CERC Forms Committee To Evaluate SCOD Extensions For Renewable And Storage Projects

Representational image. Credit: Canva

The Central Electricity Regulatory Commission (CERC) issued an office order on July 30, 2025, to constitute a committee for recommending extensions in the Scheduled Commercial Operation Date (SCOD) of certain renewable energy and energy storage projects. This is in reference to Regulation 13(2)(h) of the amended CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020, which were published on July 4, 2025.

According to the revised regulation, renewable energy generating stations (REGS) based on wind, solar, or hybrid sources, and Battery Energy Storage Systems (ESS), which are eligible for inter-state transmission charge waivers and have their SCOD on or before June 30, 2025, can seek an extension if they fail to meet the timeline due to Force Majeure events or reasons beyond their control. If the project achieves COD within the extended time, it will still qualify for the waiver as if it had been commissioned by June 30, 2025.

Such extensions can be granted up to a maximum of two times, each not exceeding six months. In cases where there is no Power Purchase Agreement under Section 63 of the Electricity Act, the CERC will decide on the extension based on the recommendation of a designated committee.

The committee includes Sh. Indu Shekhar Jha (Ex-Member, CERC) as Chairman, Ms. Anjuli Chandra (Ex-Member, PSERC), Sh. A.K. Rajput (Ex-Member, CEA), and the COO of CTUIL, as the Convenor. They may also co-opt other experts if needed, and secretarial support will be provided by CTUIL.

The extension process involves three steps. First, the REGS or ESS must apply to the Committee with all relevant documents and send a copy to the buyer, if applicable. The application should be sent to CTUIL at its Gurugram office. Second, the Committee will analyze and conduct prudence checks before submitting its recommendation to the Commission within three months. Third, the Commission will issue an order accepting or rejecting the extension.

The Committee’s term is 18 months from the date of the order or until a further order is issued, whichever is earlier. Retired members of the committee will receive per-sitting remuneration following Regulation 60A of the Conduct of Business Regulations.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Desert Solar Innovation Tackling Heat And Dust To Maximize Efficiency

    Representational image. Credit: Canva The global solar energy sector is growing rapidly, but the focus is now shifting from just adding more capacity to improving performance, especially in challenging environments.…

    International Energy Agency Brings 200+ Global Energy Leaders To Mexico City To Boost Efficiency And Energy Security

    Policymakers and industry leaders from across Latin America and the Caribbean gathered in Mexico City this week to exchange knowledge and best practices on strengthening energy efficiency as a pathway…

    Have You Seen?

    Crowley’s LNG carrier marks first year of supply to Puerto Rico

    • April 17, 2026
    Crowley’s LNG carrier marks first year of supply to Puerto Rico

    Switzerland could cut gas imports by half with domestic biomethane, study finds

    • April 17, 2026
    Switzerland could cut gas imports by half with domestic biomethane, study finds

    Earlbeck Gases CEO talks AI impact, industry connections, and GAWDA

    • April 17, 2026
    Earlbeck Gases CEO talks AI impact, industry connections, and GAWDA

    Freedom of passage and security to dominate global strait summit

    • April 17, 2026
    Freedom of passage and security to dominate global strait summit

    Spirit Energy Reveals Proposal to Restructure UK Organization

    • April 17, 2026
    Spirit Energy Reveals Proposal to Restructure UK Organization

    NASA tests cost-saving cryogenic tech for spacecraft

    • April 17, 2026
    NASA tests cost-saving cryogenic tech for spacecraft

    Polish, Hungarian trade bodies look to set up Central European hydrogen auction

    • April 17, 2026
    Polish, Hungarian trade bodies look to set up Central European hydrogen auction

    India’s Central Bank Tells Oil Refiners To Stop Buying Dollars On Spot Market

    • April 17, 2026
    India’s Central Bank Tells Oil Refiners To Stop Buying Dollars On Spot Market

    IEA Chief Says Oil, Gas Recovery Could Take Two Years After War Damage

    • April 17, 2026
    IEA Chief Says Oil, Gas Recovery Could Take Two Years After War Damage

    A Lebanon Ceasefire and Potential Iran Peace Talks Push Oil Prices Down

    • April 17, 2026
    A Lebanon Ceasefire and Potential Iran Peace Talks Push Oil Prices Down