Changjiang 3 containment building completed

Tuesday, 1 July 2025

Changjiang 3 containment building completed
(Image: CNNC)

“This marks the completion of the main structure of the reactor building of the nuclear island of unit 3 and the entry of the project construction into a new stage, laying a solid foundation for the full launch of subsequent nuclear island hot test and commissioning,” China National Nuclear Corporation said.

First concrete was poured for the base slab of unit 3’s nuclear island in March 2021, with that of unit 4 being poured in the December of that year. Changjiang Phase II – units 3 and 4 – represents a total estimated investment of CNY40 billion (USD6.4 billion), according to China Huaneng, which holds a 51% share in the project, with China National Nuclear Corporation holding the remaining 49%. The construction period is expected to be 60 months. Both Hualong One (HPR1000) units are scheduled to be fully operational in early 2027.

The Hualong One reactor design features a double-layered containment building, the main function of which is to ensure the integrity and leak tightness of the reactor building, and it plays a key role in the containment of radioactive substances.

The steel dome for Changjiang unit 3’s inner containment – measuring more than 46 metres in diameter and 23 metres in height – was placed on top of the walls of the double containment structure in February 2023.

The outer steel dome – measuring 53 metres in diameter, 13 metres in height and weighing about 415 tonnes – was hoisted into place on top of the containment building in October last year.

Cold hydrostatic testing – carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition – were completed in April. These will now be followed by hot functional tests, which involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should.

The Changjiang nuclear site is already home to two operating CNP-600 pressurised water reactors (PWRs) – Changjiang 1 and 2 – which entered commercial operation in 2015 and 2016, respectively. In 2021, CNNC also began construction of a demonstration ACP100 small modular reactor at the site. The multi-purpose 125 MWe PWR – also referred to as the Linglong One – is designed for electricity production, heating, steam production or seawater desalination.

   

  • Related Posts

    Podcast: World Nuclear Symposium 2026

    People featured, in order of appearance: Sama Bilbao y León, Director General, World Nuclear Association Mark Muldowney, MD, Energy, Resources and Infrastructure, BNP Paribas Alejandro López Delgado, Managing Director, Infrastructure,…

    Hydraulic tests completed at Turkey’s Akkuyu 1

    During the tests, the pressure in the primary circuit (the reactor, main circulation pumps, steam generators, the pressuriser, and the main circulation pipeline connecting them) was increased to 24.5 MPa…

    Have You Seen?

    IEA Members Support Oil Stock Release Acceleration

    • October 10, 2026
    IEA Members Support Oil Stock Release Acceleration

    ACEN Secures €50 Million Loan To Expand Renewable Energy Portfolio

    • October 10, 2026
    ACEN Secures €50 Million Loan To Expand Renewable Energy Portfolio

    Clean Max To Acquire 100% Stake In Thailand’s Massmunch Company For THB 1.25 Million

    • October 10, 2026
    Clean Max To Acquire 100% Stake In Thailand’s Massmunch Company For THB 1.25 Million

    ESCOM Opens Tender For 20 MW/40 MWh Grid-Forming Battery Storage Project In Malawi

    • October 10, 2026
    ESCOM Opens Tender For 20 MW/40 MWh Grid-Forming Battery Storage Project In Malawi

    Offshore Wind And Ocean Energy Offer Small Island Nations A Path To Energy Security – IRENA

    • October 10, 2026
    Offshore Wind And Ocean Energy Offer Small Island Nations A Path To Energy Security – IRENA

    SECI Floats Tender for 120 MW Solar Project with 60 MW/240 MWh Battery Storage in Bihar’s Aurangabad District

    • October 10, 2026
    SECI Floats Tender for 120 MW Solar Project with 60 MW/240 MWh Battery Storage in Bihar’s Aurangabad District

    Crude Oil is Underpriced, Energy Aspects Says

    • October 9, 2026
    Crude Oil is Underpriced, Energy Aspects Says

    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    • October 9, 2026
    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    129 Gulf Platforms Evacuated as Isaias Gets Stronger

    • October 9, 2026
    129 Gulf Platforms Evacuated as Isaias Gets Stronger

    Lessons from Covid: Achieving resilience in medical oxygen supply

    • October 9, 2026
    Lessons from Covid: Achieving resilience in medical oxygen supply