GUVNL’s Phase IX Solar Projects Face Delays Due To Land Allotment Issues In Gujarat

Representational image. Credit: Canva

On April 3, 2025, the Gujarat Electricity Regulatory Commission (GERC) heard the petition filed by Gujarat Urja Vikas Nigam Limited (GUVNL), along with related interlocutory applications. The case revolves around a solar project under GUVNL’s Phase IX bidding, in which multiple developers, including TEQ Green Power Pvt. Ltd., Vena Energy Renewables Urja Pvt. Ltd., Tata Power Company Ltd., and others, were awarded capacities.

GUVNL submitted that it had applied on October 10, 2024, seeking to amend its original petition to include two additional respondents—SJVN Ltd. and ReNew Solar Power Pvt. Ltd.—who were not part of the original filing. The commission directed GUVNL to serve copies of the amendment application to all respondents and asked for an affidavit confirming service. Respondents were given two weeks to respond.

A key issue that emerged during the hearing was the delay in land demarcation and allocation by Gujarat Power Corporation Ltd. (GPCL), which is impacting the timely execution of awarded solar power projects. TEQ Green Power Pvt. Ltd., a respondent in the case, informed the commission that despite signing the Power Purchase Agreement (PPA) on March 20, 2024, they have not been allotted the project land in the Special Economic Zone (SEZ), which has led to delays. TEQ submitted that it had already invested heavily in contracts and preparatory works, and urged the commission to direct GPCL to expedite land allotment and submit necessary documents.

Veena Energy and Tata Power, who had earlier indicated that land issues were resolved, revised their stance and raised concerns during the latest hearing. Their counsels argued that GPCL had changed the terms regarding land demarcation and increased the development charge per megawatt from the earlier ₹13.98 lakh, causing confusion and delay. The commission questioned why these companies had previously indicated that the issue was resolved despite no formal communication or documentation from GPCL.

GPCL confirmed that it had submitted its response, which included clarifications about the current status of land allocation and demarcation. The commission directed all other respondents to file their replies within two weeks and asked GUVNL to file a rejoinder within one week after receiving the responses.

The commission emphasized the duty of GPCL to allocate land on time to avoid project delays and potential penalties for developers. It also noted that the sudden change in charges and lack of formal land demarcation documents could negatively affect project timelines and coordination among developers.

The commission acknowledged the seriousness of delays due to land issues and scheduled further proceedings, the date of which will be announced later. All parties were instructed to complete the exchange of documents and responses in the given timeframe to avoid any further hold-up in the matter.

 

  • Related Posts

    Australia Boosts Local Battery Manufacturing With $2.3 Million Grant To Powerplus Energy

    Representational image. Credit: Canva The Australian federal government has taken a significant step to strengthen its clean energy sector by awarding a $2.3 million grant to PowerPlus Energy, a local…

    Guiuan Moves Toward Energy Independence With New Renewable Energy Roadmap

    Representational image. Credit: Canva The municipality of Guiuan in Eastern Samar is taking an important step toward improving its energy situation by launching a detailed Renewable Energy Plan and Roadmap.…

    Have You Seen?

    TECHNOLOGY: China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    • April 22, 2026
    TECHNOLOGY: China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    US Supreme Court Rrejects Enbridge Challenge to Michigan Pipeline Case

    • April 22, 2026
    US Supreme Court Rrejects Enbridge Challenge to Michigan Pipeline Case

    Oil Flows via Druzhba Set To Restart Today

    • April 22, 2026
    Oil Flows via Druzhba Set To Restart Today

    UK, France Lead 30-Nation Military Push to Reopen Strait of Hormuz

    • April 22, 2026
    UK, France Lead 30-Nation Military Push to Reopen Strait of Hormuz

    Lufthansa Cancels Unprofitable European Summer Routes to Save Jet Fuel

    • April 22, 2026
    Lufthansa Cancels Unprofitable European Summer Routes to Save Jet Fuel

    Traders Place $430 Million Bet on Lower Oil Price Before Trump Ceasefire Extension

    • April 22, 2026
    Traders Place $430 Million Bet on Lower Oil Price Before Trump Ceasefire Extension

    Iran Ceasefire Extension Reduces Immediate Escalation Risk

    • April 22, 2026
    Iran Ceasefire Extension Reduces Immediate Escalation Risk

    Air Liquide to build $350m ASU for Louisiana steel plant

    • April 22, 2026
    Air Liquide to build $350m ASU for Louisiana steel plant

    Terra Innovatum secures helium circulator supply deal

    • April 22, 2026
    Terra Innovatum secures helium circulator supply deal

    Death Toll From Boiler Explosion at Vedanta’s India Coal Power Plant Rises to 24, Triggers Probes

    • April 22, 2026
    Death Toll From Boiler Explosion at Vedanta’s India Coal Power Plant Rises to 24, Triggers Probes