Dutch nuclear new build timeline set to slip

Wednesday, 12 February 2025

Dutch nuclear new build timeline set to slip
Borssele nuclear power plant (Image: Amentum)

In December 2021, the Netherlands’ coalition government placed nuclear power at the heart of its climate and energy policy. Based on preliminary plans, two new reactors would be completed around 2035 and each have a capacity of 1000-1650 MWe. The two reactors would provide 9-13% of the Netherlands’ electricity production in 2035. The cabinet announced in December 2022 that it currently sees the existing Borssele nuclear power plant site as the most suitable location for the construction of the new reactors.

As well as Borssele, two other locations are being considered for the reactors: the Tweede Maasvlakte near Rotterdam and Terneuzen in Zeeland. Eemshaven in Groningen had previously been excluded due to strong local opposition.

However, Hermans has now said that, based on the advice of the Dutch attorney general (the State Advocate), Eemshaven will again be included in the list of potential locations. 

“This is a dilemma for the cabinet,” she said in a letter to parliament. “On the one hand, the cabinet does not consider it appropriate to investigate Eemshaven in view of the agreements made to remove Eemshaven as a guarantee area. On the other hand, the cabinet considers due care and robust decision-making to be crucial. 

“All things considered and with a view to the advice of the State Advocate, the cabinet concludes that it is unfortunately not possible to exclude the Eemshaven area from the Environmental Impact Assessment procedure in advance and at the same time arrive at a legally tenable decision. Failure to investigate the Eemshaven area leads to too great a legal risk, which could ultimately result in the project decision being annulled by the Council of State.”

She added: “Not including Eemshaven would in all probability lead to (more) delays in the future, because additional investigation would have to be carried out at a very late stage in order to reach a sustainable decision. The impact will then only be greater, because part of the investigation would then have to be done again. Moreover, this would significantly hinder other work tracks, such as financing and technology selection.”

Hermans said she will make a decision on the preferred location for the two new reactors, in consultation with the Minister of Housing and Spatial Planning, once the location investigation has been completed.

“As soon as possible this year, the government will announce which location alternatives it will investigate. Then more will become clear about the planning of the location choice, which until now was set at mid-2025,” she said. “It is clear that this year is no longer feasible for the location choice.

“What this delay means for the final construction and delivery of the two nuclear reactors is not yet clear. However, it does not seem realistic to have the first reactor operational in 2035. A great many steps still have to be completed before we can start building two new reactors. Both in the spatial procedure, in the tender, in the granting of permits, and in the final construction. A detailed planning of all these steps is not yet available at this time.”

The Dutch government earlier awarded contracts to Westinghouse and to Korea Hydro & Nuclear Power to conduct technical feasibility studies on the deployment of their respective reactors at Borssele, saying it also intended to award a similar contract to EDF. In November, Amentum of the USA was selected to review and advise on the studies submitted by the three potential reactor vendors.

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    Hy2gen aims for 2028 groundbreaking on EU-backed 100MW Danish hydrogen plant

    • June 24, 2026
    Hy2gen aims for 2028 groundbreaking on EU-backed 100MW Danish hydrogen plant

    Renergen secures first offtake for South African helium project

    • June 24, 2026
    Renergen secures first offtake for South African helium project

    California Threatens to Sue Trump Administration Over Offshore Wind Cancellation

    • June 24, 2026
    California Threatens to Sue Trump Administration Over Offshore Wind Cancellation

    Trump Administration, Qatar Say EU Methane Rules Threaten Energy Security

    • June 24, 2026
    Trump Administration, Qatar Say EU Methane Rules Threaten Energy Security

    Video | The role of connected devices in modern hospital gas systems

    • June 24, 2026
    Video | The role of connected devices in modern hospital gas systems

    Poland bank invests €25m in pan-European biomethane fund

    • June 24, 2026
    Poland bank invests €25m in pan-European biomethane fund

    Stegra closes $1.4bn rescue package for green hydrogen-based steel plant

    • June 24, 2026
    Stegra closes $1.4bn rescue package for green hydrogen-based steel plant

    Tanker Owners Are Having the Best Week of the Hormuz Crisis

    • June 24, 2026
    Tanker Owners Are Having the Best Week of the Hormuz Crisis

    Pemex Wants Petrobras’ Deepwater Magic

    • June 24, 2026
    Pemex Wants Petrobras’ Deepwater Magic

    Asian Demand for Mideast Oil Slows after Splurge

    • June 24, 2026
    Asian Demand for Mideast Oil Slows after Splurge