Posiva completes backfilling trial run at repository

Friday, 14 March 2025

Posiva completes backfilling trial run at repository
The tunnel filling installation system (Image: Posiva)

At the repository, used fuel will be placed in the bedrock, at a depth of about 430 metres. The disposal system consists of a tightly sealed iron-copper canister, a bentonite buffer enclosing the canister, a tunnel backfilling material made of swellable clay, the seal structures of the tunnels and premises, and the enclosing rock.

The procedure qualification test on backfill installation was designed to demonstrate the operability of the systems and equipment in tunnel conditions at a depth of 435 metres in the bedrock. Another requirement was to achieve the specified result by deploying the operating methods and procedures that will be deployed during operation of the repository.

The minimum goal for the test, which took about three weeks, was to fill at least 10 metres of tunnel. The actual test acceptance criterion was to achieve a tunnel backfill degree of a minimum of 98%. Posiva noted that analyses that are still to be verified indicate that the achieved backfill degree exceeded this criterion.

“The large, long combination machine almost fills the entire tunnel and compacts clay with large screws while pushing it into the tunnel,” said Posiva Development Manager Ari Maarni. “At the same time, it reverses slowly in order to achieve a uniform backfill degree. During the test, the transfer vehicle ran autonomously between the discharge station and the installation machine supplying more clay to the installation machine.”

Maarni noted that the biggest challenges during the test were caused by the uneven floor of the tunnel. “The docking of the transfer vehicle to the installation machine was difficult in points with large surface height differences. This slowed down the work. However, as the test proceeded a lot was learned and we were able to adjust the equipment to operate faster.”

The qualification test was carried out in the 50-metre-long tunnel used for the Trial Run of Final Disposal. The remaining 40 metres of the tunnel will be filled in the actual Trial Run of Underground Operation, before the tunnel is finally sealed.

The next installation procedure qualification tests will focus on testing the buffer installation system as well as the canister transfer and installation vehicle. These installation procedure qualification tests will be carried out as the last ones, and in practice parallel with each other, before the actual underground stage of the Trial Run of Final Disposal.

During the Trial Run, the operation of the complete final disposal facility is tested. Instead of actual used nuclear fuel, the trial run is conducted using non-radioactive test elements.

The Finnish government granted Posiva a construction licence for the project in November 2015 and construction work on the repository started in December 2016. Once it receives the operating licence, Posiva can start the final disposal of the used fuel generated from the operation of TVO’s Olkiluoto and Fortum’s Loviisa nuclear power plants. The operation will last for about 100 years before the repository is closed.

   

  • Related Posts

    Nineteen years on, companies team up for US new-build project

    Fulcrum Point is an affiliate of Utah nuclear services company Hi Tech Solutions. Last year, Hi Tech Solutions signed a strategic cooperation agreement with Holtec International and the State of Utah…

    Decommissioning milestone reached at Trawsfynydd

    The 392 MWe Trawsfynydd Magnox nuclear power plant – the only inland nuclear power station in the UK – began operation in 1965 and was retired in 1991, with defueling…

    Have You Seen?

    Iran, US Tentatively Agree to Renew Truce for 60 Days

    • May 30, 2026
    Iran, US Tentatively Agree to Renew Truce for 60 Days

    EBRD Supports Sustainable Agriculture Development Through Green Financing In Mongolia

    • May 30, 2026
    EBRD Supports Sustainable Agriculture Development Through Green Financing In Mongolia

    Koraam Powered by Kosol Energie Secures 4th Order from MSEDCL for Solar Water Pumping Systems

    • May 30, 2026
    Koraam Powered by Kosol Energie Secures 4th Order from MSEDCL for Solar Water Pumping Systems

    Indonesia Pushes Ahead With 100 GW Solar Power Plan, Focuses On Fast-Track Renewable Energy Growth

    • May 30, 2026
    Indonesia Pushes Ahead With 100 GW Solar Power Plan, Focuses On Fast-Track Renewable Energy Growth

    Asia-Pacific Dominates Global Solar Growth With 68% Share Of Worldwide Installations

    • May 30, 2026
    Asia-Pacific Dominates Global Solar Growth With 68% Share Of Worldwide Installations

    PM Surya Ghar Scheme Solarises 40 Lakh Households, Accelerating India’s Rooftop Solar Growth

    • May 30, 2026
    PM Surya Ghar Scheme Solarises 40 Lakh Households, Accelerating India’s Rooftop Solar Growth

    Oil Falls on Hopes for US-Iran Ceasefire Agreement

    • May 30, 2026
    Oil Falls on Hopes for US-Iran Ceasefire Agreement

    Devon Energy Gets $8 Billion Offer for Marcellus Position, Sources Say

    • May 30, 2026
    Devon Energy Gets $8 Billion Offer for Marcellus Position, Sources Say

    US Crude Production Largely Steady on the Month in March, EIA Says

    • May 29, 2026
    US Crude Production Largely Steady on the Month in March, EIA Says

    Chevron Won’t Pay Toll to Move Ships Through Hormuz, CEO Tells Bloomberg TV

    • May 29, 2026
    Chevron Won’t Pay Toll to Move Ships Through Hormuz, CEO Tells Bloomberg TV