Posiva completes backfilling trial run at repository

Friday, 14 March 2025

Posiva completes backfilling trial run at repository
The tunnel filling installation system (Image: Posiva)

At the repository, used fuel will be placed in the bedrock, at a depth of about 430 metres. The disposal system consists of a tightly sealed iron-copper canister, a bentonite buffer enclosing the canister, a tunnel backfilling material made of swellable clay, the seal structures of the tunnels and premises, and the enclosing rock.

The procedure qualification test on backfill installation was designed to demonstrate the operability of the systems and equipment in tunnel conditions at a depth of 435 metres in the bedrock. Another requirement was to achieve the specified result by deploying the operating methods and procedures that will be deployed during operation of the repository.

The minimum goal for the test, which took about three weeks, was to fill at least 10 metres of tunnel. The actual test acceptance criterion was to achieve a tunnel backfill degree of a minimum of 98%. Posiva noted that analyses that are still to be verified indicate that the achieved backfill degree exceeded this criterion.

“The large, long combination machine almost fills the entire tunnel and compacts clay with large screws while pushing it into the tunnel,” said Posiva Development Manager Ari Maarni. “At the same time, it reverses slowly in order to achieve a uniform backfill degree. During the test, the transfer vehicle ran autonomously between the discharge station and the installation machine supplying more clay to the installation machine.”

Maarni noted that the biggest challenges during the test were caused by the uneven floor of the tunnel. “The docking of the transfer vehicle to the installation machine was difficult in points with large surface height differences. This slowed down the work. However, as the test proceeded a lot was learned and we were able to adjust the equipment to operate faster.”

The qualification test was carried out in the 50-metre-long tunnel used for the Trial Run of Final Disposal. The remaining 40 metres of the tunnel will be filled in the actual Trial Run of Underground Operation, before the tunnel is finally sealed.

The next installation procedure qualification tests will focus on testing the buffer installation system as well as the canister transfer and installation vehicle. These installation procedure qualification tests will be carried out as the last ones, and in practice parallel with each other, before the actual underground stage of the Trial Run of Final Disposal.

During the Trial Run, the operation of the complete final disposal facility is tested. Instead of actual used nuclear fuel, the trial run is conducted using non-radioactive test elements.

The Finnish government granted Posiva a construction licence for the project in November 2015 and construction work on the repository started in December 2016. Once it receives the operating licence, Posiva can start the final disposal of the used fuel generated from the operation of TVO’s Olkiluoto and Fortum’s Loviisa nuclear power plants. The operation will last for about 100 years before the repository is closed.

   

  • Related Posts

    First fast reactor fuel safety tests in decades carried out at INL

    Friday, 14 March 2025 TREAT: INL says the tests are the first of their kind anywhere in the world in over 20 years (Image: INL) Transient tests on a high-burnup…

    Newcleo plans fuel development centre

    Friday, 14 March 2025 (Image: Pininfarina) Newcleo said the FASTER (Fuel process Assembly Storage Training and Enhanced Reality) centre, which will not store or handle any radioactive materials, will play…

    Have You Seen?

    Oil Rebounds 1% to End Week Steady Amid Prospect of Ukraine Ceasefire

    • March 15, 2025
    Oil Rebounds 1% to End Week Steady Amid Prospect of Ukraine Ceasefire

    Williams Says it Welcomes Trump’s Support for Constitution Gas Pipeline

    • March 14, 2025
    Williams Says it Welcomes Trump’s Support for Constitution Gas Pipeline

    Wildcatter Harold Hamm Says Shale Needs $80 Oil for Costly Fields

    • March 14, 2025
    Wildcatter Harold Hamm Says Shale Needs $80 Oil for Costly Fields

    CERAWEEK Texas LNG Aims to Make Final Investment Decision by December

    • March 14, 2025
    CERAWEEK Texas LNG Aims to Make Final Investment Decision by December

    Brazil’s Petrobras in Talks With US LNG Suppliers for Long-Term Deal, Executive Says

    • March 14, 2025
    Brazil’s Petrobras in Talks With US LNG Suppliers for Long-Term Deal, Executive Says

    Chevron Advances Plans to Develop US Data Centers With Power Generation

    • March 14, 2025
    Chevron Advances Plans to Develop US Data Centers With Power Generation

    US Oil and Gas Rig Count Unchanged This Week, Baker Hughes Says

    • March 14, 2025
    US Oil and Gas Rig Count Unchanged This Week, Baker Hughes Says

    Alaska LNG Project Could Start Up as Soon as 2030, State Governor Says

    • March 14, 2025
    Alaska LNG Project Could Start Up as Soon as 2030, State Governor Says

    ADNOC Considers Buying UAE Sovereign Fund’s Energy Assets

    • March 14, 2025
    ADNOC Considers Buying UAE Sovereign Fund’s Energy Assets

    U.S. and Vietnam Sign $4-Billion Energy and Minerals Deals

    • March 14, 2025
    U.S. and Vietnam Sign $4-Billion Energy and Minerals Deals