Dutch nuclear new build timeline set to slip

Wednesday, 12 February 2025

Dutch nuclear new build timeline set to slip
Borssele nuclear power plant (Image: Amentum)

In December 2021, the Netherlands’ coalition government placed nuclear power at the heart of its climate and energy policy. Based on preliminary plans, two new reactors would be completed around 2035 and each have a capacity of 1000-1650 MWe. The two reactors would provide 9-13% of the Netherlands’ electricity production in 2035. The cabinet announced in December 2022 that it currently sees the existing Borssele nuclear power plant site as the most suitable location for the construction of the new reactors.

As well as Borssele, two other locations are being considered for the reactors: the Tweede Maasvlakte near Rotterdam and Terneuzen in Zeeland. Eemshaven in Groningen had previously been excluded due to strong local opposition.

However, Hermans has now said that, based on the advice of the Dutch attorney general (the State Advocate), Eemshaven will again be included in the list of potential locations. 

“This is a dilemma for the cabinet,” she said in a letter to parliament. “On the one hand, the cabinet does not consider it appropriate to investigate Eemshaven in view of the agreements made to remove Eemshaven as a guarantee area. On the other hand, the cabinet considers due care and robust decision-making to be crucial. 

“All things considered and with a view to the advice of the State Advocate, the cabinet concludes that it is unfortunately not possible to exclude the Eemshaven area from the Environmental Impact Assessment procedure in advance and at the same time arrive at a legally tenable decision. Failure to investigate the Eemshaven area leads to too great a legal risk, which could ultimately result in the project decision being annulled by the Council of State.”

She added: “Not including Eemshaven would in all probability lead to (more) delays in the future, because additional investigation would have to be carried out at a very late stage in order to reach a sustainable decision. The impact will then only be greater, because part of the investigation would then have to be done again. Moreover, this would significantly hinder other work tracks, such as financing and technology selection.”

Hermans said she will make a decision on the preferred location for the two new reactors, in consultation with the Minister of Housing and Spatial Planning, once the location investigation has been completed.

“As soon as possible this year, the government will announce which location alternatives it will investigate. Then more will become clear about the planning of the location choice, which until now was set at mid-2025,” she said. “It is clear that this year is no longer feasible for the location choice.

“What this delay means for the final construction and delivery of the two nuclear reactors is not yet clear. However, it does not seem realistic to have the first reactor operational in 2035. A great many steps still have to be completed before we can start building two new reactors. Both in the spatial procedure, in the tender, in the granting of permits, and in the final construction. A detailed planning of all these steps is not yet available at this time.”

The Dutch government earlier awarded contracts to Westinghouse and to Korea Hydro & Nuclear Power to conduct technical feasibility studies on the deployment of their respective reactors at Borssele, saying it also intended to award a similar contract to EDF. In November, Amentum of the USA was selected to review and advise on the studies submitted by the three potential reactor vendors.

   

  • Related Posts

    Viewpoint: Four million workers won’t be enough without the right leaders

    Somewhere in the nuclear industry today is the engineer who will bring a country’s first reactor online, the regulator who will license it, and the financier who will make it…

    FID sees Etango enter full-scale construction 

    The Etango project is in the Erongo Region of Namibia, 30 kilometres south-east of Swakopmund, with an estimated mineral resource base of 207 million pounds U3O8 (79,622 tU) at a…

    Have You Seen?

    Global Energy Transition Requires 38.2 TW Renewable Capacity by 2050, Stronger Grids and Energy Efficiency – Report

    • October 24, 2026
    Global Energy Transition Requires 38.2 TW Renewable Capacity by 2050, Stronger Grids and Energy Efficiency – Report

    Solidus Techno Power Integrates 27.31 MWh BESS With 50 MW Solar Project For SBF Ispat

    • October 24, 2026
    Solidus Techno Power Integrates 27.31 MWh BESS With 50 MW Solar Project For SBF Ispat

    ACCIONA Energía Starts Operations Of 72 MW Wind Farms In Croatia

    • October 24, 2026
    ACCIONA Energía Starts Operations Of 72 MW Wind Farms In Croatia

    Solidus Techno Power Delivers 27.31 MWh BESS For SBF Ispat’s 50 MW Solar Project

    • October 24, 2026
    Solidus Techno Power Delivers 27.31 MWh BESS For SBF Ispat’s 50 MW Solar Project

    Kerala Engineering College Invites Tender For Green Hydrogen Research Equipment

    • October 24, 2026
    Kerala Engineering College Invites Tender For Green Hydrogen Research Equipment

    RE:MAKE India 2026 to Connect Renewable Energy Manufacturing, Technology and Supply Chains at Yashobhoomi

    • October 24, 2026
    RE:MAKE India 2026 to Connect Renewable Energy Manufacturing, Technology and Supply Chains at Yashobhoomi

    NVVN Invites Bids For Rooftop Solar Project At NIB Noida

    • October 24, 2026
    NVVN Invites Bids For Rooftop Solar Project At NIB Noida

    Fourth Partner Energy Executes 75 MWp Open Access Solar Park In Maharashtra

    • October 24, 2026
    Fourth Partner Energy Executes 75 MWp Open Access Solar Park In Maharashtra

    Three Weeks to Go: Thailand Clean Energy Week 2026 Brings Industry Leaders Together in Bangkok

    • October 24, 2026
    Three Weeks to Go: Thailand Clean Energy Week 2026 Brings Industry Leaders Together in Bangkok

    Buskowitz Energy Wins Company of the Year – Solar EPC (Commercial/Industrial)

    • October 24, 2026
    Buskowitz Energy Wins Company of the Year – Solar EPC (Commercial/Industrial)