (NOC). The company had sought approval to source 100 MW of round-the-clock (RTC) renewable power from its captive interstate-connected wind-solar hybrid projects located in Gujarat and Madhya Pradesh. The renewable power was intended to meet the electricity needs of JSL’s manufacturing facility in Hisar, Haryana.

The state utilities opposed the request during the peak summer months of June, July, and August. They argued that Haryana experiences heavy electricity demand during this period because of increased cooling requirements and agricultural consumption. According to the utilities, the state’s peak demand could reach around 16,500 MW, creating transmission constraints. They also stated that allowing JSL’s long-term power transfer could reduce the state’s flexibility to import emergency power through Temporary General Network Access (T-GNA) and increase Deviation Settlement Mechanism (DSM) charges. Based on these concerns, the utilities granted only partial approval for off-peak periods.

JSL challenged the decision before HERC, arguing that the partial denial violated the Electricity Act, 2003, and the principles of non-discriminatory open access. The company claimed that the decision was intended to force it to continue buying expensive electricity from state distribution companies during high-demand periods. JSL explained that its renewable energy procurement would simply replace its existing grid power consumption and would not increase the overall demand on the state’s electricity network.

To address concerns over grid reliability, JSL made several voluntary commitments. The company agreed to accept complete curtailment of up to 100 MW of renewable power during severe grid constraints without seeking any compensation from the state. It also agreed to bear all costs and risks related to DSM charges. According to JSL, shifting to captive renewable energy would reduce the burden on Haryana’s discoms and help them avoid costly short-term power purchases, resulting in estimated annual savings of ₹65 crore to ₹100 crore.

After examining the matter, HERC ruled that the utilities’ blanket restriction during the summer months was not legally justified. The commission observed that long-term open access enjoys higher priority under national regulations than temporary arrangements such as T-GNA. It also noted that denying open access to renewable energy projects could discourage private investment and hinder India’s target of achieving 500 GW of non-fossil fuel capacity by 2030.

HERC directed HVPNL to develop the required operational procedures, undertakings, and mechanisms for implementing JSL’s voluntary curtailment and DSM commitments within two weeks. After these arrangements are completed, the utility has been instructed to issue the full NOC, enabling JSL to procure the approved 100 MW of renewable energy for its Haryana facility.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    Tata Power Delhi Distribution Limited (Tata Power-DDL) has intensified its monsoon preparedness programme with network maintenance, safety inspections and emergency response measures aimed at ensuring uninterrupted power supply and enhancing…

    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    TP Saurya Limited has received relief from the Central Electricity Regulatory Commission (CERC), which has allowed the company to continue injecting infirm power from the 100 MW solar component of…

    Have You Seen?

    Icelandic tech firm installs record reactor at Chinese e-methanol plant

    • July 7, 2026
    Icelandic tech firm installs record reactor at Chinese e-methanol plant

    Ineos lines up blue hydrogen supply from Equinor-Engie for Antwerp cracker

    • July 7, 2026
    Ineos lines up blue hydrogen supply from Equinor-Engie for Antwerp cracker

    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    • July 7, 2026
    Tata Power-DDL Steps Up Monsoon Preparedness to Strengthen Grid Reliability and Public Safety

    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    • July 7, 2026
    CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

    What Natural Gas Ascendancy Says About the US

    • July 7, 2026
    What Natural Gas Ascendancy Says About the US

    Russia’s Oil Windfall Vanishes as Urals Crashes to $42 a Barrel

    • July 7, 2026
    Russia’s Oil Windfall Vanishes as Urals Crashes to $42 a Barrel

    UAE Oil Production Nears Record High After OPEC Exit

    • July 7, 2026
    UAE Oil Production Nears Record High After OPEC Exit

    Jupiter International Wins ₹108 Crore LoE from MSEDCL for 5,000 Solar-Powered Agricultural Pumps

    • July 7, 2026
    Jupiter International Wins ₹108 Crore LoE from MSEDCL for 5,000 Solar-Powered Agricultural Pumps

    CEA Directs Discoms to Strengthen Distribution Networks to Prevent Summer Power Outages

    • July 7, 2026
    CEA Directs Discoms to Strengthen Distribution Networks to Prevent Summer Power Outages

    Serentica Renewables Signs PPA with SECI for 600 MW FDRE Project

    • July 7, 2026
    Serentica Renewables Signs PPA with SECI for 600 MW FDRE Project