Leak tests completed for Rooppur I’s containment structure

Wednesday, 25 June 2025

Leak tests completed for Rooppur I's containment structure
(Image: Rosatom)

During the process a compressor was used and the pressure was increased to the design value of 4.6kgf/cm2 and a series of tests was carried out to “confirm the tightness of the structure and its ability to withstand internal loads that occur in abnormal conditions”.

Rosatom describes the reactor’s hermetic enclosure as “a physical barrier made of prestressed reinforced concrete with an internal sealing steel lining. It is designed to prevent the release of radioactive substances into the environment in the event of an emergency and to localise them, as well as to protect against possible external influences. The enclosure serves as the last protective barrier in the event of a hypothetical accident”.

Alexey Deriy, vice president for projects in Bangladesh at Atomstroyexport JSC, said: “A number of operations carried out during these tests are unique and are carried out once, only after the full completion of construction and installation work in the reactor building. The results of the tests confirm that the hermetic enclosure system fully complies with all design and regulatory requirements. This is an important step towards commissioning the first power unit and evidence of the high quality of work at all stages of construction.”

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Podcast: World Nuclear Symposium 2026

    People featured, in order of appearance: Sama Bilbao y León, Director General, World Nuclear Association Mark Muldowney, MD, Energy, Resources and Infrastructure, BNP Paribas Alejandro López Delgado, Managing Director, Infrastructure,…

    Hydraulic tests completed at Turkey’s Akkuyu 1

    During the tests, the pressure in the primary circuit (the reactor, main circulation pumps, steam generators, the pressuriser, and the main circulation pipeline connecting them) was increased to 24.5 MPa…

    Have You Seen?

    IEA Members Support Oil Stock Release Acceleration

    • October 11, 2026
    IEA Members Support Oil Stock Release Acceleration

    IEA Members Support Oil Stock Release Acceleration

    • October 10, 2026
    IEA Members Support Oil Stock Release Acceleration

    ACEN Secures €50 Million Loan To Expand Renewable Energy Portfolio

    • October 10, 2026
    ACEN Secures €50 Million Loan To Expand Renewable Energy Portfolio

    Clean Max To Acquire 100% Stake In Thailand’s Massmunch Company For THB 1.25 Million

    • October 10, 2026
    Clean Max To Acquire 100% Stake In Thailand’s Massmunch Company For THB 1.25 Million

    ESCOM Opens Tender For 20 MW/40 MWh Grid-Forming Battery Storage Project In Malawi

    • October 10, 2026
    ESCOM Opens Tender For 20 MW/40 MWh Grid-Forming Battery Storage Project In Malawi

    Offshore Wind And Ocean Energy Offer Small Island Nations A Path To Energy Security – IRENA

    • October 10, 2026
    Offshore Wind And Ocean Energy Offer Small Island Nations A Path To Energy Security – IRENA

    SECI Floats Tender for 120 MW Solar Project with 60 MW/240 MWh Battery Storage in Bihar’s Aurangabad District

    • October 10, 2026
    SECI Floats Tender for 120 MW Solar Project with 60 MW/240 MWh Battery Storage in Bihar’s Aurangabad District

    Crude Oil is Underpriced, Energy Aspects Says

    • October 9, 2026
    Crude Oil is Underpriced, Energy Aspects Says

    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    • October 9, 2026
    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    129 Gulf Platforms Evacuated as Isaias Gets Stronger

    • October 9, 2026
    129 Gulf Platforms Evacuated as Isaias Gets Stronger