Leak tests completed for Rooppur I’s containment structure

Wednesday, 25 June 2025

Leak tests completed for Rooppur I's containment structure
(Image: Rosatom)

During the process a compressor was used and the pressure was increased to the design value of 4.6kgf/cm2 and a series of tests was carried out to “confirm the tightness of the structure and its ability to withstand internal loads that occur in abnormal conditions”.

Rosatom describes the reactor’s hermetic enclosure as “a physical barrier made of prestressed reinforced concrete with an internal sealing steel lining. It is designed to prevent the release of radioactive substances into the environment in the event of an emergency and to localise them, as well as to protect against possible external influences. The enclosure serves as the last protective barrier in the event of a hypothetical accident”.

Alexey Deriy, vice president for projects in Bangladesh at Atomstroyexport JSC, said: “A number of operations carried out during these tests are unique and are carried out once, only after the full completion of construction and installation work in the reactor building. The results of the tests confirm that the hermetic enclosure system fully complies with all design and regulatory requirements. This is an important step towards commissioning the first power unit and evidence of the high quality of work at all stages of construction.”

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    US uranium production up again

    US mines produced 1,388,000 pounds U3O8 (534 tU) in 2025, up from 677,000 pounds U3O8 in 2024. The 2025 figure was the highest since 2016’s production of 2,545,000 pounds, according…

    Sogin begins re-encapsulation of uranium-thorium fuel

    Between 1968 and 1970, 84 elements of irradiated fuel from the uranium-thorium cycle from the Elk River experimental reactor in Minnesota, USA, were shipped to the Rotondella plant for reprocessing…

    Have You Seen?

    US electricity demand to rise 21% by 2030

    • June 26, 2026
    US electricity demand to rise 21% by 2030

    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    • June 26, 2026
    Oil Set for Hefty Weekly Losses as Tankers Exit Strait of Hormuz

    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    • June 26, 2026
    Trump Clean Energy Tax Credit Cutoff Drives Project Rush as Prices Set to Soar

    Podcast | AI, semiconductor growth & the future of specialty gases

    • June 26, 2026
    Podcast | AI, semiconductor growth & the future of specialty gases

    Will Europe’s new Biomethane Mechanism make a difference?

    • June 26, 2026
    Will Europe’s new Biomethane Mechanism make a difference?

    Sasol, Topsoe to dissolve Zaffra SAF joint venture

    • June 26, 2026
    Sasol, Topsoe to dissolve Zaffra SAF joint venture

    Canada waste-to-energy project grapples with carbon price pressures

    • June 26, 2026
    Canada waste-to-energy project grapples with carbon price pressures

    Australia Awards 15 Battery Storage Projects Under CIS Tender 8, Adding 4.2 GW/16.1 GWh Capacity

    • June 26, 2026
    Australia Awards 15 Battery Storage Projects Under CIS Tender 8, Adding 4.2 GW/16.1 GWh Capacity

    B.Grimm Power Subsidiary Acquires Future Green Tech to Expand Solar Power Portfolio

    • June 26, 2026
    B.Grimm Power Subsidiary Acquires Future Green Tech to Expand Solar Power Portfolio

    Salzgitter Signs Long-Term Green Hydrogen Supply Deal with EWE to Advance Low-Carbon Steel Production

    • June 26, 2026
    Salzgitter Signs Long-Term Green Hydrogen Supply Deal with EWE to Advance Low-Carbon Steel Production