Posiva completes backfilling trial run at repository

Friday, 14 March 2025

Posiva completes backfilling trial run at repository
The tunnel filling installation system (Image: Posiva)

At the repository, used fuel will be placed in the bedrock, at a depth of about 430 metres. The disposal system consists of a tightly sealed iron-copper canister, a bentonite buffer enclosing the canister, a tunnel backfilling material made of swellable clay, the seal structures of the tunnels and premises, and the enclosing rock.

The procedure qualification test on backfill installation was designed to demonstrate the operability of the systems and equipment in tunnel conditions at a depth of 435 metres in the bedrock. Another requirement was to achieve the specified result by deploying the operating methods and procedures that will be deployed during operation of the repository.

The minimum goal for the test, which took about three weeks, was to fill at least 10 metres of tunnel. The actual test acceptance criterion was to achieve a tunnel backfill degree of a minimum of 98%. Posiva noted that analyses that are still to be verified indicate that the achieved backfill degree exceeded this criterion.

“The large, long combination machine almost fills the entire tunnel and compacts clay with large screws while pushing it into the tunnel,” said Posiva Development Manager Ari Maarni. “At the same time, it reverses slowly in order to achieve a uniform backfill degree. During the test, the transfer vehicle ran autonomously between the discharge station and the installation machine supplying more clay to the installation machine.”

Maarni noted that the biggest challenges during the test were caused by the uneven floor of the tunnel. “The docking of the transfer vehicle to the installation machine was difficult in points with large surface height differences. This slowed down the work. However, as the test proceeded a lot was learned and we were able to adjust the equipment to operate faster.”

The qualification test was carried out in the 50-metre-long tunnel used for the Trial Run of Final Disposal. The remaining 40 metres of the tunnel will be filled in the actual Trial Run of Underground Operation, before the tunnel is finally sealed.

The next installation procedure qualification tests will focus on testing the buffer installation system as well as the canister transfer and installation vehicle. These installation procedure qualification tests will be carried out as the last ones, and in practice parallel with each other, before the actual underground stage of the Trial Run of Final Disposal.

During the Trial Run, the operation of the complete final disposal facility is tested. Instead of actual used nuclear fuel, the trial run is conducted using non-radioactive test elements.

The Finnish government granted Posiva a construction licence for the project in November 2015 and construction work on the repository started in December 2016. Once it receives the operating licence, Posiva can start the final disposal of the used fuel generated from the operation of TVO’s Olkiluoto and Fortum’s Loviisa nuclear power plants. The operation will last for about 100 years before the repository is closed.

   

  • Related Posts

    KHNP, Southern to cooperate on nuclear engineering

    Under the agreement – signed at KHNP’s headquarters in Gyeongju in South Korea – both companies plan to strengthen their partnership by operating technology exchange programmes, holding workshops, and sharing…

    World Nuclear Fuel Cycle: How best to meet growing demand?

    The first panel of the two-day conference saw industry leaders set the scene, outlining accelerating plans for new nuclear deployment from countries with long-established nuclear programmes to newcomer countries and…

    Have You Seen?

    US Government’s Energy Arm Assumes Strait of Hormuz Will Stay Shut Through Late May

    • May 12, 2026
    US Government’s Energy Arm Assumes Strait of Hormuz Will Stay Shut Through Late May

    US Power Use to Beat Record Highs in 2026 and 2027 as AI Use Surges, EIA Says

    • May 12, 2026
    US Power Use to Beat Record Highs in 2026 and 2027 as AI Use Surges, EIA Says

    Asia’s Major LNG Importers Japan and Korea Turn to Coal

    • May 12, 2026
    Asia’s Major LNG Importers Japan and Korea Turn to Coal

    Brazil’s Oil Exports to China Double as Iran War Upends Crude Flows

    • May 12, 2026
    Brazil’s Oil Exports to China Double as Iran War Upends Crude Flows

    Qatar Asks Vessels at Key LNG Port To Go Dark for Safety

    • May 12, 2026
    Qatar Asks Vessels at Key LNG Port To Go Dark for Safety

    Analysis: Counting the costs of the Middle East crisis

    • May 12, 2026
    Analysis: Counting the costs of the Middle East crisis

    LanzaTech to develop ‘Europe’s first’ ethanol-based SAF facility in Belgium

    • May 12, 2026
    LanzaTech to develop ‘Europe’s first’ ethanol-based SAF facility in Belgium

    Nikkiso signs long-term marine service agreement with Maran Tankers

    • May 12, 2026
    Nikkiso signs long-term marine service agreement with Maran Tankers

    ISS Recommends Shareholders Vote Against Exxon Moving its Registration to Texas

    • May 12, 2026
    ISS Recommends Shareholders Vote Against Exxon Moving its Registration to Texas

    A Trump-Xi Deal Could Revive US Energy Exports to China

    • May 12, 2026
    A Trump-Xi Deal Could Revive US Energy Exports to China